3-Contract Nos. 26-4A,-B,-C,-D ADDENDUM 1.pdf
PDF 1 MB Posted
- Attached to
- PFAS Water Treatment Project Well Nos. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 & 45, Contract No. 26-4
- Solicitation number
- US.255879
- Issued by
- Bucks County, Pennsylvania
About this file
This Addendum No. 1, issued by ARRO CONSULTING, INC. on October 8, 2026, modifies the contract documents for the PFAS Water Treatment Project for the Warminster Municipal Authority in Bucks County, Pennsylvania. The project encompasses furnishing, construction, and installation of new Ion Exchange (IX) resin filtration systems at ten well sites (Well Nos. 1, 3, 5, 7, 9, 14, 15, 37, 43/44, and 45), along with general construction of treatment buildings, electrical upgrades, mechanical HVAC systems, and plumbing work across all sites. Four separate contracts were issued: Contract No. 26-4A for General Construction, 26-4B for Electrical Construction, 26-4C for Mechanical Construction (HVAC), and 26-4D for Plumbing Construction. A pre-bid site meeting was scheduled for October 15, 2026, with bidders advised to inspect sites prior to submission. The addendum extends the construction period from the original timeframe to 540 calendar days from the date of Notice to Proceed, with work to commence within seven calendar days of that notice.
The addendum makes six substantive modifications to the contract documents, including removal of references to a Borough and Well 17, updated equipment/material manufacturer specifications on page FOP-32, incorporation of Warminster Municipal Authority's Third Amended Responsible Contractor Resolution No. 24-1 requiring journeyperson workers with Class A Apprenticeship completion or registered apprentices for craft labor, and revised performance and maintenance bond pages. Liquidated damages are assessed at $250 per calendar day for project delays, with total combined penalties not to exceed $2,000 per day; the Authority may seek injunctive relief after 30 days of overrun and may dismiss the contractor after 60 days of overrun. The project is partially funded through the Military Installation Remediation and Infrastructure Authority (MIRIA) grant and an agreement with the United States Navy, requiring compliance with associated grant requirements. All bids must include lump sum or unit prices, with substitutions to base bid equipment manufacturers permitted only if listed on specified pages and subject to Authority approval after award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARRO CONSULTING, INC. October 8, 2026 Ref: #14005-14011-14037
ADDENDUM NO. 1 – CONTRACT NOS. 26-4A,-B,-C,-D
To the Contract Documents for the “PFAS WATER TREATMENT PROJECT WELL NOS. 1,3,5,7,9,14,15,37,43/44, & 45” for Warminster Municipal Authority, Bucks County, Pennsylvania, dated September 2026, Contract Nos. 26-4A General Construction, 26-4B Electrical Construction, 26-4C Mechanical Construction, 26-4D Plumbing Construction.
This Addendum is hereby made part of the Contract Documents for the “PFAS WATER TREATMENT PROJECT WELL NOS. 1,3,5,7,9,14,15,37,43/44, & 45” for Warminster Municipal Authority, Bucks County, Pennsylvania, dated September 2026, Contract Nos. 26-4A General Construction, 26-4B Electrical Construction, 26-4C Mechanical Construction, 26-4D Plumbing Construction, and includes the following modifications/clarifications:
A. In the Contract Documents, replace Page FOP-32 with the revised Page FOP-
32. Removes reference to the Borough.
B. In the Contract Documents, replace Page FOP-35 with the revised Page FOP-
35. The construction period has been extended to 540 days.
C. In the Contract Documents, replace Pages A-A-2, A-B-2, A-C-2, and A-D-2 with the revised Pages A-A-2, A-B-2, A-C-2, and A-D-2. The construction period has been extended to 540 days.
D. In the Contract Documents, replace BQS-1 with the revised BQS-1. Revised to reference Warminster Municipal Authority’s Third Amended Responsible Contractor Resolution No. 24-1.
E. In the Contract Documents, replace Pages PMB-A-2, PMB-B-2, PMB-C-2, and PMB-D-2 with the revised Pages PMB-A-2, PMB-B-2, PMB-C-2, and PMB-D-2. Removes reference to a Well 17.
