4-Contract Nos. 26-4A,-B,-C,-D ADDENDUM 2.pdf
PDF 845 KB Posted
- Attached to
- PFAS Water Treatment Project Well Nos. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 & 45, Contract No. 26-4
- Solicitation number
- US.255879
- Issued by
- Bucks County, Pennsylvania
About this file
This is Addendum No. 2 to Contract Nos. 26-4A, -B, -C, -D for the PFAS Water Treatment Project serving Warminster Municipal Authority in Bucks County, Pennsylvania, dated September 2026. The project involves the furnishing, construction, and installation of ten (10) pre-purchased Ion Exchange (IX) resin filtration systems across ten well sites (Well Nos. 1, 3, 5, 7, 9, 14, 15, 37, 43/44, and 45) to remove Perfluorinated Compounds (PFOS and PFOA) from groundwater. The scope includes general construction of treatment buildings, electrical construction with service upgrades and instrumentation, mechanical construction (HVAC), and plumbing construction (water, sanitary sewer, and storm sewer systems). The addendum incorporates Appendix B containing pre-purchased IX Resin Treatment Systems specifications from Altair Equipment Co., Inc. and revises Section 18100 pertaining to installation of these systems. The prime contractors are responsible for receiving delivery of system components, unloading and assembling equipment within the constructed buildings, providing all rigging and material handling equipment, and connecting systems to the water supply infrastructure. System components will be delivered in three pieces per well, with approximate weights ranging from 7,920 to 11,120 pounds per well depending on tank size. A pre-bid meeting and site visits were scheduled for October 15, 2026. The project is partially funded through the Military Installation Remediation and Infrastructure Authority (MIRIA) and requires compliance with associated grant requirements.
The Altair proposal totals $2,440,430.00 for eight wells (Nos. 1, 3, 5, 7, 9, 14, 15, 37) and $615,945.00 for two wells (Nos. 43/44, 45), with additional costs for Purolite 694 EBF Resin media and optional installation and start-up support at $8,000 per well. Equipment specifications include double-unit PFOS Resin Filters fabricated from 316 stainless steel with sizes ranging from 66"D x 72" to 84"D x 72" depending on flow rate requirements (200-400 GPM per well). The systems include Allen Bradley PLC controls, Panelview Plus 7 HMI displays, Hoffman NEMA4x enclosures, and manual and automatic valves with differential pressure transmitters. Payment terms are Net 30 with phased installments: 20% deposit upon approval, 30% upon receipt of engineered drawings, 30% upon receipt of major components, 10% upon delivery, and 10% upon startup. Engineering drawings are estimated within four weeks; equipment delivery is estimated at ten to twelve weeks after receipt at Altair's facility, with total estimated delivery of twenty-four to twenty-six weeks after approval of submittals. The purchaser (Warminster Municipal Authority) is responsible for providing all foundations, structural supports, labor for installation, drains and wastewater equipment, interconnecting piping, final painting and insulation, water supply (400 GPM), and electrical service (120 VAC single phase, 60 Hz). Altair provides a two-year limited warranty on mechanical and electrical components and will conduct performance testing and operator training as part of the system supply agreement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARRO CONSULTING, INC. October 9, 2026 Ref: #14005-14011-14037
ADDENDUM NO. 2 – CONTRACT NOS. 26-4A,-B,-C,-D
To the Contract Documents for the “PFAS WATER TREATMENT PROJECT WELL NOS. 1,3,5,7,9,14,15,37,43/44, & 45” for Warminster Municipal Authority, Bucks County, Pennsylvania, dated September 2026, Contract Nos. 26-4A General Construction, 26-4B Electrical Construction, 26-4C Mechanical Construction, 26-4D Plumbing Construction.
