6-2-MP27009-27323210 FINAL Programming Document.pdf

PDF 5 MB Posted

Attached to
DFCM Construction - VBS Consultant Services - Design - Bridgerland Technical College - Main Building Renovation - 27323210
Solicitation number
MP27009
Issued by
Utah

About this file

Summary

This is a programming document and feasibility study for a construction project involving the State of Utah Division of Facilities Construction and Management (DFCM) and Bridgerland Technical College (BTECH). The project seeks design services to remodel approximately 11,720 gross square feet of existing space within the Main Building into an advanced Automation Technology and Control Systems & Robotics facility. The scope includes consolidating and expanding hands-on instructional labs, robotics lab, specialized danger lab, faculty support spaces, and mechanical/electrical/plumbing infrastructure to address current capacity constraints. The remodel will serve manufacturing workforce development needs in the Bear River Region, with current facility utilization at 106% of capacity and the Automation Technology program specifically operating at 216% capacity. The programming document was published in October 2026 and establishes comprehensive space requirements, building code compliance strategies, architectural character guidelines, and mechanical, electrical, and plumbing design criteria. Construction is anticipated to begin in 2027 with substantial completion targeted for April 2028, allowing classes to resume Fall Semester 2029.

The total construction cost is estimated at approximately $4.8 million for Phase 1, with soft costs (design, furnishings, project support) ranging between 10 and 15 percent, escalated to account for 2027 market conditions. The design approach prioritizes reuse of existing equipment while strategically incorporating new assets to accommodate enrollment growth. The college anticipates needing approximately ten new full-time equivalent positions within three years at an average cost of $120,000 per position to support expanded instructional delivery and program management. Potential funding sources include performance-based funding, growth funding, and capacity-based models through Utah's higher education funding mechanisms. The project aligns with the Governor's manufacturing workforce development initiatives and Talent Ready Utah grant programs, addressing a regional employment demand characterized by approximately 40% annual growth in manufacturing and construction-related fields. The master plan envisions total renovation of 124,160 square feet with a relatively small 10,000-square-foot addition, estimated at approximately $34.1 million for all phases.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AUTOMATION TECHNOLOGY PROGRAMMING

B R I D G E R L A N D

TECHNICAL COLLEGE

360 West Aspen Ave Salt Lake City, UT 84101 801-832-4422

DFCM PROJECT NO: 27323210

PUBLISHED: OCTOBER 2026

SIGNATURE SHEET

BRIDGERLAND TECHNICAL COLLEGE | AUTOMATION TECHNOLOGY

We have reviewed the document for Bridgerland Technical College and confirmed that it adequately represents our request for a programming document and that it fulfills our mission and goals. The appropriate parties listed below have reviewed it for approval.

STATE OF UTAH DFCM

Brad Demond, Project Manager Date

BRIDGERLAND TECHNICAL COLLEGE

Lisa Moon, Interim President Date

Emily Hobbs, Administrative Chief of Staff Date

Brandi Gittins, VP for Administrative Services & CFO Date

10/30/2026

10/30/2026

10/30/2026

11/10/2026

“BRIDGERLAND

TECHNICAL

COLLEGE INSPIRES

STUDENTS

TO PURSUE

TECHNICAL

EDUCATION

AND SECURE

HIGH-WAGE,

HIGH-DEMAND

CAREERS”

ACKNOWLEDGMENTS

Many thanks to all faculty, staff, students, stakeholders, and the communities of the Bear River Region.

BRIDGERLAND TECHNICAL COLLEGE

Lisa MoonInterim President
Brandi GittinsVP for Administrative Services & CFO
Emily HobbsAdministrative Chief of Staff

Scott Danielson AVP for Instruction

Matt FullerDepartment Head
Alex BaltodanoChief Information Officer
Paul JamesDirector of Facilities

STATE OF UTAH DFCM

Brad DeMond Project Manager

METHOD STUDIO

Joshua GreenePrincipal
Matt WallaceAssoc. Principal
Rafael LopezArchitect
Angelica LamasDesigner

CONSULTANT GROUPS

Scot MuirResolut Group
Lance KobayashiLynk Engineering

TABLE OF CONTENTS

A EXECUTIVE SUMMARY

Bridgerland’s Mission and History

Project Justification, Vision and Goals

Space Needs & Project Approach

Budget and Project Schedule

Phasing & Financing

B EXISTING CONDITIONS

Campus Overview

Main Building Overview

Architectural Character

C BUILDING REQUIREMENTS

Building Code Analysis

Architectural Narrative

Building Systems Design Criteria (Structural, Electrical & Mechanical)

D SPACE REQUIREMENTS

Schedule of Programs

Overall Test Fit Plan

Room Data sheets & Criteria

E APPENDICES

Cost Analysis Hazmat Survey

A1 - A2

A3 - A8

A9

A10 - A11

A12 - A16

B1 - B2

B3

B4 - B5

C1 - C3

C4 - C9

C9 - C29

D1

D2

D3 - D16

E1 - E4

A - EXECUTIVE SUMMARY

Automation Technology Programming A-1

Bridgerland’s Mission The mission of the Bridgerland Technical College is to deliver competency-based, employer guided career and technical education to both secondary and post-secondary students through traditional and technology-enhanced methodologies. This hands-on technical education provides occupational education, skills training, and workforce development to support the educational and economic development of the

Bear River Region.

Where instruction and all other activities are student centered.

That offers a comprehensive range of quality programs to prepare students for entry into high demand careers

Where strong relationships are developed with employers to enable training to be responsive to current industry needs.

We Envision a College...

THAT IS A STUDENT DRIVEN

COMMUNITY WHERE

ACHIEVEMENT OCCURS

WITHOUT BOUNDARIES.

