6-105169 , 105170 105868 - AFI@4PS - SPECS.pdf
PDF 15 MB Posted
- Attached to
- ITB - Athletic Field Improvements at Rockwood, Rolling Hills, Northwest Community and Gateway Parks
- Solicitation number
- 26-0273
- Issued by
- Tarrant County, Texas
About this file
This is a Standard Construction Specification Document and Invitation to Bidders issued by the City of Fort Worth, Texas, for Athletic Field Improvements at four parks: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks (Project Nos. 105169, 105170, and 105868). The scope of work includes installation of remote equipment controllers at Gateway Park, rehabilitation of softball infields at Gateway and Rockwood Parks, construction of bleacher shading structures at Northwest Community Park, and alternate lighting installation and grass replacement at Rockwood Park. The project encompasses ten bid units with various line items including sod installation, infield clay material, shade structures, irrigation improvements, and electrical work. Electronic bids are due by August 27, 2026, with public bid opening at 2:00 PM CST in the City Council Chambers. A pre-bid conference will be held on August 12, 2026, at 10:00 AM via web conferencing. Bidders must indicate intent to bid by a specified deadline to receive conference invitations and addenda. The contract completion timeline requires the work to be finished within 120 calendar days after the Contract Time commences, plus any approved extensions. Award of the contract will be made to the lowest responsible and responsive bidder, with City Council authorization required before formal award.
The bid must include a Bid Bond equal to five percent of the maximum bid price, and the successful bidder must execute the Contract Documents within 14 days of receiving the Notice of Award. The City has established a Small Business goal of 30 percent of the total bid amount, with small businesses required to be certified by approved agencies and located within five Fort Worth counties (Tarrant, Denton, Wise, Parker, and Johnson). Contractors must be pre-qualified by the City prior to bid opening and must submit audited or reviewed financial statements, organizational documents, and proof of qualifications. The contract is expected to be funded from General Funding revenues reserved by the City for the project. Nonresident bidders must comply with Texas Government Code Chapter 2252 and submit evidence of authority to conduct business in Texas. All bidders must complete a Conflict of Interest Questionnaire or certify one on file with the City Secretary's Office, and the apparent low bidder may be required to submit additional information regarding manpower, equipment, key personnel, and construction schedule prior to award recommendation to City Council.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT FOR
THE CONSTRUCTION OF
Athletic Field Improvements at Rockwood, Rolling Hills, Northwest
Community, and Gateway Parks
City Project No. 105169, 105170, & 105868
Mattie Parker Jesus “Jay” Chapa
Mayor City Manager
Teresa Thomason
Deputy Director, Park & Recreation Department
Lauren Prieur
Director, Transportation & Public Works Department
Prepared for
The City of Fort Worth Park & Recreation Department
1300 Summit Ave Ste 300 Fort Worth, TX 76102
5/7/2026
NOT INTENDED FOR PERMIT,
BIDDING OR CONSTRUCTION.
NOT FOR CONSTRUCTION
SUBMITTED FOR REVIEW
BY.
LICENSE NO.
FIRM.
FIRM NO.
DATE.
F-2614
LOCKWOOD, ANDREWS & NEWNAM, IN
ADAM T. GIBLIN
137032
STATE OF TEXAS
L ICENSED
PROFESS I ONA L ENG I N
EE
R
ADAM T. GIBLIN
137032
CITY OF FORT WORTH Athletic Field Improvements at: Rockwood, Rolling Hills, STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012 Project Number 105169 & 105170
CITY OF FORT WORTH Athletic Field Improvements at: Rockwood, Rolling Hills, STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012 Project Number 105169 & 105170
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH Athletic Field Improvements at: Rockwood, Rolling Hills, STANDARD CONSTRUCTION SPECIFICATION DOCUMENTSSTANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway ParksNorthwest
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
SECTION 00 00 00
TABLE OF CONTENTS
Division 00 - General Conditions Last Revised 00 05 10 Mayor and Council Communication 07/01/2011 00 05 15 Addenda 07/01/2011 00 11 13 Invitation to Bidders 02/08/2024 00 21 13 Instructions to Bidders 09/01/2025 00 35 13 Conflict of Interest Statement 09/19/2025 00 41 00 Bid Form 09/19/2025 00 42 43 Proposal Form Unit Price 09/19/2025 00 43 13 Bid Bond 09/19/2025 00 43 37 Vendor Compliance to State Law Nonresident Bidder 09/19/2025 00 45 11 Bidders Qualifications 08/13/2021 00 45 26 Contractor Compliance with Workers' Compensation Law 07/01/2011 00 45 41 Small Business Goal 09/01/2025 00 45 42 Small Business Utilization Form 06/05/2026 00 52 43 Agreement 09/19/2025 00 61 13 Performance Bond 12/08/2023 00 61 14 Payment Bond 12/08/2023