This Addendum is hereby made part of the Contract Documents for the “PFAS WATER TREATMENT PROJECT WELL NOS. 1,3,5,7,9,14,15,37,43/44, & 45” for Warminster Municipal Authority, Bucks County, Pennsylvania, dated September 2026, Contract Nos. 26-4A General Construction, 26-4B Electrical Construction, 26-4C Mechanical Construction, 26-4D Plumbing Construction, and includes the following modifications/clarifications:
A. In the Contract Documents, insert Appendix B – Pre-Purchased IX Resin Treatment Systems
B. In the Contract Documents, replace Section 18100 – Installation of Pre-
Purchased IX Resin Treatment Systems in its entirety with the revised Section 18100 – Installation of Pre-Purchased IX Resin Treatment Systems.
ARRO CONSULTING, INC.
APPENDIX B
PRE-PURCHASED IX TREATMENT SYSTEMS
Ferrero, Bradley Typewriter
215-672-9000 | 335 Constance Drive, Warminster, PA 18974 | altairequipment.com
September 23, 2026
Subject: PFOS/PFAS Filter Systems Warminster Municipal Authority PFAS Water Treatment Project – Well No. 1, 3, 5, 7, 9, 14, 15, 37 Altair Proposal # 0225384 COSTAR ID#000571499
Altair offers the following proposal for the referenced project. The double unit PFOS Resin filter systems offered are designed based on CKS Engineers.
The Altair supplied filtration system consists of the following equipment:
• Double Unit 84” x 72” PFOS Resin Filters for Well #’s 9, 37
• Double Unit 72” x 72” PFOS Resin Filters for Well #’s1, 5, 14, 15
• Double Unit 66” x 72” PFOS Resin Filters for Well #s 3, 7
We appreciate the opportunity of submitting this proposal and are confident of providing you with the highest quality equipment and service.
If you should have any questions or require clarification on the information contained in this proposal, please contact:
Altair Equipment Co. Inc.
Voice: 1-215-672-9000 Fax: 215-682-0284 Email: AECO@ALTAIREQUIPMENT.COM
Sincerely, Joseph Kane 215-672-9000 joe_kane@altairequipment.com mailto:AECO@ALTAIREQUIPMENT.COM mailto:joe_kane@altairequipment.com
PFOS Resin Filter System Scope
The system proposed is comprised of three different diameter double unit resin filters used for ion exchange for the eight wells detailed in the RFQ. The system proposed for Wells 9 and 37 have an identical process design but consists of 84”D x 72” tanks and 4” process pipe and valves. Wells 1, 5, 14, and 15 will have the same process design but the tank sizes will be 72”D x 72” for the approximately 300 GPM flow rate needed. The last two wells, designed for the lowest flow rate of 200 GPM will be 66”D x 72” and maintain the process design. Each system as proposed will be manufactured with validated domestic 316 stainless steel and supplied with schedule 80 PVC pipe and manual valves.
The systems shall be used for the removal of Perfluorated Compounds (PFOS and PFOA) which are present in the groundwater being extracted from the Warminster Authority wells operated under the conditions noted in CKS Engineers Specification.
The Contractor will be responsible for installation of the new systems. Altair will provide, as an option,media and manpower pricing to fill the vessels. Start-up support is optional also.
Filter Operation
The filters can operate in a Lead/Lag or parallel configuration. Control of the filters will be by others.