Automation Technology Programming A-2

Bridgerland Technical College (BTECH) was founded on

Sept. 17, 1971, when the Utah State Board of Vocational

Education unanimously voted to create a new vocational district that would serve Box Elder, Cache, and Rich counties. This move combined the Cache Vocational Center and some of the vocational programs offered by Utah

State University. Though originally pitched both as the Tri-

County Area Vocational Center and the Bear River Area

Vocational Center, the center opened in October of that year under the name Bridgerland Area Vocational Center.

Since then, BTECH has seen three more name changes under legislative direction: Bridgerland Applied Technology

Center, Bridgerland Applied Technology College, and finally

Bridgerland Technical College.

The legislature changed vocational centers in 1990 to improve public perception and thus became Bridgerland

Applied Technology Center.

As a result of Governor Mike Leavitt’s dedication for improved educational pathways, the state Legislature created the Utah

College of Applied Technology governed by the Board of Regents. Bridgerland became an applied technology college campus in 2001. Accreditation then transitioned to the nationally recognized non-profit organization The

Council on Occupational Education (COE) in 2006.

In 2017 the Utah College of Applied Technology was reorganized into the Utah System of Technical Colleges resulting, once again, in a legislatively mandated name change to Bridgerland Technical College.

Effective July 1, 2020, under SB111, the Utah State Legislature put all public degree-granting colleges and universities and technical colleges under a single governing body, the newly created Utah Board of Higher Education.

Institutional Profile and History

A - EXECUTIVE SUMMARY

Built in 1970, the former Wurlitzer manufacturing facility became the first building for the college.

Changing lives one student at a time, as we’ve

Automation Technology Programming A-3

Project Justification

BTECH is located on the western edge of Logan, UT, one of the fastest-growing regions in the state. The location provides an abundant set of opportunities to grow, expand, and address a series of infrastructure issues, including: Capacity and critical program adjacencies. Portions of BTECH’s aging building need to be remodeled, renovated, and repurposed to meet the new standards set by industry.

Since its founding in 1971, BTECH moved to multiple locations throughout Cache Valley, finding a permanent home at the former Wurlitzer piano factory in 1984. The building itself is over 60 years old (opened in 1970) and was never meant for educational purposes. Over the years, the college has invested time and resources in remodeling, re-purposing, and upgrading spaces as well as the mechanical/electrical systems. As the standards for technical education grow and the demand for essential workers increases throughout the state, BTECH must upgrade and envision the way its existing facilities function. While it has served the college well, the building was never designed for modern educational use. Despite its low acquisition cost (less than $20 per square foot), the facility has now reached the limits of its adaptability without significant renovation for various sections of the facility.

The student body keeps growing every year, and unfortunately, numerous prospective students have been put on waiting lists. It is clear, there is significant student and employer demand as evidenced by expansion of business and industry representatives looking for more trained graduates. BTECH’s highest demands are dictated by the current industry, with major growth in Automation Technology and Control Systems & Robotics.

Automation Technology Programming A-4

CONTROL SYSTEMS & ROBOTICS

The Control Systems and Robotics program prepares qualified students for advanced work as Control System Technicians in an automated manufacturing environment. This certificate provides hands-on training in Programmable Logic Controllers (PLCs), industrial robots, industrial networking, servo system programming, vision systems, and Human Machine Interface (HMI) programming.

Program Summary

AUTOMATION TECHNOLOGY

The Automation Technology program supports a wide variety of mechanical and automated systems. This program is designed to help prepare students with the necessary skills to become technicians in several critical industries. Students are introduced to a wide variety of tools, practices, and procedures.

SPACE UTILIZATION

Past Feasibility studies create a plan for phased construction to remodel the existing building. Timing is dependent upon when the project receives its first allocation of funds and how many phases are required to complete the total project. In addition, it should be noted, the facility houses several non-instructional services or functions, including academic support, student support, Administration, Accounting, and Information Systems. These functions are already operating at or near capacity.

The first priority for this request is to remodel and repurpose space for the Automation Technology, Control Systems and Robotics programs. This newly remodeled space, because of its efficient design, will allow these programs to expand their enrollment significantly, which will occur almost immediately upon completion of the project. These two programs, using the most recent available FTE numbers, produced 127.01 FTE, so the number of student FTE in this existing Main building will immediately jump from 613.41 to 740.42 FTE. Since the employment demand in this region for manufacturing and construction-related programs is close to a 40% annual growth rate, expanding these facilities to accommodate the additional student demand cannot be completed soon enough.

It is anticipated, once constructed, full utilization will be achieved in less than three years.

The space utilization standards for technical colleges are currently under review by a statewide task force, and final benchmarks are still evolving. However, the most relevant guidance to date comes

Building Capacity and Utilization

SPACE UTILIZATION (CONT.)

from the SmithGroup study, which evaluated technical college facilities and confirmed that traditional space models used for degree-granting institutions do not accurately reflect the instructional model of technical education.

Unlike universities, technical colleges operate using self-contained program spaces where students remain in dedicated labs and classrooms for extended periods, rather than rotating hourly between general-purpose classrooms. As a result, existing methodologies for calculating space utilization based on student station hours or classroom turnover rates are not applicable.

In response, the SmithGroup proposed an overly simplified metric based on assignable square feet per student FTE, recommending approximately 160 sq. ft. per FTE for technical instruction. Bridgerland Technical College’s internal analysis places its usage at 156 sq.

ft. per FTE, or 98% of the recommended benchmark, indicating strong alignment with best practices.

Utilizing the methodology proposed by the SmithGroup for technical colleges, the Utah System of Higher Education Data Team developed a draft facility utilization model to test this theory. The result for Bridgerland Technical College as a whole found that facility utilization using the most current available data is 106% of capacity. This is accomplished by utilizing the facilities year-round as well as on nights and weekends.

