This Information for Bidders document is issued by the City of St. George, Utah for the construction of Curly Hollow Adventure Park, a community park project located at 2200 Tonaquint Drive, St. George, Utah 84770. The project consists of earthwork, concrete flatwork, retaining walls, asphalt paving, utilities, landscaping, and irrigation to support various amenities including a restroom building, playground, pickleball courts, obstacle course, splash pad, artificial turf field, running track, hammock area, climbing areas, and walking paths. The geotechnical investigation has identified subsurface conditions with expansive clay and undocumented fill materials requiring specialized foundation and subgrade preparation measures, with close coordination needed between the contractor and geotechnical engineer during construction. The bid opening date is November 13, 2026, with a mandatory pre-bid meeting scheduled for December 1, 2026 at 1:00 p.m. on-site; failure to attend will result in automatic disqualification. Questions are due by December 4, 2026, and bid submissions close on December 10, 2026 at 2:00 p.m. via sgcity-utah.bonfirehub.com. The City intends to commence construction within 30 days of issuing the Notice to Proceed and complete the project within 182 days.

Bids will be evaluated and ranked using the following criteria: Work Qualification demonstrating a minimum of three similar past projects (10 points); St. George City past performance evaluations (5 points); Bid Schedule pricing (45 points); Construction Schedule demonstrating resources and ability to meet timeline requirements (10 points); and Geotechnical Response addressing the project's expansive soils and undocumented fill challenges (30 points). Each bid must include a 5 percent bid bond payable to the City, with performance and payment bonds each required at 100 percent of the contract price from an approved corporate surety. Contractors must demonstrate the capability to perform at least 30 percent of the contract amount using their own workforce and must list all proposed subcontractors, with the City retaining the right to reject any bid if the contractor or subcontractors lack required experience. Award will be granted to the highest-scoring responsible bidder, who must execute the agreement and obtain all required bonds, insurance certificates, and legal work status documentation within ten calendar days of the Notice of Award.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

26-285 INFORMATION FOR BIDDERS

The City of St. George, hereinafter called “CITY,” shall receive BIDS for the following:

Project: Curly Hollow Adventure Park

Project Address: 2200 Tonaquint Drive, St George, Utah 84770

1. Project Description:

The project consists of constructing a community park on an undeveloped parcel. A geotechnical investigation identified subsurface conditions consisting generally of undocumented fill overlying native clay, sandy clay, claystone, weathered shale, cemented silty sand, and sandstone. Portions of the undocumented fill and underlying materials include processed mudstone/claystone materials that are known to exhibit expansive characteristics.

The geotechnical report provides multiple foundation support and subgrade preparation recommendations based on the type of structure being supported. Close coordination with the geotechnical engineer will be required during construction, including field observations to verify that recommended subgrade preparation and foundation support measures have been implemented and that suitable subgrade conditions have been achieved.

Anticipated work consists of earthwork, concrete flatwork, retaining walls, footings, etc., asphalt, landscape and irrigation, utilities and more. Amenities include a restroom building, playground, pickleball courts, obstacle course, splash pad, artificial turf field, running track, hammock area, climbing areas, walking paths, etc. Coordination will be required for some amenities installed by others.

2. BID TIMELINE:

BID OPENING DATE: November 13, 2026

PRE-BID MEETING DATE, TIME & LOCATION: December 1, 2026, at 1pm. On site

MANDATORY: YES

Failure to attend a mandatory Pre-Bid meeting will result in automatic disqualification

QUESTIONS DUE DATE: December 4, 2026

SUBMISSION CLOSE DATE: December 10, 2026, at 2pm

2. All BIDS must be submitted via sgcity-utah.bonfirehub.com. Any BID may be edited or withdrawn prior to the above scheduled time for the opening of BIDS. Any BID received after the time and date specified shall not be considered. No BIDDER may withdraw a BID within 60 days after the actual date of the opening thereof. Should there be reasons why the contract cannot be awarded within the specified period, the time may be extended by mutual agreement between the CITY and the BIDDER.

https://sgcity-utah.bonfirehub.com/

3. Each BID must be accompanied by Work Qualification, Geotechnical Response, Bid

Schedule, and Construction Schedule. Contractors will be ranked and project awarded based on the following item criterion.