Filter System Specifications – Per Well
Vessels Quantity Material Design Pressure Design Temperature
Wells 9 and 37 Diameter Straight Side
Wells 1,5,14,15
Wells 3,7
Manways Side Top Sight Glass Vessel Supports
Two (2) Vessels 316 Stainless Steel ASTM 312
150 PSIG ASME CODE
100 DEG. F
84” 72”
66”
24" Diameter Davited 14” x 18” None Structural Stainless Steel Legs
Media – Quoted Separately Quantity 220 Ft3/ 84” Vessel x4 880 Ft3
160 Ft3/ 72” Vessel x8 1280 Ft3 130 Ft3/ 66” Vessel x4 520 Ft3
2680 Ft3
Filter Systems Specification
INTERNALS
Inlet Distributor Under Drain Header Support Bars
PIPING & FITTINGS
PIPE STAND AND TREE
MANUAL VALVES
Butterfly Ball
AUTOMATIC VALVES
INSTRUMENTS
Enclosure
PLC
HMI
DP Transmitter
CARTRIDGE PRE- FILTER
MISCELLANEOUS
Air Vent Valves Drawings Manuals/Documentation
316 Stainless Steel Header/Lateral 316 SS Header/Lateral/Drop Leg Strainer 316 Stainless Steel
Schedule 80 PVC
Class 150B, 316 internals Delta T w/positioners
NONE
Hoffman NEMA4x
Allen Bradley CompactLogix L33ER
Allen Bradley Panelview Plus7
Dwyer 3100
Shelco Stainless Steel Pre-filters 22FOS 84” tanks -12FOS Series 72” & 66” tanks
Qty 2 – APCO Series 145c
(6) Sets of Complete Shop Drawings,
(6) Copies of manufacturer’s installation, operation and maintenance manuals, bulletins, and spare parts list, materials of construction, manufacturer’s catalog data, operating literature, specifications, performance data, power usage
INSTRUMENT SCOPE
A Hoffman NEMA4x enclosure will be mounted on the skid between the two vessels. Cables will be run from the valve-mounted limit switches back to the enclosure. The cables will be terminated on terminal blocks inside the enclosure before being routed to the AB CompactLogix L33ER PLC. The feedback from the limit switches will be displayed on a 10” AB Panelview Plus 7 HMI. On the HMI display, piping between limit switches will be highlighted to show the flowpath through the system. A dry contact will be made available in the cabinet that will allow for the control of a pump (pump to be provided by others) provided that a complete flow path is available through the system.
PURCHASER TO FURNISH
• All foundations and structural supports necessary for installation of the new equipment
• All labor as required to unload, receive, and install new equipment in customer supplied enclosure
• All drains, sumps, and waste water equipment
• All ladders, stairs, and walkways
• All interconnecting piping between equipment furnished by AECo, and existing equipment
• All final painting and insulation
• 400 GPM inlet water supply
• 120 VAC, single phase, 60 HZ electric for control panels
• Operation of all equipment in accordance with AECo operating instructions
• All interconnecting electrical and components / labor as required
• Applicable sales tax exemption certificate, if any.
TERMS AND CONDITIONS
Price Validity: All prices are valid for 45 days from the date of this proposal.
Taxes: Prices in this proposal do not include use, sales or similar type taxes that may be imposed on the Purchaser by local laws.
FOB Point: The prices in this proposal are quoted FOB shipping point. All shipping charges will be added to the final invoice.
Warranty: AECo. will provide a Two (2) year limited warranty on all mechanical and electrical components supplied.
Field Service: Unless noted otherwise in this proposal, the prices in this proposal do not include field or start-up services.
Engineering Drawings: Altair Engineering Drawings (if required) will be furnished in AutoCad 2025. Hard copy prints of AECo Drawings will be furnished on 11” x 17” format.
PRICING
DU PFOS Resin Filter Systems Wells 9, 37 $323,915.00 per well DU PFOS Resin Filter Systems Wells 1, 5,14,15 $302,135.00 per well DU PFOS Resin Filter Systems Wells 3,7 $292,030.00 per well
TOTAL $2,440,430.00
Purolite 694 EBF Resin $437.75 per cubic foot x 2680
Installation of Media and Start-up Support by Altair per well
$1,173,170.00 $8000.00 per well
PAYMENT TERMS: NET30 TERMS
20% Deposit ARO $488086.00 30% With Receipt of Engineered Drawings $732129.00 30% On Receipt of Major Components $732129.00 10% 10%
On Delivery On Startup
$244043.00 $244043.00
DELIVERY
ENGINEERING DRAWINGS: Four (4) weeks after receipt of order
Equipment: Ten (10) to Twelve (12) weeks after receipt of tanks at Altair yard.