Automation Technology Programming A-5

A - EXECUTIVE SUMMARY

The college’s first phase of construction (following the masterplan) would include a remodel for Automation Technology. This is critical as current utilization of program space is at 216% of capacity. It’s also important to note that this project primarily involves re-purposing space in an existing building. The areas to be remodeled are currently being used for Continuing Education purposes, but that is not the highest priority. Once remodeled, these spaces will be returned to valuable instructional and support functions, thereby improving overall facility utilization.

Project Impacts

COMMUNITY IMPACTS

With the expansion of existing facilities and increased enrollment there is a likely chance traffic will increase in the area. Most of the impact will be felt along 1400 North, as the new entry will be accessed from that road.

Once 800 West is developed the college’s access will become two sided and help ease any future congestion with additional entries to the south.

ECONOMIC IMPACTS

Since the employment demand in this region for manufacturing and construction-related programs is close to a 40% annual growth rate, expanding these facilities to accommodate the additional student demand cannot be completed soon enough.

All of these programs are in high demand.

They will help the college meet or exceed the

Automation Technology Programming A-6

Utah Board of Higher Education’s goal. The Governor’s Office of Planning and Budget along with Talent Ready Utah, are very concerned with meeting the workforce needs of employers across the state. The workforce shortage is so significant that the state has two important initiatives to increase the availability of workers. One is in healthcare, and one is in manufacturing/construction. Bridgerland Technical College has been fortunate to receive a grant from Talent Ready Utah for both initiatives. The new Health Sciences building at BTECH has helped facilitate the space needs for the healthcare initiative, and this new project will help facilitate the apprenticeship/pre-apprenticeship grant for manufacturing and construction.

A - EXECUTIVE SUMMARY

Project Vision & Goals

The proposed programming study will support expanding college enrollment, promote collaboration between existing programs, align with the campus master plan, and overall improve student instructional areas. With the current facilities, the instructional programs are isolated from one another. There are limited visual connections, shared resources, and opportunities for students to interact or gather.

This project will help improve and generate necessary spaces for students to excel in their desired fields. It will also help create a design language for future phases and entries at the Main building. Additionally the design will help connect the West building, the Health

Automation Technology Programming A-7

PROJECT VISION & GOALS (CONT.)

Sciences Building and the Business & Innovation building. As an added benefit, the previous master plans will help increase BTECH’s presence in the community along 1400 North and 600 West.

The goal of the programming document is to facilitate the high quality standards established by the Utah System of Higher Education’s strategic plan. With expanded labs and critical adjacencies, these new spaces within the existing facilities will ensure the college is responsive to workforce needs.

This project will re-purpose three key types of space within the Main building:

1. Instructional Space.

Renovated/ modernized hands-on instructional environments for Automation Technology, Control Systems, and Robotics programs. The updated facilities combine “high-bay” or flexible layouts with adjoining smart lab spaces, engineered to accommodate industrial equipment, robotic arms, PLC (Programmable Logic Controller) stations, and integrated control hardware. The design will prioritize clear sightliness, adaptable utility distribution, and robust safety zoning, mirror contemporary industrial environments.

2. Academic Support Space.

The new suite will have dedicated offices and collaborative environments for instructors, the department head, and Instructional System Design (ISD) staff. The area integrates spaces equipped for professional development on learning management systems (LMS) and instructional technologies. Additionally, the

A - EXECUTIVE SUMMARY

layout will be flexible, and have collaborative zones designed to foster active engagement, project-based mentoring, and drop-in interaction between students and faculty.

3. Entrances, Student Access, and Safety Improvements.

Updates to the lab entries from the main corridor will be necessary to accommodate access for an increased number of students.

Additionally, informal study niches will integrate along primary pathways. Visual transparency into active lab environments will be maximized to support guided facility tours, promote program visibility, and enhance community engagement without compromising operational safety or instructional workflows.

This request also aligns with the Governor’s priority to grow Utah’s manufacturing sector.

The state is leading the nation in manufacturing job growth with a 12% increase from 2019 to 2023 - the largest jump of any state (U.S. Bureau of Labor Statistics). Meeting this goal requires a skilled workforce essential to modern manufacturing, which drives productivity gains that lead companies to expand and hire more skilled workers with higher-paying roles.

To continue to meet the demands of industry, the college must update and modernize.

Currently, manufacturing programs at BTECH are located in two different buildings, almost a block apart, and in facilities that have never been remodeled for instructional purposes. By relocating these programs into a centralized, purpose-renovated space alongside drafting, machining, and welding, the college can expand capacity, improve efficiencies, and better serve the growing demand for high-wage, high-skill manufacturing careers.

Automation Technology Programming A-8

Automation Technology Programming A-9

Space need and Project Approach

Automation Technology

Is designed as a highly practical, operations-focused training environment that mirrors the realities of modern manufacturing. Instruction combines classroom learning with hands-on skill development supported by flexible work stations, storage/supply, and dedicated areas for skill boss and capstone trainers. Spaces support instruction in pneumatics, repair techniques, maintenance of mechanical systems, electrical systems, fluid power systems and Electrical Motor Control Systems. Additionally, to implement and properly use a variety of precision measurement tools and procedures.

Control Systems and Robotics

The Automation and Controls Lab is designed as a dynamic, hands-on learning environment dedicated to foundational and advanced training in modern industrial automation.

Bringing together Programmable Logic Controllers (PLCs), industrial robotics, industrial networking, machine vision, and Human- Machine Interface (HMI) programming, the space bridges the gap between technical instruction and real-world industrial application.

Built around competency-based training developed in direct response to industry input, the facility ensures that educational outcomes remain tightly aligned with current technological standards and workforce needs.

05 STORAGE 475 NSF 1.15 550 GSF

TOTAL 7,665 NSF 1.51 11,720 GSF

01 FLEXIBLE LAB SPACE 3,500 NSF 1.65 5,780 GSF

02 ROBOTICS LAB 1,430 NSF 1.36 1,950 GSF

03 DANGER LAB 1.260 NSF 1.47 1,860 GSF

04 TEACHING STATION / OFFICE 1,000 NSF 1.48 1,480 GSF

The new Automated Technology lab will consolidate Automation Technology, Control Systems, and Robotics programs into a single, integrated facility designed for flexible teaching, hands-on instruction, and collaboration.

