6-2- CURLY HOLLOW BID TERMS.pdf
PDF 69 KB Posted
- Attached to
- IFB - CURLY HOLLOW ADVENTURE PARK
- Solicitation number
- 26-285
- Issued by
- Washington County, Utah
About this file
This document contains the bid terms for the Curly Hollow Adventure Park construction project, issued by the City of St. George, Utah under Reference Number 26-285. The project involves the construction of a community park featuring climbing walls, playground equipment, a splash pad, pump track, and a 400-meter track. Bidders must submit proposals in compliance with the Contract Documents, drawings, specifications, and related documentation. Each bidder must certify that the bid was prepared independently without consultation with competitors. All work is subject to the City's approval, with the City maintaining decision-making authority over material quality, suitability, acceptability, and contract fulfillment. The contract documents referenced do not specify explicit response dates, due dates, site visit requirements, or bidder conference details within this particular bid terms section.
The bid must be accompanied by a bid bond equal to 5 percent of the bid amount, issued by a surety company licensed to do business in Utah and in a form acceptable to the City. One hundred percent payment and performance bonds are required upon award. Liquidated damages are assessed at $250 per calendar day for failure to complete work within the specified contract time and $250 per day for failure to repair deficiencies within 10 days of notification, with the latter charges cumulative to overall contract time penalties. The City reserves the right to reject any or all proposals or waive any formality or technicality in its interest. No set-asides, incumbent information, or specific funding sources are identified in this bid terms document.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TERMS
Project Name: Curly Hollow Adventure Park
Reference No: 26-285
Proposal of (“BIDDER"), organized and existing under the laws of the State of doing business as a corporation, partnership, or an individual (circle applicable status), to the City of St. George ("CITY"). Pursuant to and in compliance with the Public Notice, BIDDER hereby proposes to perform all Work for the above named Project in strict accordance with the Contract Documents, BIDDER'S Instructions, Drawings, Specifications, and other documents related thereto, the undersigned, having familiarized themselves with the existing conditions on the site and the conditions under which the work on the Drawings and in the Specifications is to be done, hereby proposes to furnish all labor, materials, equipment, incidental items, permits, fees, and services to perform all specified work on the above named project.
By submission of this BID, each BIDDER certifies, and in the case of a joint BID each party thereto certifies as to his own organization, that this BID has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this BID with any other BIDDER or with any competitor.
All Work shall be in strict accordance with the Contract Documents and documents issued thereto and shall be installed at the price/prices set forth in the Contract Documents.
Bidder acknowledges that all Work shall be done subject to CITY’S approval. Decisions and questions as to the quality, suitability, and acceptability of the materials, interpretation of drawings and specifications, and acceptable fulfillment of the Contract by the BIDDER shall be made by CITY.
Of particular importance to be considered in the BID are the following:
CONTRACT TIME AND LIQUIDATED DAMAGES
The WORK is to be performed within the specified CONTRACT TIME. If the CONTRACTOR shall fail to complete the WORK within the CONTRACT TIME, or extension of time granted by the CITY, then the CONTRACTOR will pay the CITY LIQUIDATED DAMAGES assessed at the rates established as follows:
a. $250.00 (dollars) per day for each calendar day that the CONTRACTOR shall be in default after the CONTRACT TIME.
b. $250.00 (dollars) per day for failure to make repairs to deficiencies in the work within 10 days of notification to repair.
The rates specified in ‘b.’ above are cumulative and are in addition to LIQUIDATED DAMAGES assessed in association with the overall Contract Time as listed in ‘a.’ above.
Additional information on LIQUIDATED DAMAGES is provided in the GENERAL
CONDITIONS.
File details come from the government source that posted it. Updated .