Total Estimated Delivery: Twenty (24) to Twenty-Two (26) weeks after approval of Altair Submittals.
215-672-9000 | 335 Constance Drive, Warminster, PA 18974 | altairequipment.com
September 23, 2026
Subject: PFOS/PFAS Filter Systems Warminster Authority PFAS Water Treatment Project – Well No. 43/44, 45 Altair Proposal # 0325424 COSTARS ID# 0000571499
Altair offers the following proposal for the referenced project. The double unit PFOS Resin filter system offered is designed based on CKS Engineers.
The Altair supplied filtration system consists of the following equipment:
• Floor mounted Double Unit 84” x 72” PFOS Resin Filters for Well # 43/44
• Floor Mounted Double Unit 66” x 72” PFOS Resin Filters for Well #45
We appreciate the opportunity of submitting this proposal and are confident of providing you with the highest quality equipment and service.
If you should have any questions or require clarification on the information contained in this proposal, please contact:
Altair Equipment Co. Inc.
Voice: 1-215-672-9000 Fax: 215-682-0284 Email: AECO@ALTAIREQUIPMENT.COM
Sincerely, Joseph Kane 215-672-9000 joe_kane@altairequipment.com mailto:AECO@ALTAIREQUIPMENT.COM mailto:joe_kane@altairequipment.com
PFOS Resin Filter System Scope
The system proposed for Well 43/44 is comprised of 84”D x 72” double unit resin filters for ion exchange for the well detailed in the RFQ. This equipment is designed for the highest flow rate of 400 GPM maintaining the process design.
The system proposed for Well 45 is comprised of 66”D x 72” double unit resin filters used for ion exchange for the well detailed in the RFQ. This equipment is designed for the lowest flow rate of 200 GPM which will maintain the process design. These two systems as proposed will be manufactured with validated domestic 316 stainless steel, schedule 80 PVC pipe and manual valves.
The systems shall be used for the removal of Perfluorated Compounds (PFOS and PFOA) which are present in the groundwater being extracted from the indicated Warminster Authority well operated under the conditions noted in CKS Engineers Specification.
The Contractor will be responsible for installation of the new system. Altair will provide, as an option, supply of media and manpower to fill the vessels. Start-up support is optional also.
Filter Operation
The filter can operate in a Lead/Lag or parallel configuration. Control of the filter will be by others.
Filter System Specifications – Per Well
Vessels Quantity Material Design Pressure Design Temperature Well 43/44 Diameter Straight Side Well 45 Diameter Straight Side Manways Side Top Sight Glass Vessel Supports
Two (2) Vessels 316 Stainless Steel ASTM 312
150 PSIG ASME CODE
100 DEG. F
84”
66”
24" Diameter Davited Manway 14” x 18” None 316 Structural Stainless Steel Legs
Media – Quoted Separately Quantity 130 Ft3/ 66” Vessel x 2 260 Ft3
220 Ft3/84” Vessel x 2 440 Ft3
Filter Systems Specification
INTERNALS
Inlet Distributor Under Drain Header Support Bars
316 Stainless Steel Header/Lateral 316 SS Header/Lateral/Drop Leg Strainer 316 Stainless Steel
Class 150B, 316 internals Delta T w/positioners
NONE
Hoffman NEMA4x
Allen Bradley CompactLogix L33ER
Allen Bradley Panelview Plus7
Shelco 12FOS Stainless Steel Pre-filter 72” & 66” Shelco 22FOS Stainless Steel Pre-filter 84” tank
Dwyer 3100
Qty 2 – APCO Series 145c
(6) Sets of Complete Shop Drawings,
(6) Copies of manufacturer’s installation, operation and maintenance manuals, bulletins, and spare parts list, materials of construction, manufacturer’s catalog data, operating literature, specifications, performance data, power usage
PIPING & FITTINGS
PIPE STAND AND TREE
MANUAL VALVES
Butterfly Ball
AUTOMATIC VALVES
INSTRUMENTS
Enclosure
PLC
HMI
CARTRIDGE PRE-
FILTER
Differential Pressure Transmitter
MISCELLANEOUS
Air Vent Valves Drawings Manuals/Documentation
INSTRUMENT SCOPE
A Hoffman NEMA4x enclosure will be mounted on the skid between the two vessels. Cables will be run from the valve-mounted limit switches back to the enclosure. The cables will be terminated on terminal blocks inside the enclosure before being routed to the AB CompactLogix L33ER PLC. The feedback from the limit switches will be displayed on a 10” AB Panelview Plus 7 HMI. On the HMI display, piping between limit switches will be highlighted to show the flowpath through the system. A dry contact will be made available in the cabinet that will allow for the control of a pump (pump to be provided by others) provided that a complete flow path is available through the system.