F. In the Contract Documents, replace Pages LMP-A-2, LMP-B-2, LMP-C-2 and
LMP-D-2 with the revised Pages LMP-A-2, LMP-B-2, LMP-C-2 and LMP-D-2.
Removes reference to a Well 17.
FOP-32
DETERMINATION OF BASE BID AMOUNT
MAJOR EQUIPMENT/MATERIAL MANUFACTURERS
Base Bid: Only the acceptable equipment/material manufacturers listed below shall be used in determining the BASE BID amount under this Contract. The Contractor shall utilize the products/equipment of the acceptable Base Bid equipment/material manufacturers listed on Page FOP-33 as the basis of the Base Bid Cost Proposal.
Substitution: Substitutions to the Base Bid equipment/material manufacturers listed on Page FOP-33 may be considered by the Authority after award. If the bidder desires to propose a substitution to the acceptable Base Bid equipment/material manufacturer, said substitute equipment/material manufacturer must be listed on Page FOP-33.
Prospective bidders are advised that the Authority may select any or all of the substitutions listed in the tabulation on Page FOP-33 after a contract is awarded. If the Authority selects any substitutions, the undersigned agrees to furnish and install the substitution(s) listed for the price adjustment indicated on Page FOP-33. The BASE BID amount will then be adjusted accordingly.
If a substitute bid proposal includes items of equipment/material of any manufacturer which may require any modification or deviation from the Contract Documents, the undersigned agrees to prepare and submit detailed drawings to the Engineer showing all modifications in structures, piping, electrical and mechanical work required to adapt the Contract Documents to the proposed substitute equipment/material. Prospective bidders are advised that the Engineer will review said detailed drawings of modifications and either approve them or indicate thereon changes necessary to comply with the project requirements. Detailed drawings which are not approved will be revised then resubmitted to the Engineer. The prices listed in the following tabulation are "installed" prices and take into consideration any of the changes that may be required.
ARRO CONSULTING, INC.
FOP-35
undersigned further agrees to complete fully all work covered by the proposal to the point of final acceptance by the Authority within five hundred forty (540) calendar days after the date of said "Notice to Proceed." Should Contractor fail to complete all work or any part of the work by the specified completion date, then the Authority shall assess a liquidated penalty in the amount of two hundred fifty dollars ($250) per calendar day for each day the project remains incomplete. In addition to the liquidated penalty, Contractor shall be liable for all costs and fees incurred by the Authority, due to the overrun. These costs and fees include, but are not limited to, legal fees, engineering fees, inspection fees, insurance costs, administrative costs, interest and debt service charges. The total cost of the liquidated penalty and the additional incurred costs shall not exceed $2,000 per day. Should the overrun last thirty (30) days, then the Authority shall be entitled to obtain, from a Court of competent jurisdiction, injunctive or other equitable relief restraining Contractor from entering into any new contracts or beginning any new projects until the project which it undertook for the Authority is fully completed. Contractor shall be liable to the Authority for any and all monies spent in obtaining said injunction including, but not limited to, attorney's and engineer's fees.
Additionally, should the overrun last sixty (60) days, then the Authority, upon five (5) days' written notice, may dismiss Contractor. Should the Authority dismiss Contractor pursuant to this Agreement, then the Contractor shall indemnify the Authority for all costs incurred including, but not limited to, the costs and fees of retaining a new contractor.
The undersigned understands and agrees that the General Manager has the right to defer issuance of a "Notice to Proceed" for a period not to exceed thirty (30) days after the date of execution of the Agreement.
Payment for all work called for on the Contract Drawings and in the Construction Specifications or required for proper completion of the work under this Contract and not specifically mentioned in the Construction Specifications or noted on the Contract Drawings, will be considered as covered by the lump sum or unit prices, and no extra payments will be allowed therefore.
