6-Addendum No. 1.10232026.pdf

PDF 7 MB Posted

Attached to
Schuylkill County, PA - Pine Grove Township, CDBG Building ADA Improvement - Phase III (0326-609043.26)
Solicitation number
US.258250
Issued by
Somerset County, Pennsylvania

About this file

This Addendum No. 1, issued October 23, 2026, by Alfred Benesch & Company on behalf of Schuylkill County, modifies the bidding documents for the Pine Grove Township Building ADA Improvement Project – Phase III (Project No. 0326-609043.26). The project encompasses interior ADA-accessible restroom and transaction counter improvements and exterior sidewalk ADA improvements at the Pine Grove Township Municipal building in Schuylkill County, Pennsylvania. Bids were due on Wednesday, October 28, 2026, at 9:00 AM via the PennBid online platform. The addendum updates Davis Bacon Federal wage rates (dated 10/15/26, replacing rates from 5/18/26), adds Davis Bacon Heavy/Highway wage rates for exterior improvements, and revises the Form of Agreement (Section 5200) to correct retainage statements and allow exterior work completion in spring due to seasonal temperature constraints. The interior work must be substantially completed by February 7, 2027, with final payment readiness by February 14, 2027; exterior work must be substantially completed by April 30, 2027, with final payment readiness by May 7, 2027. Contract time begins upon issuance of the Notice to Proceed after all contract documents are received and compiled.

The contract is awarded to a single contractor and establishes liquidated damages of $500 per day for delays beyond the specified completion dates. Progress payments will be made based on a schedule of values, with 10 percent retainage until the project reaches 50 percent completion, then reduced to 5 percent if work character and progress are satisfactory. Upon substantial completion, retainage is reduced to 2 percent; final payment includes interest at six percent per annum accruing from the due date. The contractor must provide a bid bond equal to 10 percent of the total bid and performance and payment bonds each equal to 100 percent of the contract price. The project is funded through CDBG (Community Development Block Grant) funds. Davis Bacon prevailing wage requirements apply to both building and heavy/highway work. The contractor must comply with Pennsylvania employment discrimination laws, workers' compensation requirements, and the Steel Products Procurement Act for any steel or steel products used in the work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Y:\Pennsylvania\03XX-60S\0326-609043.26_PGTwpBldgADA\Office_Docs\Specifications\Addenda\Addendum 1\Addendum No1.102026.doc

ADDENDA NO. 1

To: All Prospective Bidders

Date: October 23, 2026

From: James Tohill, P.E. Alfred Benesch & Company

Subject: Pine Grove Township – Township Building ADA Improvement Project – Phase III Addendum No. 1 – Project No. 0326-609043.26

Bid Receipt: Wednesday, October 28, 2026, at 9:00 AM

This Addendum forms a part of the Contract Documents and modifies the Bidding Documents dated October 2026.

1. Davis Bacon Building wage rates for this project have been updated. Replace the Davis Bacon Federal Wage Rates dated 5/18/26 in the project manual with the attached new rates dated 10/15/26.

2. Davis Bacon Heavy/Highway wage rates have been added to this contract for the exterior improvements.

3. Section 5200, Form of Agreement has been updated to correct the retainage statement and allow exterior work to be completed in the spring due to seasonal temperatures. Replace Section 5200 Form of Agreement in the project manual and in the Documents to Submitted with Bid file with the attached Form of Agreement.

This Addendum is issued to all registered plan holders pursuant to the Contract Documents. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda, if any. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement.

The Bidder shall acknowledge receipt of this Addendum in the appropriate space on PennBID.

End of Addendum No. 1

PGT - CDBG Twp. Building ADA Improvement – Phase III - Project No. 0326-609043.26 FORM OF AGREEMENT Section 005200

FORM OF AGREEMENT Section 005200 – Page 1

FORM OF AGREEMENT

BETWEEN OWNER AND CONTRACTOR

THIS AGREEMENT is by and between

County of Schuylkill (“Owner”) and

(“Contractor”).