PURCHASER TO FURNISH
• All foundations and structural support necessary for installation of the new equipment
• All labor as required to unload, receive, and install new equipment in customer supplied enclosure
• All drains, sumps, and wastewater equipment
• All ladders, stairs, and walkways
• All interconnecting piping between equipment furnished by AECO and existing equipment
• All final painting and insulation
• 400 GPM inlet water supply
• 120 VAC, single phase, 60 HZ electric for control panels
• Operation of all equipment in accordance with AECO operating instructions
• All interconnecting electrical and components / labor as required
• Applicable sales tax exemption certificate, if any.
TERMS AND CONDITIONS
Price Validity: All prices are valid for 30 days from the date of this proposal.
Taxes: Prices in this proposal do not include use, sales or similar type taxes that may be imposed on the Purchaser by local laws.
FOB Point: The prices in this proposal are quoted fob shipping point. All shipping charges will be added to the final invoice.
Warranty: AECo. will provide a Two (2) year limited warranty on all mechanical and electrical components supplied.
Field Service: Unless noted otherwise in this proposal, the prices in this proposal do not include field or start-up services.
Engineering Drawings: Altair Engineering Drawings (if required) will be furnished in AutoCad 2025. Hard copy prints of AECo Drawings will be furnished on 11” x 17” format.
PRICING
DU PFOS Resin Filter Systems Well 43/44 $323,915.00 DU PFOS Resin Filter Systems Well 45 $292,030.00
TOTAL $615,945.00
Purolite 694EBF Resin $437.75 per cubic foot x 700 $306,425.00 Installation of Media and Start-up Support by Altair $8000.00 per well
PAYMENT TERMS: Net 30 Terms
20% Deposit ARO $123,189.00 30% On Receipt of Engineered Drawings $184,783.50 30% On Receipt of Major Components $184,783.50 10% On Delivery $61,594.50 10% On Startup $61,594.50
DELIVERY
ENGINEERING DRAWINGS: Four (4) weeks after receipt of order
EQUIPMENT: Ten (10) to Twelve (12) weeks after receipt of tanks at Altair yard.
ESTIMATED DELIVERY: Twenty (24) to Twenty-Two (26) weeks after approval of Altair Submittals.
SECTION 08100 – INSTALLATION OF PRE-PURCHASED IX RESIN TREATMENT SYSTEMS
18100-1
SECTION 18100 – INSTALLATION OF PRE-PURCHASED IX RESIN TREATMENT
SYSTEMS
PART 1 - GENERAL
1.1 SCOPE
A. Description of Work
1. Provide all labor, material, supplies, and equipment to take delivery of, and install ten (10) Ion Exchange Resin (IX) Filtration Systems.
The ten (10) systems will be pre-purchased by the Warminster Municipal Authority. Submittal information of the systems will be provided to the Prime Contractors.