Automation Technology Programming A-10

Budget Estimate and Schedule

Based on a feasibility assessment completed in December 2025, the proposed 11,580-square-foot Advance Manufacturing Lab was initially estimated to have a construction cost of approximately $4.12 million, escalating to roughly $4.28 million when accounting for projected market conditions through 2026. Soft costs, including design, furnishings, and project support, are anticipated to range between 10 and 15 percent, with an approach that prioritizes reuse of existing equipment while strategically incorporating new assets to accommodate program growth. For a projected 2027 construction start, the total project cost is estimated at approximately $4.8 million, resulting in a modern facility that enhances hands-on instruction, applied research, and workforce readiness for manufacturing in Cache Valley.

DESCRIPTION UNIT COST TOTAL

PROJECT ESTIMATE CONSTRUCTION CONTROL CORPORATION 10/6/2026

PROJECT NAME……...…..BTECH REMODEL AUTOMATED TECH

ARCHITECT…..….….…….METHOD STUDIO 11,720 SF

STAGE OF DESIGN…..…..FEASIBILITY

CSI # DESCRIPTION QTY UNIT UNIT COST TOTAL

02 EXISTING CONDITIONS 6.24$ 73,140$

03 CONCRETE 2.40$ 28,128$

04 MASONRY -$ -$

05 METALS 6.48$ 75,887$

06 WOODS & PLASTICS 11.00$ 128,920$

07 THERMAL & MOISTURE PROTECTION 2.35$ 27,542$

08 DOORS & WINDOWS 15.86$ 185,910$

09 FINISHES 68.78$ 806,073$

10 SPECIALTIES 6.00$ 70,320$

11 EQUIPMENT -$ -$

12 FURNISHINGS 1.26$ 14,790$

13 SPECIAL CONSTRUCTION -$ -$

14 CONVEYING SYSTEMS -$ -$

21 FIRE SUPPRESSION 6.50$ 76,180$

22 PLUMBING 6.00$ 70,320$

23 HVAC 65.00$ 761,800$

26 ELECTRICAL 46.00$ 539,120$

27 COMMUNICATION 17.50$ 205,100$

28 ELECTRONIC SAFETY & SECURITY 7.00$ 82,040$

31 EARTHWORK -$ -$

32 EXTERIOR IMPROVEMENTS -$ -$

33 UTILITIES -$ -$

SUBTOTAL 268.37$ 3,145,271$

GENERAL CONDITIONS 10% 26.84$ 314,527$

BONDS & INSURANCE 2.0% 5.90$ 69,196$

OVERHEAD & PROFIT 3.5% 10.54$ 123,515$

DESIGN CONTINGENCY 15% 40.26$ 471,791$

TOTAL CONSTRUCTION COST 351.90$ 4,124,299$

LOCATION……….…..…….LOGAN, UT

BUILDING COST SUMMARY

(INCLUDES EXTERIOR ENVELOPE GLAZING UPGRADES)

AUG

NOV Schematic Design Begins (6 weeks)

Programming Doc. IssuedOCT

JUL

SEP

DEC

MAR

FEB

JAN

MAY

AUG

JUL

APR

JUN

SEP

26 Programming Begins

(2 Months)

25 Feasibility Study Submitted

DEC

DEC

JAN

NOV

AUG

NOV

OCT

MAY

JUL

SEP

DEC

JAN

FEB

MAR

APR

JUN

Design Development Begins (2 Months)

Construction Documents Begins (2.5 Months)

Permitting/Bidding (1 Month)

Construction Begins (8-9 Months)

Contractor Selected

Substantial Completion (April 2028)

Classes Begin Fall Semester 2029

2025 Feasibility Study

90% CD Owner Review

50% CD QC Review

50% DD QC Review

Project Completion/Move-In

**Schedule & dates are estimates and are subject to change.

Design (SD, DD, CD) - 10 Months Permitting & Bidding - 3 Months Construction Schedule - 18 Months

OCT

Automation Technology Programming A-11

The Main building at Bridgerland Technical College will remain in active use as the college’s primary facility for both instructional and non-instructional functions during the multiple proposed phases shown in this current feasibility study.

As a result of relocating healthcare programs into the new Health Sciences Building, space had become available in the Main building triggering a series of possible alignments.

This project seeks to remodel and re-purpose available space to support growing needs in:

Automation Technology | Electronics Technology | Machining Technology, Welding Technology | Collision Repair Technology | Student Services | Administration

The original Feasibility Study estimated the total cost of a partial building remodel at approximately $20 million. Due to construction inflation and phased implementation over several years, current estimates suggest the total project cost could now range around $30 million.

While the facility remains structurally sound, it will require targeted renovations to meet evolving program needs. These include internal remodels, improved entry areas, and updates to HVAC systems, many of which are over 20 years old. These systems fall under Capital Improvement needs, which will be addressed concurrently with each remodeling phase where feasible, to avoid rework and reduce overall cost.

Masterplan Phasing & Financing

Automation Technology Programming A-12

FINANCING SUMMARY

Based on the provided cost analysis (see chart on following sheet) the master planning architects are using between $240/sq. ft. - $325/sq. ft for remodeled space and $550 /sq.

ft. for new space (as direct construction costs).

This project is much more cost-effective than new construction with an overall construction cost of $316 sq ft when compared to new construction costs over $500 sq ft. In addition, 42% of future capital improvement needs would no longer be necessary when this project is funded (see appendix for third party cost estimate).