The undersigned certifies this proposal is in all respects genuine and not sham or collusive, nor made in the interest or in the behalf of any person, firm or corporation not herein named, and that there has been no attempt on the part of the undersigned by collusion to secure an advantage over any other bidder. The bidder must submit an executed copy of the NON-COLLUSION AFFIDAVIT which is attached hereto these Contract Documents in conjunction with this proposal.
The undersigned acknowledges receipt of the following addenda to the Contract
Documents:
ADDENDUM
DATED
A-A-2
The work on the Contract is to commence within seven (7) calendar days from the date of the “Notice to Proceed.” Work on any wellhouse to be diligently brought to completion within five hundred forty (540) calendar days from the “Notice to Proceed”. Should the
Contractor fail to complete all work or any part of the work by the specified completion date, then the Authority shall assess a liquidated penalty in the amount of two hundred fifty dollars
($250) per calendar day for each day the project remains incomplete. In addition to the liquidated penalty, the Contractor shall be liable for all costs and fees incurred by the
Authority, due to the overrun. These costs and fees include, but are not limited to, legal fees, engineering fees, inspection fees, insurance costs, administrative costs, interest and debt service charges. The total cost of the liquidated penalty and the additional incurred costs shall not exceed $2,000 per day. Should the overrun last thirty (30) days, then the Authority shall be entitled to obtain, from a Court of competent jurisdiction, injunctive or other equitable relief restraining the Contractor from entering into any new contracts or beginning any new projects until the project which it undertook for the Authority is fully completed. The
Contractor shall be liable to the Authority for any and all monies spent in obtaining said injunction including, but not limited to, attorney's fees. Additionally, should the overrun last sixty (60) days, then the Authority, upon five (5) days written notice, may dismiss the
Contractor. Should the Authority dismiss the Contractor pursuant to this agreement, then the Contractor shall indemnify the Authority for all costs incurred including, but not limited to, the costs and fees of retaining a new contractor.
To prevent all disputes and litigations, it is agreed by and between the parties of this
Contract that the Engineer, subject to final approval of the Warminster Municipal Authority, shall, in all cases, determine the quality and quantity of the several kinds of work and materials
A-B-2 of the “Notice to Proceed.” Work on any wellhouse to be diligently brought to completion within five hundred forty (540) calendar days from the “Notice to Proceed”. Should the
Contractor fail to complete all work or any part of the work by the specified completion date, then the Authority shall assess a liquidated penalty in the amount of two hundred fifty dollars
($250) per calendar day for each day the project remains incomplete. In addition to the liquidated penalty, the Contractor shall be liable for all costs and fees incurred by the
Authority, due to the overrun. These costs and fees include, but are not limited to, legal fees, engineering fees, inspection fees, insurance costs, administrative costs, interest and debt service charges. The total cost of the liquidated penalty and the additional incurred costs shall not exceed $2,000 per day. Should the overrun last thirty (30) days, then the Authority shall be entitled to obtain, from a Court of competent jurisdiction, injunctive or other equitable relief restraining the Contractor from entering into any new contracts or beginning any new projects until the project which it undertook for the Authority is fully completed. The
Contractor shall be liable to the Authority for any and all monies spent in obtaining said injunction including, but not limited to, attorney's fees. Additionally, should the overrun last sixty (60) days, then the Authority, upon five (5) days written notice, may dismiss the
Contractor. Should the Authority dismiss the Contractor pursuant to this agreement, then
A-C-2 of the “Notice to Proceed.” Work on any wellhouse to be diligently brought to completion within five hundred forty (540) calendar days from the “Notice to Proceed”. Should the
Contractor fail to complete all work or any part of the work by the specified completion date, then the Authority shall assess a liquidated penalty in the amount of two hundred fifty dollars
($250) per calendar day for each day the project remains incomplete. In addition to the liquidated penalty, the Contractor shall be liable for all costs and fees incurred by the