• Work Qualification – A minimum of three (3) past projects that are similar in nature

(see Paragraph 9 below). 10 points possible

• St. George City past performance evaluations (internal review only). 5 points possible

• Bid Schedule. 45 points possible

• Construction Schedule – The contractors proposed schedule shall demonstrate resources and ability to complete the project in accordance with Paragraph 6, 7, 10 and 11 below. Construction schedule shall be submitted in PDF format. 10 points possible

• Geotechnical Response – The contractor shall demonstrate understanding of the project and the geotechnical challenges for this project, and provide a proposal to address these challenges as outlined in paragraph 8 below. Response shall be submitted in PDF format. 30 points possible

4. BIDS shall be based on the BID SCHEDULE UNIT PRICES and shall include all work called for by the plans and specifications and bidding documents. In the case of a discrepancy in the extension of a line item, the unit price shall govern. In the case of a difference between the amount written in words and the amount written in figures, the written words shall govern. BIDDERS must satisfy themselves of the accuracy of the estimated quantities, where given, by examination of the site and a review of the drawings and specifications including

ADDENDA. After BIDS have been submitted, the BIDDER shall not assert that there was a misunderstanding concerning the quantities of WORK or of the nature of the WORK to be done. UNIT PRICES as called for in the BID Schedule shall be submitted to cover all additions and deductions in the scope of the WORK. CITY has the right to reduce or remove items from the project.

5. Bid Schedules are included in the Requested Information for a Base Bid and any alternates. It is the CITY'S intent to award this contract based upon the Base Bid and any selected

Alternates. The CITY, in consultation with the ENGINEER, shall add bid items at the City’s sole discretion. The low bid shall be considered to be the bid which has the lowest base bid items selected by the CITY for inclusion in the final Agreement.

6. The CONSTRUCTION SCHEDULE is particularly important to the CITY. The BID shall include a construction schedule prepared using spreadsheet or scheduling software, showing all main work categories, including at least clearing and grubbing, grading, and drainage, building construction, building interiors, concrete work, asphalt paving, site amenities, and planting and irrigation.

7. It is the CITY'S intention to commence construction no later than 30 days of issuing the

Notice to Proceed and to complete the project within 182 days.

8. Understanding the GEOTECHNICAL REPORT is particularly important to this project. The

BID shall include a proposal describing the BIDDER’s approach to addressing the geotechnical conditions and construction requirements outlined in the Geotechnical Report included in the Bid Documents. The proposal shall address the primary geotechnical considerations, including expansive soils and undocumented fill, required over-excavation and replacement with non-expansive structural fill, varying mitigation depths for the different project elements, excavation and handling of variable soil and bedrock conditions, structural fill sourcing, placement, moisture conditioning, and compaction, and coordination with the

Geotechnical Engineer for required observations, testing, and adjustments to mitigation limits based on conditions encountered during construction.

9. The BIDDER shall list work experience on similar relevant projects in the Bid Forms which shall include a minimum of three projects of similar cost, complexity, and duration, including references for each project listed. The CITY reserves the right to reject any and all bids where it deems the BIDDER lacks the specific experience necessary to perform the Work.

10. The BIDDER shall demonstrate that it has the capability to complete the required work utilizing its own workforce to perform at least 30% of the Contract Amount in the Bid

Schedule(s).

11. The BIDDER shall list all subcontractors proposed for use in Bid Forms. The CITY reserves the right to reject any and all bids where it deems the BIDDER’s subcontractors lack the specific experience necessary to perform the Work. The BIDDER may not substitute subcontractors prior to – or during – construction without prior approval of the CITY.

12. The CITY shall provide to BIDDERS prior to BIDDING, all information which is pertinent to, and delineates and describes, the land owned, and rights-of-way acquired or to be acquired.

CONTRACT DOCUMENTS INCLUDING BONDS:

1. The CONTRACT DOCUMENTS contain the provisions required for the construction of the project. Information obtained from an officer, agent, or employee of the CITY or any other person shall not affect the risks or obligations assumed by the CONTRACTOR or relieve him from fulfilling any of the conditions of the contract.