Owner and Contractor hereby agree as follows:

ARTICLE 1 – WORK

1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents.

The Work is generally described as follows:

Project: Pine Grove Township - CDBG Township Building ADA Improvement Project – Phase III

Contract Number: 0326-609043.26

ARTICLE 2 – THE PROJECT

2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:

The project involves interior ADA accessible restroom and transaction counter improvements and exterior sidewalk ADA improvements at Pine Grove Township Municipal building.

ARTICLE 3 – ENGINEER

3.01 The Project is being administered by Alfred Benesch & Company (Engineer), which is to act as Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.

ARTICLE 4 – CONTRACT TIMES

4.01 Time of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

FORM OF AGREEMENT Section 005200 – Page 2

4.02 Dates for Substantial Completion and Final Payment

A. The Interior/Building Work will be completed by February 7, 2027, and ready for final payment in accordance with Paragraph 14.07 of the General Conditions by February 14, 2027. The Exterior Work will be completed by April 30, 2027, and ready for final payment in accordance with Paragraph 14.07 of the General Conditions by May 7, 2027.

Contract time will begin when Notice to Proceed is issued after all contract documents are received and compiled.

4.03 Liquidated Damages

A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial loss if the Work is not completed within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay Owner $500 for each day that expires after the time specified in Paragraph 4.02 above for Substantial Completion until the Work is substantially complete. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time or any proper extension thereof granted by Owner, Contractor shall pay Owner $500 for each day that expires after the time specified in Paragraph 4.02 above for completion and readiness for final payment until the Work is completed and ready for final payment.

ARTICLE 5 – CONTRACT PRICE

5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to Paragraphs below:

A. For all Unit Price Work, an amount equal to the sum of the established unit price for each separately identified item of Unit Price Work times the actual quantity of that item in Accordance with Attached Unit price Schedule, See Exhibit A.

Total of all Bid Prices (Unit Price Work)

Total of all Base Price (words):

The Bid prices for Unit Price Work set forth as of the Effective Date of the Agreement are based on estimated quantities. As provided in Paragraph 11.03 of the General Conditions, estimated quantities are not guaranteed, and determinations of actual quantities and classifications are to be made by Engineer as provided in Paragraph 9.07 of the General Conditions.

B. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.

FORM OF AGREEMENT Section 005200 – Page 3

ARTICLE 6 – PAYMENT PROCEDURES

6.01 Submittal and Processing of Payments

A. Contractor shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.

6.02 Progress Payments; Retainage

A. OWNER shall consider progress payments on account of the Contract Price on the basis of CONTRACTOR's Applications for Payment as recommended by ENGINEER, on the day of the OWNER's regularly scheduled and advertised monthly meeting.

CONTRACTOR shall be advised of the OWNER's meeting schedule at the preconstruction conference. All such payments will be measured by the schedule of values established as provided in Paragraph 2.07.A of the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements.

1. Prior to Substantial Completion, progress payments will be made in an amount equal to the total of work completed less the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Engineer may determine or Owner may withhold, including but not limited to liquidated damages, in accordance with Paragraph 14.02 of the General Conditions.

a. Until the project is 50 percent complete, 10 percent of Work completed will be retained. Once the Work has reached or exceeded 50 percent complete as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, the retainage withheld will be reduced to 5 percent; and

b. 10 percent of cost of materials and equipment not incorporated in the Work will be retained.

B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less 2% retainage and/or as such amounts as Engineer shall determine in accordance with Paragraph 14.02.B.5 of the General Conditions and less 200 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the tentative list of items to be completed or corrected attached to the certificate of Substantial Completion.

6.03 Final Payment

A. Upon final completion and acceptance of the Work in accordance with Paragraph 14.07 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 14.07.