Upon completion of the remodel, existing faculty and staff will be relocated into the newly re-purposed space. However, because this project is designed to support enrollment growth and expand student support functions, additional program costs are anticipated. To support this growth, the college estimates the need for approximately ten new FTE positions within the first three years, at an average cost of $120,000 per position (including salary and benefits), for a total of $1.2 million. These positions will support instructional delivery, lab management, and student engagement functions. Potential funding sources for these expanded costs may include performance-based funding, growth funding, capacity-based models, or other higher education funding mechanisms.

Automation Technology Programming A-13

The proposed project masterplan will consist of 124,160 sq. ft. of renovated space and a relatively small addition of 10,000 sq. ft. of new construction attached to the existing Main building. The project will renovate and add new space for the Automated Manufacturing, Control Systems & Robotics, Machining Technology, Collision Repair Technology and Welding Technology programs. In addition, academic support and student services updates will create efficiencies and adjacencies for program and support functions.

Manufacturing is the Bear River region’s largest and fastest growing industry sector. It makes up 22% of the region’s workforce and 35% of the wages paid. The Bear River region has the lowest unemployment rate in the nation, which makes it essential to cultivate a pipeline of students into manufacturing, automation, and construction careers for local employers.

Main Building - Masterplan | Scope of work

Automation Technology Programming A-14

CONSTRUCTION-COST $26,906,003

FACILITY-COST $23,867,665

SOFT-COST $7,238,844

PHASE 1 - 5 COST ANALYSIS

SITE COST $772,386

TOTAL-COST $34,144,847

FURNISHING & EQUIPMENT $234,519

IT/AV & SECURITY $2,031,433

GENERAL CONDITIONS (6%) $1,614,360

BONDS & INSURANCE (2%) $570,407

DESIGN CONTINGENCY (15%) $4,035,900

OTHER COST (3.5%) $1,018,177

COMPLETE MASTERPLAN TEST-FIT

Before the Main building can begin the upgrades needed for their Manufacturing Hub, the college will be relocating their ISD Program and Assessment & Learning center to the north end of the building. This will vacate the space needed for Automation Technology.

**CD and Permitting currently under way**

Phase 1.0 - Instructional Systems Design & Testing Relocation

Programming Phasing Sequence

Automation Technology Programming A-15

The next step will include strategically demolishing interior walls, flooring, and exterior wall panels.

This will allow the college and design team to build properly sized, dedicated lab spaces, and bring in natural daylight into the space. Along with the interior updates, the design team will also work on upgrading/replacing mechanical units and power to serve all the new equipment.

Programming Phasing Sequence

Phase 1.2 - Automation Technology & Control System Robotics

Automation Technology Programming A-16

Relocated from West Building

B - EXISTING CONDITIONS

Site and Context - Existing Campus Plan

Bridgerland’s existing campus is made up of (4) separate structures. The Main building completed in 1984 is on the east side of campus. To the west, the college has had an opportunity to expand their campus through the purchase of the West Building in 2006 and the B and Innovation building in 2022. The West building serves as additional instructional space while the B & I building provides spaces for entrepreneurs and business development. Each building has a dedicated parking area and entry space, providing students with multiple options to access their programs. Lastly, the Health Sciences was added and completed in 2024 on the north east corner of the campus.

There is also a large swath of land between the building which will be developed as part of the campus masterplan in the future.

Access and Circulation

The Main building currently has about six public entries around the perimeter of the building. The south entry is predominantly used by the InTech Collegiate Academy , the west for the trade programs, the north to connect to the Health Sciences building and lastly, the east which acts as the main entry point.

With the current parking layout along all four sides of the campus, there is a limited amount

1) Main building 2) West Building 3) B&I Building 4) Health Sciences Building

FUTURE CAMPUS

EXPANSION

Automation Technology Programming B-1

FUTURE CAMPUS

EXPANSION

Automation Technology Programming B-2

Site and Context - Program Re-location of pedestrian access and visual exposure to the main entries. The architecture and design currently lacks a level of presence and transparency that would allow students, faculty, and the surrounding community to feel engaged with the college.

Planned Visual Upgrades

The feasibility study and Programming document proposes to improve the college’s visual aesthetics and transparency to the surrounding community. An upgraded facade near the east entry and future Advance Manufacturing lab (increased glazing & branding) will allow the college to increase the amount of daylight entering the building.

Program Re-location

The current Advanced Manufacturing program is housed in the West building and is about 7,000 SF. The new proposed location will allow the program to expand close to 11,000 SF, which will provide a larger lab space with daylight, program exposure, more stations, and an expanded robotics lab.

1) Main building 2) West Building 3) B&I Building 4) Health Sciences Building

Existing Campus Plan

The existing Main Building houses a diverse mix of programs arranged by quadrant:

• North: Transportation and Food Services

• West: Construction and Manufacturing

• East: Business and Design Development

• South: Intech High School

Due to this programmatic complexity, support spaces; restrooms, data closets, and janitorial closets— have been added incrementally on an as-needed basis, resulting in complex series of spatial adjacencies.

The facility has undergone several recent improvements, including architect-designed renovations to the Culinary Arts and Meat Services spaces. Additionally, the college is actively upgrading outdated finishes in-house and systematically replacing rubber corridor flooring with terrazzo.

Automation Technology Programming B-1

Automation Technology Programming B-4

Architectural Character

The existing campus is made up of four distinct styles, due to the college’s growth and purchase of numerous buildings.

• The Main building is a tilt up system with large aggregate texture and ribbed metal panel additions.

• The West building has a stucco finish with a lower metal roof.

• The Business & Innovation building is an engineered steel building with ribbed metal cladding and a brick addition.

• The Health Sciences building is the newest building with a contemporary design. It uses brick, wood, and metal to create a new design language for the campus as a whole.

That is modern and open to invite students and visitors in.

Which uses finishes and materials to relate back to the Health Sciences building and create a unified palette.

That represents the colleges growth and emerging technologies.

We Envision a Design...

