This Pre-Bid Meeting Minutes document, dated October 23, 2026, concerns the Pine Grove Township Building ADA Improvement Projects – Phase III in Schuylkill County, Pennsylvania (Project No. 0326-609043.26). The project encompasses three primary components: restroom renovations, transaction counter improvements, and exterior approach sidewalk installation to the mailbox at the Pine Grove Township Municipal Building. The pre-bid meeting was held on October 20, 2026, at 9:30 AM at the project site. Contractor questions were due by Thursday, October 22, 2026, at 4:00 PM, with sealed bids due Wednesday, October 28, 2026, by 9:00 AM via PennBID. Bids will be publicly opened and posted following submission, with a tentative project award scheduled for November 11, 2026, at the Commissioners' meeting. The entire project will be awarded to one contractor.
Davis-Bacon prevailing wage rates apply to this project, with updated building wage rates effective October 15, 2026, and heavy/highway wage rates for exterior improvements to be provided via addendum. A bid bond equal to 10 percent of the total bid is required with submission, and successful bidders must provide performance and payment bonds each in the amount of 100 percent of the contract price. Contractors must complete all required forms, including MBE/WBE documentation demonstrating good faith efforts to reach minority and women business enterprises if using subcontractors, and public works verification forms. Building permit fees, calculated at 2.5 percent of total construction costs with a $900 minimum plus approximately $20 in additional fees, must be included in mobilization costs. A contract modification allows temperature-affected work items, including concrete sidewalks, to be completed in spring rather than winter to address weather and temperature concerns. CDBG funds will support the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 23, 2026 | Pre-Bid Meeting Minutes| 1
Pre-Bid Meeting Minutes
The pre-bid meeting was held for the above-referenced project to provide a brief overview of the plans and specifications, review County preferences of the bid preparation, highlight project requirements, and answer contractor questions. The following items were noted and/or discussed:
1. Project Summaries. The projects include the following:
a. Township Building ADA Improvements
i. Restroom Renovations
ii. Transaction Counter Improvements
iii. Exterior approach sidewalk (to mailbox)
2. Current Schedule
a. Deadline for contractor questions is Thursday, October 22, 2026, at 4:00 PM.
b. Bids are due Wednesday, October 28, 2026, by 9:00 AM online, on PennBID.
c. Bids will be opened, read aloud and posted to PennBID following bid opening.
d. The project award will tentatively occur on November 11, 2026, at the Commissioners’ meeting.
3. Davis Bacon Wage rates apply – Please check the bid documents for the rate schedule. Updated building wage rates (10/15/26) will be posted via addendum. Additionally, the current wage rates for heavy/highway will be added via addendum for the exterior improvements.
4. Document forms All forms indicated in the contract documents to be submitted with your bid must be signed.
MBE/WBE – if you are using sub-contractor, you must make a good faith effort to reach out to minority and women business enterprises for the opportunity to compete for work. If you are not using sub-contractors, you must state that on the form and sign at the bottom.
Current Date: October 23, 2026
Project: Township Building ADA Improvement Projects – Phase III
Project No.: 0326-609043.26
Date/Time: October 20, 2026 / 9:30 AM
Place: Pine Grove Township Municipal Building
175 Oak Grove Road Pine Grove, PA
Attendees: See attached.
October 20, 2026 | Pre-Bid Meeting Minutes | 2
Public works verification form must be filled out and signed.
Forms not completed or signed are reasons for a bid to be deemed incomplete and may be rejected.
5. All bids for each project will be submitted electronically via Pennbid. Bid bonds will be required with the submission of each bid.
6. The potential bidders were notified that any subcontractor brought onto the job needs to be identified for a SAM search.
7. Contractors need to include the building permit fee in their mobilization costs. The Permit Fee should be discussed with Ralph Hummel of Lehigh Engineering to verify total anticipated costs.
We anticipate the fee can be calculated to be 2.5% of the total cost of construction ($900 minimum) plus additional fees of approximately $20.
8. A question was raised about a note on the plans alluding to a first-floor chase. This note was inadvertently left on the plans from a previous phase and is not applicable.
9. A question was raised about the exhaust penetrating the roof. It was clarified that the mechanical plans (MEP 1.0), Note 7 indicate exhaust ductwork to eave vent along exterior of building. The MEP drawings do not show by note or graphics any need for roof penetrations in this phase.
10. The language regarding the retainage was questioned. Section 5200 Form or Agreement will be revised in an addendum to correct the retainage statements.
11. A question was asked about extending the contract duration to allow concrete work to be completed in the spring, due to weather and temperature concerns during the winter months. The contract will be modified to allow temperature-affected items of work, including concrete sidewalks, to be completed in the spring. Section 5200 Form of Agreement will be modified to extend those deadlines.
12. A question was raised regarding the review timeframes of the building permit. We reached out to Ralph Hummel, BCO for the Township of Lehigh Engineering and was told that he anticipated a review may take up to two weeks. Please note that this information is only to be used as guidance for estimating purposes. If the review process is longer than anticipated, the County will consider the associated delays if a time extension is needed.
All Attendees are requested to review the above minutes for corrections and/or comments. If no comments are received within ten (10) business days, these minutes will become the basis for all official action.
Respectfully submitted, James Tohill, P.E.
Project Manager cc: Public Notices on PennBID