FORM OF AGREEMENT Section 005200 – Page 4

ARTICLE 7 – INTEREST

7.01 No allowance for interest shall be made with respect to progress payments prior to Substantial Completion. The final payment due the CONTRACTOR from the OWNER after the ENGINEER has certified Substantial Completion of the Work shall bear interest at a rate of six percent per annum, such interest to begin to accrue from the date such payment shall become due and payable to CONTRACTOR; provided, however, that where OWNER has issued bonds to finance the project to which the Work relates, interest shall be payable to CONTRACTOR at the rate of interest of the bond issue or at the rate of six percent per annum whichever is less.

ARTICLE 8 – CONTRACTOR’S REPRESENTATIONS

8.01 In order to induce Owner to enter into this Agreement, Contractor makes the following representations:

A. Contractor has examined and carefully studied the Contract Documents and the other related data identified in the Bidding Documents.

B. Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. Contractor is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work.

D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities), if any, that have been identified in Paragraph SC-4.02 of the Supplementary Conditions as containing reliable "technical data," and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in Paragraph SC-

4.06 of the Supplementary Conditions as containing reliable "technical data."

E. Contractor has considered the information known to Contractor; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Site-related reports and drawings identified in the Contract Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, including any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Contract Documents; and (3) Contractor’s safety precautions and programs.

F. Based on the information and observations referred to in Paragraph 8.01.E above, Contractor does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract Documents.

FORM OF AGREEMENT Section 005200 – Page 5

G. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.

H. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

I. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

ARTICLE 9 – CONTRACT DOCUMENTS

9.01 Contents

A. The Contract Documents consist of the following:

1. This Agreement (pages 1 to 10 inclusive).

2. Advertisement

3. Instructions to Bidders

4. Notice of Award

5. Statement of Surety Company

6. Contractor’s Affidavit

7. Contractor’s Release

8. Performance Bond

9. Payment Bond

10. General Conditions (pages 1 to 62, inclusive).

11. General Conditions Part II Federal Requirements (Pages 1 to 16)

12. Supplementary Conditions (pages 1 to 16, inclusive).

13. Federal labor standard provisions

14. Schuylkill County Standard Terms and Conditions.

15. Specifications as listed in the table of contents of the Project Manual.

16. Drawings consisting of 10 sheets with each sheet bearing the following general title:

CDBG Township Building ADA Improvement Project – Phase III.

FORM OF AGREEMENT Section 005200 – Page 6

17. PSATS CDL Program Contractor’s Statement of Compliance.

18. Statement of Bidder’s Qualifications Form.

19. Non-Collusion Affidavit.

20. Public Works Employment Verification Form.

21. Nondiscrimination/Sexual Harassment Clause.

22. MBE/WBE Contact Solicitation and Commitment Statement.

23. Certification of Bidder Regarding Equal Employment.

24. Pre-Bid Meeting Minutes (if applicable).

25. Addenda (numbers _ to _, inclusive).

26. Exhibits to this Agreement (enumerated as follows):

a. Contractor’s Bid (pages _ to _, inclusive).

b. Documentation submitted by Contractor prior to Notice of Award (pages - to -, inclusive).

27. The following which may be delivered or issued on or after the Effective Date of the Agreement and are not attached hereto:

a. Notice to Proceed

b. Work Change Directives.

c. Change Orders.

d. Pre-Construction Meeting Minutes.

28. Federal Contract Provisions Certification Form.

29. All other documents listed in the Appendix of the Project Manual.

B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above).

C. There are no Contract Documents other than those listed above in this Article 9.

D. The Contract Documents may only be amended, modified, or supplemented as provided in Paragraph 3.04 of the General Conditions.

FORM OF AGREEMENT Section 005200 – Page 7

ARTICLE 10 – MISCELLANEOUS

10.01 Terms

A. Terms used in this Agreement will have the meanings stated in the General Conditions and the Supplementary Conditions.

10.02 Assignment of Contract

A. No assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.

10.03 Successors and Assigns

A. Owner and Contractor each binds itself, its partners, successors, assigns, and legal representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents.

10.04 Severability

A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon Owner and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.