Automation Technology Programming B-5

Interior Conditions

Existing ISD and Testing (Main Building)

Existing Robotics and Control Systems (West Building)

The future location for Advance Manufacturing is occupied by ISD and Testing . The space has a mixtures of 10’ ceiling, and exposed 16’-18’ foot ceilings. Floors are predominantly carpet with rubber base and painted walls (Gyp. and

CMU).

The current location for Advance manufacturing Has 10’ ceilings through out their suite, with a mix of carpet and linoleum flooring, rubber base and Painted Gyp. wall. Power is provided through three separate methods; typical wall outlets, ceiling chords, and power poles.

C - BUILDING REQUIREMENTS

Building Code Analysis & Strategy

Applicable Codes & Standards

•2024 International Building Code (IBC)
•2024 International Existing Building Code (IEBC)
•ICC A117.1 Accessibility
•DFCM High Performance Building Standards (HPBS)

Type of Construction (IBC Table 601)

• Type IIB (Sprinklered)

Occupancy Types (IBC Chapter 3)

•Educational (Classroom)B (Section 304.1)
•Offices / ConferenceB (Section 304.1)
•Educational (Classroom)E (Section 305.1)
•Amenity (Flex & Cafe)A-3 (Section 303.1)
•Shops & LabsF-1 (Section 306.1)
•Storage (Mechanical & Support)S-1 (Section 311.1)

** Per IBC 508.3 the building is determined as a non-separated mixed-use occupancy. However, the building will need to be separated to meet allowable building requirements. (See diagram in the following spreads.)

Fire Sprinklers (IBC Chapter 9)

• Sprinklers required: Automatic Sprinkler System (NFPA 13)

Frontage Increase (IBC 506.3)

Assume a frontage increase of 0.75

Allowable Building Area (IBC 508.4.2)

Maximum allowable square footage is calculated using the most restrictive area for a non-separated mixed-use building per IBC 506.2.2 and 508.1.

Automation Technology Programming C-1

Building Code Analysis & Strategy Cont.

Allowable area includes the frontage area increase per IBC 506.3. The following quantities below include all phases. Occupancy A-3 and S-1 are counted as accessory spaces.

OccupancyProposedAllowedRatio
(With Frontage Increase)(X < 1.0)
Occupancy A-36,741 SFN/A
Occupancy B87,170 SF109,250 SF
Occupancy F-188,104 SF73,625 SF
Occupancy E26,013 SF68,875 SF
Occupancy S-12,740 SFN/A
210,768 SF68,875 SF3.06

The ratio after adding up all areas should be less than or equal to 1.0. The current ratio of the existing building with the additions is calculated at 3.06. To make the Main building compliant, the design team recommends separating it into five separate areas through the use of fire walls (Per IBC 706.4).

As mentioned previously, to meet code, the Main building should be separated to meet occupancy building requirements. This can be achieved by building new fire walls shown as a dashed red line in the floor plan above. The fire walls need to align with roof parapets to make sure the wall extends from the slab past the roof to create a full separation between spaces.

Education Occ. (E)

Business Occ. (B)

Factory Occ. (F1)

Amenity Occ. (A3)

Storage Occ. (S1)

Fire Wall

**The current program would fall under Building 02.**

Automation Technology Programming C-2

The “first building” will be made up by Intech, falling under an (E) occupancy with a total square footage of +/-

26,000 SF.

BUILDING 02

(B) - 29,320 SF

The “second building” will be made up of B and F1 occupancy with a total square footage of +/- 59,600 SF.

BUILDING 01

(E) - 25,986 SF

(F1) - 30,307 SF

BUILDING 03

(F1) - 32,354 SF

BUILDING 04

(B) - 16,775 SF

The “fourth building” will be made up of B , A and F1 occupancy with a total square footage of +/- 52,100 SF.

BUILDING 05

(A3) - 7,163 SF

The “fifth building” will be made up A3 occupancy with a total square footage of +/- 7,200 SF.

(A3) - 2,972 SF

(5.5% of building footprint)

(F1) - 25,443 SF

(B) - 36,423 SF

The “third building” will be made up of B and F1 occupancy with a total square footage of +/- 67,000 SF.

(S1) - 5,197 SF

(7.5% of building footprint)

Automation Technology Programming C-3

Architectural Narrative

VISION

BTECH leadership aims to re-envision their existing Main building by approaching the proposal in two different ways.

On one hand, the building must meet the pragmatic need for additional instructional space that is flexible and efficient to maximize student enrollment. The college wants to focus on the development of a Manufacturing hub by remodeling 14,500 square feet of existing spaces and dedicated an area of the building to Automated Manufacturing, and Control Systems and Robotics.

On the other hand, the school understands the exterior of the building needs to be revitalized to improve visibility from a busy thoroughfare. The college aims to enhance student & community engagement through updated entries, clear way finding and quick access to student support spaces.

The design of technical college facilities has seen vast improvement since BTECH initially was founded in 1971. There has been a large push to move away from utilitarian type facilities towards facilities that place technical education as a direct alternate and pathway to degree granting.

This aligns with the state of Utah’s public policy makers to legitimize the mission of technical colleges. Each year, enrollment keeps growing throughout all institutions due to the investment of the state. Since BTECH opened their first, modern, dedicated instructional building, they have seen their programs grow as much as 70%.

The contrasting approach between pragmatic & efficient flexibility and improved community presence defines the design challenge in the proposed feasibility study. The existing Main building must work within a defined perimeter while expanding student and community spaces to improve their overall outreach.

PROGRAMS ON DISPLAY

BTECH seeks to improve on their existing building by transforming the traditionally isolated educational environment into one that is open, visible and connected. The goal is to showcase the hands-on learning being provided by the college. This will allow prospective students, industry partners, and policy makers to be more clear about the learning and technical activities on campus. Interior glazing and open sight lines should be used intentionally to showcase instructional spaces (particularly labs) while maintaining safety, privacy and acoustical control. Faculty and service spaces should be located to support this openness, reinforcing accessibility and visibility without distraction.