2. Each BID must be accompanied by a BID bond payable to the CITY for five percent of the total amount of the BID. As soon as the BID prices have been compared, the CITY will return the BONDS of all except the three lowest responsible BIDDERS. The BID BOND of the successful BIDDER will be retained until the payment BOND and performance BOND have been executed and approved and the Notice to Proceed has been issued, after which the BID BOND will be returned. A certified check may be used in lieu of a BID BOND.

3. A performance BOND and a payment BOND, each in the amount of 100 percent of the

CONTRACT PRICE, with a corporate surety approved by the CITY, will be required for the faithful performance of the contract.

4. Attorneys-in-fact who sign BID BONDS, payment BONDS or performance BONDS must file with each BOND a certified copy of their power of attorney with the effective date.

AWARDING CONTRACT:

1. The CITY may waive any informalities, minor defects, or reject any and all BIDS.

2. The CITY may make such investigations as it deems necessary to determine the ability of the

BIDDER to perform the WORK, and the BIDDER shall furnish to the CITY all such information and data for this purpose as the CITY may request. The CITY reserves the right to reject any BID if the evidence submitted by, or investigation of, such BIDDER fails to satisfy the CITY that such BIDDER is properly qualified to carry out the obligations of the

Agreement and to complete the Agreement and to complete the WORK contemplated therein.

3. The BIDDER, by evidence of the submission of the BID, acknowledges that BIDDER and

BIDDER’S subcontractors meet or exceed the specified requirements for related project experience and insurances, and that should the CITY discover at any time evidence to the contrary, BIDDER agrees to withdraw BIDDER’S BID and to allow the CITY to award the

CONTRACT to the next lowest responsible BIDDER. BIDDER must have the proper contractor’s license for this type of project prior to bidding on the project. It is solely

BIDDER’S responsibility to comply with all applicable federal, state, and local laws, regulations, and ordinances that affect this project.

4. Award will be given to the highest scoring responsible BIDDER as determined by the City using the criteria contained in City ordinances governing the award of contracts. The BID shall be awarded on the condition that the BIDDER provides all required documents prior to the NOTICE TO PROCEED being issued. Failure to provide the required documents shall be considered a default on the Contract and may result in the CITY awarding the Contract to another BIDDER in addition to other legal remedies.

5. The party to whom the contract is awarded will be required to execute the Agreement and obtain the performance BOND, the payment BOND, the Certificate of Legal Work

Status for the BIDDER and all Subcontractors and the certificate of insurance within ten (10) calendar days from the date when NOTICE OF AWARD is delivered to the BIDDER. The

NOTICE OF AWARD shall be accompanied by the necessary Agreement and BOND forms.

The bid shall be awarded on the condition that the BIDDER provides all required documents prior to the NOTICE TO PROCEED being issued. Failure to provide the required documents shall be considered a default on the Contract and may result in the City

Awarding the CONTRACT to another BIDDER in addition to other legal remedies.

6. In case of failure of the BIDDER to execute the Agreement or is found to be ineligible or becomes ineligible to meet all the requirements for the project, the CITY may at its option consider the BIDDER in default, in which case the BID BOND accompanying the proposal shall become the property of the CITY.

7. Upon receipt of acceptable performance BOND, payment BOND, insurance certificates and

Agreement signed by the party to whom the Agreement was awarded, the CITY shall sign the Agreement and return to such party an executed duplicate of the Agreement. Should the

CITY not execute the Agreement, the BIDDER may by WRITTEN NOTICE withdraw the

BIDDER’S signed Agreement. Such notice of withdrawal shall be effective upon receipt of the notice by the CITY.

8. The NOTICE TO PROCEED shall be issued immediately upon the following occurring:

providing the executed Agreement to the CITY, providing the performance and payment

BONDS to City, and providing the insurance certificates to City. Should there be reasons why the City wants to delay and the NOTICE TO PROCEED cannot be issued within such period the time may be extended by mutual agreement between the CITY and

CONTRACTOR. If the NOTICE TO PROCEED has not been issued within the ten (10) day period or within the period mutually agreed upon, the CONTRACTOR may terminate the Agreement without further liability on the part of either party.

9. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout.

10. Each BIDDER is responsible for inspecting the site and for reading and being thoroughly familiar with the CONTRACT DOCUMENTS. Failure or omission of any BIDDER to do any of the foregoing shall in no way relieve any BIDDER from any obligation in respect to his BID.

File details come from the government source that posted it. Updated .