6-Addendum No. 3.pdf

PDF 247 KB Posted

Attached to
Contract No. 2026-439 Route 19 Waterline Replacement Project
Solicitation number
US.253294
Issued by
Butler County, Pennsylvania

About this file

This is Addendum No. 3, issued October 14, 2026, by Cranberry Township's Engineering Department for Contract No. 2026-439 - Route 19 Waterline Replacement Project located in Butler County, Pennsylvania. The addendum modifies the contract documents by inserting requirements for the Build America, Buy America Act (BABAA) and American Iron & Steel (AIS) compliance provisions. Specific technical specification changes replace valve box descriptions in the Base Bid section (Items 18, 19, 20, 21, 25, and 26) and Alternate Bid section (Items 10, 11, and 12) to read "two-piece valve box" rather than "Resilient Wedge Gate Valve." The project involves replacement of the Route 19 waterline with all labor, materials, supervision, and equipment provided by the contractor. Sealed bids were accepted electronically via PennBid until 10:00 AM on Tuesday, November 10, 2026.

The project is partially funded using EPA Grant monies, requiring compliance with Federal Davis-Bacon Prevailing Wage requirements and federal funding regulations. Contractors must certify compliance with BABAA requirements, ensuring that all iron, steel, manufactured products, and construction materials are produced in the United States, with manufactured products containing greater than 55 percent domestic content by cost. The American Iron & Steel certification requirement mandates that materials and products shipped to the project comply with the Consolidated Appropriations Act, 2014, with documentation provided on company letterhead and submitted to both the prime contractor and engineer. All bids require a certified check or bid bond in the amount of $1,000, with bids remaining irrevocable for 90 days following the bid opening date. The estimated project cost exceeds $25,000.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 3

October 14, 2026 Page 1 of 4

TO ALL PLANHOLDERS OF RECORD

This addendum is issued in accordance with the requirements of the Contract Documents prepared by Cranberry Township’s Engineering Department titled 2026-439 – Route 19 Waterline Replacement Project and shall be considered part of said Contract Documents.

A. Where any part of the Contract Documents are modified or voided by this Addendum, the unaltered portions shall remain in effect.

CHANGES TO THE CONTRACT DOCUMENTS

A. Article 1 – Bidding Documents:

1. INSERT The Build America, Buy America Act (BABAA). (1 page)

2. INSERT the American Iron & Steel Requirements of the Consolidated

Appropriations Act, 2014. (1 page)

B. Article 2 – Instructions to Bidders

1. N/A

CHANGES TO THE TECHNICAL SPECIFICATIONS

A. Section – 5.1.1 General Information – Base Bid

1. REPLACE the following items in the Base Bid section.

a. Item No. 18 - 6” Resilient Wedge Gate Valve should read “two-piece valve box”.

b. Item No. 19 - 8” Resilient Wedge Gate Value should read “two-piece valve box”.

c. Item No. 20 - 12” Resilient Wedge Gate Value should read “two-piece valve box”.

d. Item No. 21 - 8x6x8 Tee and 6” Valve should read “two-piece valve box”.

e. Item No. 25 - 8x8x8 Tee and Three Valves should read “two-piece valve box”.

f. Item No. 26 - 8x8x8 Tee and Two Valves should read “two-piece valve box”.

ADDENDUM NO. 3

October 14, 2026 Page 2 of 4

B. Section – 5.1.2 General Information – Alternate Bid.

1. REPLACE the following items in the Alternate Section

a. Item No. 10 - 6” Resilient Wedge Gate Valve should read “two-piece valve box”.

b. Item No. 11 - 8” Resilient Wedge Gate Valve should read “two-piece valve box”.

c. Item No. 12 - 8x8x6 Tee and 6” Valve should read “two-piece valve box”.

CHANGES TO THE CONSTRUCTION DRAWINGS

A. N/A

Attachments:

- The Build America, Buy America Act (BABAA). (1 page)

- American Iron & Steel Requirements of the Consolidated Appropriations

Act, 2014. (1 page)

END OF ADDENDUM NO. 3

THE BUILD AMERICA, BUY AMERICA ACT (BABAA)

The undersigned certifies, to the best of their knowledge and belief, that:

The Build America, Buy America Act (BABAA) requires that no federal financial assistance for “infrastructure” projects is provided “unless all of the iron, steel, manufactured products, and construction materials used in the project are produced in the United States.”

Section 70914 of Public Law No. 117-58, §§ 70901-52.

The undersigned certifies that for the Route 19 Waterline Replacement Project the iron, steel, manufactured products, and construction materials used in this contract are in full compliance with the BABAA requirements including:

1. All iron and steel used in the project are produced in the United States. This means all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.

2. All manufactured products purchased with EPA financial assistance must be produced in the United States. For a manufactured product to be considered produced in the United States, the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55% of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation.

“The, ________________________, certifies or affirms the truthfulness and accuracy of (Contractor or Subcontractor) each statement of its certification and disclosure, if any. In addition, the [Contractor or Subcontractor] understands and agrees that the provisions of 31 U.S.C. Chap. 38, Administrative Remedies for False Claims and Statements, apply to this certification and disclosure, if any.”

Signature of [Contractor’s or Subcontractor’s] Authorized Official

Name & Title of [Contractor’s or Subcontractor’s] Authorized Official

Date: _______________________________

AMERICAN IRON & STEEL REQUIREMENTS OF THE CONSOLIDATED

APPROPRIATIONS ACT, 2014

The following information is provided as a sample letter of certification for AIS compliance.

Documentation must be provided on company letterhead.

Date Company Name Company Address City, State Zip

Subject: American Iron and Steel Certification for Project 2026-439 - Route 19 Waterline Replacement Project

I, (company representative), certify that the following products and/or materials shipped/ provided to the subject project are in full compliance with the American Iron and Steel requirement as mandated by the requirements of the Consolidated Appropriations Act, 2014.

Item, Products and/or Materials:

1. Xxxx

2. Xxxx

3. Xxxx

Such process took place at the following location: If any of the above compliance statements change while providing material to this project, we will immediately notify the prime contractor and the engineer.

Signed by company representative.

File details come from the government source that posted it. Updated .