This document is a Bid Form for Construction Services from Halifax Health Medical Center (HHMC) for project PROJ-25-131, specifically a Chiller Replacement for HHPO. The bid requires contractors to submit a comprehensive proposal that includes a detailed project schedule/timeline, a Schedule of Values broken down by division, and a detailed work description demonstrating full understanding of the project scope. Bidders must provide their total project cost and commit to completing the work within a schedule to be reviewed and approved by HHMC. The bid must remain open for acceptance for 120 days from the bid due date.

The bid form outlines specific requirements for contractors, including responsibility for any facility repairs resulting from trucks traveling outside designated routes. Bidders must provide a comprehensive submission that includes a detailed timeline with sufficient detail to demonstrate project comprehension, a Schedule of Values with any requested allowances listed separately, and a work description proving understanding of the Scope of Work. The contractor will be expected to accomplish the project work in accordance with the bid solicitation details and complete the work according to a schedule submitted to and approved by Halifax Health Medical Center.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G

HALIFAX HEALTH MEDICAL CENTER

BID FORM of TOTAL PROJECT COST

Invitation to Bid for Construction Services

PROJ-25-131 – CHILLER REPLACEMENT FOR HHPO

I/We propose to furnish the work described below at the following delivered price:

Contractor shall be responsible for any repair needed to the facility as a result of damages caused by trucks going outside designated routes.

As part of the project bid submittal, a detailed schedule/timeline must be included with each bid response. Sufficient detail will be included in the project schedule/timeline to demonstrate the bidder fully understands the project scope and specifications.

In addition, a Schedule of Values detailed by division must be provided with bid submittal and will include any requested allowances. Requested allowances will be listed separately.

Bidder will include with their bid submittal a detailed work description to show they fully understand the Scope of Work.

The Contractor agrees to:

A. Hold this bid open to acceptance for 120 days from the bid due date.

B. Accomplish project work in accordance with details provided in the bid solicitation.

C. Complete the work within a detailed schedule submitted to HHMC by the successful bidder for review and approval.