Authority, due to the overrun. These costs and fees include, but are not limited to, legal fees, engineering fees, inspection fees, insurance costs, administrative costs, interest and debt service charges. The total cost of the liquidated penalty and the additional incurred costs shall not exceed $2,000 per day. Should the overrun last thirty (30) days, then the Authority shall be entitled to obtain, from a Court of competent jurisdiction, injunctive or other equitable relief restraining the Contractor from entering into any new contracts or beginning any new projects until the project which it undertook for the Authority is fully completed. The
Contractor shall be liable to the Authority for any and all monies spent in obtaining said injunction including, but not limited to, attorney's fees. Additionally, should the overrun last sixty (60) days, then the Authority, upon five (5) days written notice, may dismiss the
Contractor. Should the Authority dismiss the Contractor pursuant to this agreement, then
A-D-2 of the “Notice to Proceed.” Work on any wellhouse to be diligently brought to completion within five hundred forty (540) calendar days from the “Notice to Proceed”. Should the
Contractor fail to complete all work or any part of the work by the specified completion date, then the Authority shall assess a liquidated penalty in the amount of two hundred fifty dollars
($250) per calendar day for each day the project remains incomplete. In addition to the liquidated penalty, the Contractor shall be liable for all costs and fees incurred by the
Authority, due to the overrun. These costs and fees include, but are not limited to, legal fees, engineering fees, inspection fees, insurance costs, administrative costs, interest and debt service charges. The total cost of the liquidated penalty and the additional incurred costs shall not exceed $2,000 per day. Should the overrun last thirty (30) days, then the Authority shall be entitled to obtain, from a Court of competent jurisdiction, injunctive or other equitable relief restraining the Contractor from entering into any new contracts or beginning any new projects until the project which it undertook for the Authority is fully completed. The
Contractor shall be liable to the Authority for any and all monies spent in obtaining said injunction including, but not limited to, attorney's fees. Additionally, should the overrun last sixty (60) days, then the Authority, upon five (5) days written notice, may dismiss the
Contractor. Should the Authority dismiss the Contractor pursuant to this agreement, then
BQS-1
BIDDER'S QUALIFICATION STATEMENT
This document must be included as part of the bid submission. In addition, Bidder must submit a fully executed Contractor/Subcontractor Responsibility Certification Form contained in these Contract Documents which certifies that the Contractor and Subcontractors meet the requirements of Warminster Municipal Authority’s Third Amended Responsible Contractor Resolution No. 24-1. As a result, journeyperson worker(s) who have successfully completed a Class A Apprenticeship Program, or apprentices registered in such a program for craft labor, are required to construct these components of the project. Third Amended Resolution No. 24-1 is contained in these Contract Documents. Failure to submit a fully completed and executed Bidder’s Qualification Statement and Contractor/Subcontractor Responsibility Certification Form may be considered justification for rejection of the bid.
This Bidder's Qualification Statement is submitted with respect to the following project:
PFAS WATER TREATMENT PROJECT
WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45
CONTRACT NO. 26-4A – GENERAL CONSTRUCTION
CONTRACT NO. 26-4B – ELECTRICAL CONSTRUCTION
CONTRACT NO. 26-4C – MECHANICAL CONSTRUCTION (HVAC)
CONTRACT NO. 26-4D – PLUMBING CONSTRUCTION
The undersigned certifies, under oath, the truth and correctness of all statements and of all answers to questions made hereinafter.
TO: PROJECT OWNER
Warminster Municipal Authority 415 Gibson Avenue Warminster, Pennsylvania 18974
Submitted by: Corporation
Name: Partnership
Address: Individual
Principal: Joint Venture
Other
1. Number of years your organization has been in business as a contractor.
2. Number of years your organization has been engaged in construction work of the type proposed under this Contract.
PMB-A-2
for maintenance as designated in Paragraph "B" below; lawful money of the United States of
America, to be paid to
WARMINSTER MUNICIPAL AUTHORITY or its agents, to which payment well and truly to be made and done, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
Sealed with our respective seals and dated this day of
20 .
