This is a requirements matrix document from a New Mexico government entity outlining funding-dependent compliance obligations for paving services projects. The document establishes a tiered framework that determines contractor requirements based on project cost and funding source, with escalating compliance thresholds as project values increase.

The requirements matrix specifies domestic preference requirements beginning at $2,000 in project costs. Davis-Bacon wage requirements apply to projects with federal funding of $25,000 or more. Performance bonds and payment and material bonds are required for projects at the $60,000 threshold regardless of funding source. Labor bonds and sub-contractors listing forms are mandatory for projects exceeding $60,000, with federal funding requiring an additional wage decision document. This tiered structure ensures that smaller projects have proportionate compliance burdens while larger projects—particularly those utilizing federal funds—are subject to comprehensive prevailing wage, bonding, and labor documentation requirements.

View the file

Other files

File Type Posted
7-7 Certification Lobbying Form.pdf PDF
1-1 Paving Services.pdf PDF
5-5 Transmittal Form OCCS.pdf PDF
10-District Map 2015.pdf PDF
3-3 Acceptance and Disclosures Form.pdf PDF
11-Paving Bid Specs.pdf PDF
8-7.1 SFLLL 1 2 P-V12a-2.pdf PDF
4-4 Exceptions Form.pdf PDF
9-9 References.pdf PDF
2-2 General Conditions ITB Indefinite Qty Contract.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTE: When a project is identified, and use of funds for the specific project is determined by the District, the following will be used to determine the requirements based on funding:

REQUIREMENTS BASED ON FUNDING

PROJECT COST OPERATIONAL FUNDING FEDERAL FUNDING

Domestic Preference

$2,000.00 + Davis-Bacon

$25,000.00 + Performance Bond Performance Bond

Payment & Material Bond Payment & Material Bond

Labor Bond Labor Bond

$60,000.00 + Sub-Contractors Listing Form Sub-Contractors Listing Form

Wage Decision