B. Labor and Components Included
1. The Prime Contractors shall construct the buildings required to contain the IX Filtration Systems in accordance with the Contract Plans and Specifications. The General Contractor shall be responsible to schedule and coordinate all required work in preparation for accepting delivery of the IX Filtration Systems, and the installation of the system.
2. The Prime Contractors will be provided with the anticipated shipment date of the equipment to the building sites. Once this date is known, the Prime Contractors shall revise their project schedules accordingly. The General Contractor shall be responsible for taking delivery of the IX Filtration Systems. This shall include off-loading the system components from the delivery truck, and placement and assembly of the delivered system components within the buildings at the location shown on the Construction Plans. The General Contractor shall provide all equipment required to handle the IX Filtration Systems, including all rigging, cranes, forklift trucks, or any other pieces of equipment necessary to unload and place the system, in accordance with the manufacturer’s requirements.
3. The Prime Contractors shall assume that the IX Filtration Systems shall each be delivered in three (3) pieces consisting of the two (2) vessels, and one pipe stand on the frame/skid. The approximate weight of the system components are as follows:
84” x 72” Tanks Each – 5,560lbs with nozzles, internals, and round manway (11,120lbs / well)
18100-2
72” x 72” Tanks Each – 4,470lbs with nozzles, internals, and round manway (8,940lbs / well)
66” x 72” Tanks Each – 3,960lbs with nozzles, internals, and round manway (7,920lbs / well)
Each valve skid with frame, PLC cabinet, and valves/piping.
(2,040lbs)
4. The contract drawings show the layout of the IX system based on the system supplier’s equipment (Altair). Contractor shall make any minor adjustments to the piping layout that are required for a complete installation. These adjustments shall be at no additional cost to the Authority.
1.2 IX SYSTEM MANUFACTURER’S RESPONSIBILITY
A. As part of their contract, the system supplier will provide initial installation guidance, start-up assistance, and performance testing. System supplier will also be responsible to install the ion exchange resin media in the filter vessels after the vessels are set in place and the system is fully assembled.
B. Installation Assistance
System supplier shall provide installation guidance to the Prime Contractors to assist in the proper assembly of the IX Filtration Systems.
C. Operating Instructions and/or Operator Training
System supplier shall provide services to instruct contractors and
Warminster Municipal Authority (WMA) personnel on the proper operation of the treatment systems.
D. Performance Testing
System suplier shall perform all required performance testing included as part of their agreement with the WMA on the supply of the IX Filtration System.
PART 2 – PRODUCTS
2.1 GENERAL
A. The Prime Contractors shall install the IX Filtration System at the locations shown on the Construction Plans. The specifics of the system are
18100-3 included as an exhibit to these Contract Documents. Contractors shall fully understand what is included in the Filtration Systems and what will be required for installation and connection to the WMA water system.
2.2 CONTRACTORS’ RESPONSIBILITY
Contractors shall provide and install all piping, valves, fittings, specified components, supports, anchors, etc., required to connect the supplied IX Filtration Systems to the WMA well supply system as shown on the Contract Drawings. Contractors shall provide any and all components not provided by the equipment supplier in order to provide a completed functioning IX Filtration Treatment System.
PART 3 – EXECUTION
3.1 INSTALLATION
A. The Contractor shall install the ten (10) IX Filtration Systems as shown on the contract drawings.
B. The Contractor shall install the equipment as shown on the drawings and in accordance with the system suppliers equipment submittal once it is received and provided to the Prime contractors.
C. Equipment shall be installed in accordance with GENERAL MECHANICAL
REQUIREMENTS, and in accordance with the Manufacturer’s recommendations to provide a complete installation.
D. Testing. System supplier is required to perform performance testing on the IX Filtration Systems prior to placing the systems in active service in the WMA water supply system. The Contractor shall provide assistance as required to provide this testing.
E. Contractors shall clean all vessels and exposed piping to remove any dirt, dust, etc., as a result of the construction work.
END OF SECTION