WHEREAS, the above bounded Principal is about to enter into a Contract with
WARMINSTER MUNICIPAL AUTHORITY dated the day of , 20 for the construction of PFAS WATER TREATMENT PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4A – GENERAL CONSTRUCTION, upon certain terms and conditions in said Contract more particularly mentioned; and
WHEREAS, it is one of the conditions of the award of PFAS WATER TREATMENT
PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4A –
GENERAL CONSTRUCTION, that these presents be executed.
WHEREAS, this bond is given pursuant to the requirements of Act of the General
Assembly of the Commonwealth of Pennsylvania approved December 20, 1967, Act 385, known as the "Public Works Contractors' Bond Law of 1967."
PMB-B-2
20 for the construction of PFAS WATER TREATMENT PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4B – ELECTRICAL CONSTRUCTION, PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4B –
ELECTRICAL CONSTRUCTION, that these presents be executed.
PMB-C-2
20 for the construction of PFAS WATER TREATMENT PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4C – MECHANICAL
CONSTRUCTION (HVAC), upon certain terms and conditions in said Contract more particularly mentioned; and
PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4C –
MECHANICAL CONSTRUCTION (HVAC), that these presents be executed.
PMB-D-2
20 for the construction of PFAS WATER TREATMENT PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4D – PLUMBING CONSTRUCTION, PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37, 43/44 AND 45, CONTRACT NO. 26-4D –
PLUMBING CONSTRUCTION, that these presents be executed.
LMP-A-2
WARMINSTER MUNICIPAL AUTHORITY, Obligee for
PFAS WATER TREATMENT PROJECT, WELL NOS. 1, 3, 5, 7, 9, 14, 15, 37,
43/44 AND 45, CONTRACT NO. 26-4A, GENERAL CONSTRUCTION, pursuant of an award of said Contract to Principal on the date hereof, and
WHEREAS, this bond is given pursuant to the requirements of the Act of the
General Assembly of the Commonwealth of Pennsylvania, approved December 20, 1967, Act 385, known as the "Public Works Contractors' Bond Law of 1967."
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said
(Contractor - Principal) shall promptly make payment of all material furnished and labor supplied or performed in the prosecution of the work, whether or not the said material and labor enter into and become component parts of the work or improvement contemplated, then this obligation shall be void, otherwise it shall remain in full force and effect.
The said Principal and Surety, jointly or severally, further covenant and agree that every claimant (person, firm, partnership, co-partnership, association or corporation, except as hereinafter provided), who, whether a subcontractor or otherwise, has furnished material or supplied or performed labor in the prosecution of the work provided for in the
Contract for which this bond has been given, and who has not been paid in full therefor before the expiration of ninety (90) days after the date on which such claimant performed
LMP-B-2
43/44 AND 45, CONTRACT NO. 26-4B, ELECTRICAL CONSTRUCTION, pursuant of an award of said Contract to Principal on the date hereof, and
(Contractor - Principal) shall promptly make payment of all material furnished and labor supplied or performed in the prosecution of the work, whether or not the said material and labor enter into and except as hereinafter provided), who, whether a subcontractor or otherwise, has furnished material or supplied or performed labor in the prosecution of the work provided for in the
LMP-C-2
43/44 AND 45, CONTRACT NO. 26-4C, MECHANICAL CONSTRUCTION (HVAC),
pursuant of an award of said Contract to Principal on the date hereof, and
(Contractor - Principal) shall promptly make payment of all material furnished and labor supplied or performed in the prosecution of the work, whether or not the said material and labor enter into and except as hereinafter provided), who, whether a subcontractor or otherwise, has furnished material or supplied or performed labor in the prosecution of the work provided for in the
LMP-D-2
43/44 AND 45, CONTRACT NO. 26-4D, PLUMBING CONSTRUCTION, pursuant of an award of said Contract to Principal on the date hereof, and
(Contractor - Principal) shall promptly make payment of all material furnished and labor supplied or performed in the prosecution of the work, whether or not the said material and labor enter into and except as hereinafter provided), who, whether a subcontractor or otherwise, has furnished material or supplied or performed labor in the prosecution of the work provided for in the
File details come from the government source that posted it. Updated .