AESTHETIC CHARACTER

With the recent completion of the Health Sciences Building, BTECH now has a foundation for finishes and branding identity. The existing Main building will bring a similar character while successfully blending in the utilitarian shop

Automation Technology Programming C-4

Automation Technology Programming C-5 aesthetics. The building’s aesthetics should reflect its programmatic purpose-learning into an elevated industrial character that brings practical benefits such as durability and ease of maintenance.

The space should be exposed, with an honest framework where architecture and technology seamlessly integrate. Along with exposed systems and building infastrucure on the ceiling, the design team should layout Linear lighting elements and continuous datum lines across wall paneling reinforce concepts of spatial grid systems, automation precision, and digital fabrication pathways. The ceiling can also incorporate PET Felt panels or Tectum panel to contorl acoustics and add branded colors to the space.

The suite should also be visually transparent and maximizes the amount of glazing to the corridor and exterior envelope.

The ground plane in active lab spaces should be a polished concrete. Providing a heavy duty, high abrasion, impact resistant surface capable of supporting high point loads and machinery re-positioning.

Near delicate eletronic assembly spaces, an epoxy floor is a potential option to prevent Electrostatic discharge.

ACOUSTICAL CONCERNS

As a State of Utah higher education facility, strong consideration for acoustical separation and sound control must be incorporated into the design. The three primary environments requiring acoustical attention are labs, classrooms, and offices. Of particular concern are adjacencies between labs and classrooms, where high-noise activities such as cutting, threading, welding, or sawing may occur concurrently with lectures or self-paced learning.

To mitigate sound transmission between active and quiet zones, all partitions separating these environments will be designed with appropriate Sound Transmission Class (STC) ratings, Impact Insulation Class (IIC) ratings for multi-level adjacencies, and background noise level targets in accordance with ANSI S12.60 / FGI Guidelines / DFCM Design Requirements.

Wall Construction & Sound Isolation

• Interior partitions separating labs from classrooms shall achieve an STC 60–65 rating using double-stud or resilient channel assemblies with multiple layers of gypsum board and acoustical insulation in the cavity.

• Classroom-to-classroom partitions should achieve an STC 50–55 minimum.

• Partitions separating classrooms from corridors or office suites should achieve

STC 45–50.

Wall Construction & Sound Isolation (cont.)

• All assemblies will extend to the structure above (slab or deck), with sealed perimeters to eliminate flanking paths.

• MEP penetrations will be minimized and acoustically sealed with non-hardening acoustical caulk or putty pads at outlet boxes.

Doors, Windows, and Openings

• Doors into labs and classrooms will utilize solid acoustical cores (minimum STC 35– 40), equipped with perimeter seals and automatic door bottoms.

• Vision glazing, where used, should employ laminated glass with an STC rating of 35 or higher, with perimeter seals to maintain performance.

• Where interior glazing is used for

“programs on display,” spatial offset or vestibule design may help maintain acoustical separation while preserving visibility.

Mechanical & Structural Noise Control

• Mechanical equipment rooms and major ductwork should not be directly adjacent

Architectural Narrative Cont.

Automation Technology Programming C-6

Automation Technology Programming C-7 to classrooms or offices.

• Airborne and structure-borne noise from mechanical systems shall not exceed NC/ RC 35–40 in classrooms, NC/RC 40–45 in labs, and NC/RC 30–35 in offices.

• Supply and return ducts shall be lined for a minimum of 10 feet from the fan or terminal device, and vibration isolators shall be used on mechanical equipment supports.

• Structure-borne vibration from shop equipment (e.g., welders, grinders, compressors) shall be isolated via inertia bases or vibration-damping mounts.

Interior Finish & Room Acoustics

• Classrooms should be designed for a reverberation time (RT60) of approximately 0.5–0.7 seconds, achieved through acoustic ceiling tile systems, wall panels, and soft finishes.

• Labs and shop spaces should maintain RT60 values under 1.0–1.2 seconds, using high-durability acoustic baffles, perforated metal panels with absorptive backing, or ceiling clouds where feasible.

• Office and conference spaces should be treated for speech privacy, targeting Articulation Index (AI) ≤ 0.20 between adjacent rooms.

Summary

The overall goal is to achieve a balanced acoustic environment that supports instruction, safety, and comfort while reinforcing visibility and openness. By combining proper wall design, door and glazing detailing, and mechanical noise mitigation, the facility will meet DFCM standards for sound isolation, occupant comfort, and long-term maintainability.

DFCM DESIGN STANDARDS

In keeping with the spirit of the DFCM Design Standards, each deviation is being evaluated through the lens of life-cycle alignment— identifying which portions of the building should meet a 50-year design life and which are expected to be more adaptable, reconfigurable, or replaceable in the near term. Core building systems and enclosure elements are expected to meet a higher standard of durability and maintainability. Interior partitions, finishes, and furnishings, by contrast, may embrace a more flexible and modular approach to support evolving program demands.

All proposed departures from the Standards are to be fully documented and processed through the formal DFCM variance procedure as outlined in Section 8.1-C of the Design Requirements. This includes clear justification demonstrating that the variance supports project intent, maintains or improves performance, and aligns with DFCM’s broader goals of life-cycle stewardship, operational efficiency, and long-term public value.

Architectural Narrative Cont.

Automation Technology Programming C-8

See the following narratives supplemental design criteria for additional detail regarding mechanical, electrical, and plumbing system requirements that differ from the Design Standards.

HIGH PERFORMANCE BUILDING

STANDARD (HPBS)

In alignment with the DFCM High Performance Building Standard (HPBS), the project will prioritize design-first strategies—using passive and low-energy architectural moves to reduce demand before adding mechanical complexity.

Thoughtful placement of openings, and climate-specific analysis for Logan, should inform design decisions early and often. These strategies carry minimal upfront cost yet can significantly lower loads on mechanical and electrical systems, contributing to reduced operational costs and long-term resource stewardship.