10.05 Contractor’s Certifications

A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 10.05:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process or in the Contract execution;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or

(c) to deprive Owner of the benefits of free and open competition;

FORM OF AGREEMENT Section 005200 – Page 8

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

10.06 In the hiring of employees for the performance of Work under this Agreement or any subcontract, neither CONTRACTOR nor any subcontractor or any person acting on behalf of CONTRACTOR or any subcontractor shall by reason of gender, race, creed or color discriminate against any citizen of the Commonwealth of Pennsylvania who is qualified and available to perform the work to which such employment relates.

10.07 Neither CONTRACTOR nor any subcontractor or any person on behalf of CONTRACTOR or any subcontractor shall in any manner discriminate against or intimidate any employee hired for the performance of the Work under this Agreement on account of gender, race, creed or color.

10.08 This Agreement may be canceled or terminated by OWNER, and all money due or to become due under the Agreement may be forfeited for a violation of the terms or conditions set forth in paragraph 10.6 and/or 10.7.

10.09 The parties hereto consent to the exclusive jurisdiction of the Court of Common Pleas of the county in which the contract work is taking place, with respect to any dispute which may arise in connection with this Agreement or the enforcement thereof unless the parties mutually agree in writing to another from of dispute resolution.

10.10 CONTRACTOR shall accept the provisions for the Workers’ Compensation Act of 1915, and any supplements or amendments thereof, and CONTRACTOR shall insure its liability thereunder or file with OWNER a certificate of exemption from insurance issued by the Department of Labor and Industry of the Commonwealth of Pennsylvania

10.11 CONTRACTOR represents and warrants:

(1) That it is financially solvent and experienced in and competent to perform the Work.

(2) That is familiar with all Federal, State, Municipal and County laws, ordinances and regulations which may in any way affect the completion of the Work

(3) That it has carefully examined the Contract Documents and that it has familiarized itself with the various conditions affecting the Work

(4) That it will perform the Work in accordance with the requirements of the Contract

Documents

FORM OF AGREEMENT Section 005200 – Page 9

10.12 In accordance with Act 3 of 1978, if any steel or steel products are to be used or supplied in the performance of the Work, only those produced in the United States as defined in the Act shall be used or supplied in the performance of the Work, including any subcontracts.

In accordance with Act 161 of 1982, cast iron products shall be considered steel products governed by the Steel Products Procurement Act, and all cast iron products shall be produced in the United States. In accordance with Act 141 of 1984, steel products is defined to include machinery and equipment, and machinery and equipment which is governed by the Steel Products Procurement Act shall be supplied in accordance with the requirements of such Act

10.13 CONTRACTOR shall assume all risk of damage or loss which may occur in the performance of the Work or any part thereof and with respect to any of the materials or other things done, furnished and supplied by CONTRACTOR, or used and employed in the Work and in the performance of this Agreement. CONTRACTOR shall assume all liability for, and shall indemnify and hold OWNER harmless from and against, all claims and expense resulting from accidents, negligence or other cause that may occur during the performance of the Work and this Agreement to any person or persons employed upon the Work or to any other person or persons who may be injured or to any property which may be damaged in any manner whatsoever by and during the performance of the Work, together with all costs (including attorneys’ fees costs of defense) incurred in connection with said claim or claims. The parties thereto agree that in any and all relevant respects CONTRACTOR is to be considered as an independent contractor.

10.14 This Agreement represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral.

FORM OF AGREEMENT Section 005200 – Page 10

IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement. Counterparts have been delivered to Owner and Contractor. All portions of the Contract Documents have been signed or have been identified by Owner and Contractor or on their behalf.

This Agreement will be effective on ___________, 20___ (which is the Effective Date of the Agreement).

OWNER: CONTRACTOR

County of Schuylkill

By: By:

Title: Title:

By:

Title:

Attest

By: Title:

Title:

(If Contractor is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest: Attest:

Title: Title:

Address for giving notices: Address for giving notices:

401 North Second Street

Pottsville, PA 17901

(If Owner is a corporation, attach evidence of authority to sign. If Owner is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)

File details come from the government source that posted it. Updated .