Mechanical zoning is expected to play a central role in supporting efficient HVAC and envelope strategies. The project’s two primary functional zones—classrooms and labs—will be differentiated to align with their unique comfort and performance needs. By maintaining some degree of physical and mechanical separation, and higher-performance HVAC systems can be focused on classroom and office areas where occupant comfort expectations are greatest.

The labs, by contrast, can rely on low-energy strategies as recommend by the consultant and engineers. These proposed systems could potentially reduce energy intensity while supporting flexibility and durability, consistent with HPBS guidance for performance-driven, maintainable design.

Zoning can also yield envelope efficiencies.

Where high comfort is required, such as in classrooms, offices, or multipurpose spaces, prescriptive assemblies with continuous insulation and vapor-permeable air barriers will be employed. In contrast, the lab areas—where large doors and variable openings naturally limit envelope performance—may utilize code-minimum assemblies, balancing investment with functional need.

Introduction

The original BTECH building was built in 1970 by Wurlitzer Company. The primary structural system consists of open web steel joists supported by steel trusses or wide flange steel beam girders. Typical columns are steel wide flange sections. The roof deck is 1 ½” x 22 gage steel deck.

The lateral force resistance for the building was provided by steel channel section braced frames located in strategic exterior and interior stud walls. New braced frames were installed as part of the phase 1 renovations dated 1985. In addition to the new steel braced frames the roof diaphragm was reinforced by adding diagonal steel angles below the roof deck to transfer lateral forces to the braced frame elements. See attached sheet S1 from the Phase 1 remodel documents.

The exterior enclosure of the building consists of 6” thick exposed aggregate concrete tilt panels.

These panels are very lightly reinforced with welded wire mesh. Anchorage of the panels is provided on the vertical edges of the panel to building columns behind the panels. These panels are not intended to participate in the resistance of lateral loads, nor do they support vertical building loads. Their only function is building enclosure. The typical floor slab consists of a 5” thick concrete slab reinforced with welded wire mesh.

ANTICIPATED MODIFICATIONS TO

PRIMARY STRUCTURE

There are two main modifications anticipated to the primary structure/enclosure. The first is the desire to add new windows in perimeter walls to enhance natural light in the building.

To provide penetrations through these panels of any appreciable size, it will be necessary to provide structural reinforcing behind the panels. We anticipate a steel HSS tube frame will be provided at all new penetrations through the concrete tilt panels. See attached details D1, D5 and C1 for a typical reinforcing frame and associated anchorage to the panel. These details are schematic in nature and have not been engineered for any specific opening size.

The second anticipated modification to primary structure will be the addition of supplemental roof framing as required to support new rooftop mechanical units. It is not likely that existing roof framing can support any additional mechanical units of substance. Elements such as light exhaust fans (or similar) weighing100-200 lbs can likely be accommodated without strengthening. We anticipate that the most cost-effective method to provide additional roof capacity will be to sister new open web joists alongside existing roof joists to carry the new mechanical units. These new joists would generally come in two sections and be connected in the field to facilitate installation from below. The installation of new roof framing members will require the removal and replacement of all ductwork, piping, and conduit that crosses the new joist.

C - BUILDING REQUIREMENTS

Automation Technology Programming C-9

Structural Narrative

Where the installation of additional elements is deemed unfeasible, in place strengthening of existing members can be explored. This type of in-place reinforcing is very labor intense and is generally significantly more costly than adding additional framing members. The placement of any new mechanical units and associated roof deck penetrations will need to be coordinated with the location of the diagonal angle bracing that was installed in the phase 1 remodel project.

Interruption or removal of these diagonal bracing elements would trigger the need for potentially costly additional structural modifications. See attached details 3 and 4 for typical angle frames required at new roof deck penetrations.

**Structural Narrative is based of the feasibility study completed in

December 2025** DESIGN CONDITIONS

Structural Narrative Cont.

Automation Technology Programming C-10

C - BUILDING REQUIREMENTS

TYPICAL STEEL TUBE CONNECTION TO EXISTING WALL (HEAD)

TYPICAL OPENING RE-ENFORCING EXISTING WALL W/ STEEL TUBES

TYPICAL STEEL TUBE CONNECTION TO EXISTING WALL (JAMB PLAN VIEW)

Automation Technology Programming C-11

NEW FRAMING AT EXISTING STEEL JOISTSPLAN VIEW NEW FRAMING AT EXISTING JOIST

Mechanical & Plumbing Narrative

Automation Technology Programming C-12

OUTSIDE DESIGN CONDITIONS:

Use the following climate data from ASHRAE Fundamentals 2025 Climatic Design Information.

Elevation 4,454 FT

Summer Design Dry Bulb Temp (ASHRAE 0.4%) 94.9 deg. F

Summer Mean Coincident Web Bulb (ASHRAE 0.4%) 61.6 deg. F

Cooling Tower Wet Bulb Temp. (ASHRAE 0.4%) 65.0 deg. F

Winter Design Dry Bulb Temp. (ASHRAE 99.6%) -4.5 deg. F

General Occupancy (Offices, Teacher Stations, Classrooms):

Design Temperature

Summer75 +/- 2 deg.F
Winter72 +/- 2 deg.F

Cooling & Heating Source VAV Rooftop Air Handling Unit

Teaching Lab/Shop (Flex Lab / Robotics Lab / Skills Boss):

Design Temperature

Summer75 +/- 2 deg.F
Winter72 +/- 2 deg.F

Cooling & Heating Source VAV Rooftop Air Handling Unit

Danger Lab:

Design Temperature

Summer75 +/- 2 deg.F
Winter72 +/- 2 deg.F

Cooling & Heating Source VAV Rooftop Air Handling Unit

Special Conditions Negative Air Pressure;…

This is the start of the file's text. The full file is on GovTribe.