00 61 19 Maintenance Bond 09/19/2025 00 61 25 Certificate of Insurance 07/01/2011 00 72 00 General Conditions 09/01/2025 00 73 00 Supplementary Conditions 09/19/2025
Division 01 - General Requirements Last Revised 01 11 00 Summary of Work 12/20/2012 01 25 00 Substitution Procedures 07/01/2011 01 29 75 Materials On Hand 09/19/2025 01 31 19 Preconstruction Meeting 09/01/2025 01 31 20 Project Meetings 07/01/2011 01 32 16 Construction Schedule 10/06/2023 01 32 33 Preconstruction Video 12/13/2023 01 33 00 Submittals 12/20/2012 01 35 13 Special Project Procedures 12/13/2023 01 45 23 Testing and Inspection Services 12/13/2023 01 50 00 Temporary Facilities and Controls 09/19/2025 01 57 13 Storm Water Pollution Prevention Plan 07/01/2011 01 58 13 Temporary Project Signage 07/01/2011 01 60 00 Product Requirements 12/13/2023 01 66 00 Product Storage and Handling Requirements 07/01/2011 01 70 00 Mobilization and Remobilization 12/13/2023 01 71 23 Construction Staking and Survey 12/13/2023 01 74 23 Cleaning 07/01/2011
Revised December 20, 2012 Project Number 105169 & 105170
CITY OF FORT WORTH Athletic Field Improvements at: Rockwood, Rolling Hills, STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012 Project Number 105169 & 105170
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH Athletic Field Improvements at: Rockwood, Rolling Hills, Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, 01 77 19 Closeout Requirements 12/13/2023 01 78 23 Operation and Maintenance Data 12/20/2012 01 78 39 Project Record Documents 07/01/2011
Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project’s Contract Documents.
Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City’s website at:
http://fortworthtexas.gov/tpw/contractors/ or https://apps.fortworthtexas.gov/ProjectResources/
Division 02 - Existing Conditions Last Revised 02 41 13 Selective Site Demolition 12/13/2023 02 41 14 Utility Removal/Abandonment 12/20/2012
Division 03 - Concrete 03 30 00 Cast-In-Place Concrete 06/13/2025 03 34 13 Controlled Low Strength Material (CLSM) 03/07/2025 03 80 00 Modifications to Existing Concrete Structures 12/20/2012
Division 11 – Park Improvement Furnishings 11 67 13 Site Furnishings 08/08/2015
Division 26 - Electrical 26 05 00 Common Work Results for Electrical 12/13/2023 26 05 10 Demolition for Electrical Systems 12/13/2023 26 05 19 FL Low-Voltage Electrical Power Conductors and Cables 11/24/2025 26 05 26 FL Grounding and Bonding for Electrical Systems 11/24/2025 26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012 26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011 26 24 16 SF Panelboards 11/24/2025 26 27 33 FL Power Distribution Units 11/24/2025 26 28 16 SF Enclosed Switches and Circuit Breakers 11/24/2025 26 56 68 SF Athletic Field Lighting 11/24/2025
Division 31 - Earthwork 31 23 16 Unclassified Excavation 12/13/2023 31 25 00 Erosion and Sediment Control 04/29/2021 http://fortworthtexas.gov/tpw/contractors/ https://apps.fortworthtexas.gov/ProjectResources/
Revised December 20, 2012 Project Number 105169 & 105170
CITY OF FORT WORTH Athletic Field Improvements at: Rockwood, Rolling Hills, STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012 Project Number 105169 & 105170
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH Athletic Field Improvements at: Rockwood, Rolling Hills, Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Division 32 – Exterior Improvements 32 11 23 Flexible Base Courses 12/20/2012 32 80 00 Irrigation 08/08/2015 32 92 13 Sodding 05/13/2021
Division 99 – Additional Specifications
99 99 00 Metal Roof Shade Structure 01/16/2026 99 99 01 Softball Infield Clay Material 05/07/2026
Appendix GC-6.07 Wage Rates GC-6.09 Permits and Utilities GR-01 60 00 Product Requirements
END OF SECTION
Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, City of Fort Worth
Standard Construction Specification Documents
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Project Number 106060
SECTION 00 05 10
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012 Project Number 105169 & 105170
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Project Number 105169 & 105170
MAYOR AND COUNCIL COMMUNICATION (M&C)
[Assembler: For Contract Document execution, remove this page and replace with the approved
M&C for the award of the project. M&C insert shall be on blue paper.]
Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 106160
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, SECTION 00 05 15
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012 Project Number 105169 & 105170
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Project Number 105169 & 105170
ADDENDA
[Assembler: For Contract Document execution, remove this page and replace with any addenda issued during bidding.]
Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 106160
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Northwest Community, and Gateway Parks Revised December 20, 2012
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
Athletic Field Improvements at: Rockwood, Rolling Hills, 00 11 13
INVITATION TO BIDDERS
RECEIPT OF BIDS
SECTION 00 11 13
INVITATION TO BIDDERS
Electronic bids for the construction of Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community and Gateway Park (“Project”) will be received by the City of Fort Worth via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities, under the respective Project until August 27, 2026.
Bids will then be opened publicly and read aloud beginning at 2:00 PM CST in the City Council Chambers.
Your submissions must be uploaded, finalized and submitted prior to the Project’s posted due date. The City strongly recommends allowing sufficient time to complete this process (ideally a week prior to the deadline) to begin the uploading process and to finalize your submission.
Uploading large documents may take time, depending on the size of the file(s) and your Internet connection speed. The Bonfire portal can be accessed using Microsoft Edge, Google Chrome, or Mozilla Firefox. Javascript must be enabled. Browser cookies must be enabled.
Electronic submission is subject to electronic interface latency, which can result in transmission delays. All bidders or proposers assume the risk of late transmission/ submission. The City shall not be held liable if an interested bidder or proposer is unable to submit a complete bid/response before the published deadline due to transmission delays or any other technical issues or obstructions. The City strongly recommends allowing sufficient time to complete the submission process (ideally a week before the deadline) to begin the uploading process and to finalize your submission to give adequate time in the event an issue arises.
All submissions must be submitted electronically prior to the close date and time under the respective Project via the Procurement Portal:
https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities
Failure to submit all completed required information listed in the respective Solicitation will be grounds for rejection of a bid as non-responsive. No late bids/proposals shall be accepted. Bids delivered in any other manner than using the Bonfire Platform (Procurement Portal) will not be accepted or considered.
If, upon being opened, a submission is unreadable to the degree that material conformance to the requirements of the procurement specifications cannot be ascertained, such submission will be rejected without liability to the City, unless such bidder provides clear and convincing evidence
(a) of the content of the submission as originally submitted and (b) that the unreadable condition of the Electronic Bid was caused solely by error or malfunction of the Bonfire Platform (Procurement Portal). Failure to scan a clear or readable copy of a bid into the system does not constitute and shall not be considered an error or malfunction of the Bonfire Platform (Procurement Portal). Bidders are encouraged to fully review each page of every document within their submission prior to submitting to ensure all documents are clear, legible, and complete.
STANDARD CONSTRUCTION SPECIFICATION DOCUMENT
Revised 2/08/24
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks Project Number 105169, 105170, & 105868 https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities
Athletic Field Improvements at: Rockwood, RollingAthletic Field Improvements at: Rockwood, Rolling Hills,CITYHills,CITY OF FORTOF FORT WORTHWORTH Northwest Community, and Gateway kSTANDARD h i d k STANDARD
Revised 2/08/24
Athletic Field Improvements at: Rockwood, Rolling Hills, SUPPORT
For technical questions, visit Bonfire’s help forum at https://vendorsupport.gobonfire.com/hc/en-us Contact the Bonfire support team at Support@GoBonfire.com or by calling 1-800-354-8010.
To get started with Bonfire, watch this five-minute training video:
Vendor Registration and Submission [VIDEO] – Bonfire Vendor Support (gobonfire.com)
GENERAL DESCRIPTION OF WORK
The major work will consist of the (approximately) following:
The work in this project includes installation of remote equipment controllers at Gateway Park, Rolling Hills Soccer Rockwood Complex, rehabilitation of softball infields at Gateway & Rockwood Parks, construction of bleacher shading structures at Northwest Community Park, and alternate lighting installation and grassing replacement at Rockwood Park.
QUALIFICATION
Certain improvements included in this project must be performed by a contractor or designated subcontractor who is pre-qualified by the City at the time of bid opening. The procedures for qualification and pre-qualification are outlined in the Section 3 of 00 21 13 – INSTRUCTIONS
TO BIDDERS.
DOCUMENT EXAMINATION AND PROCUREMENTS
The Bidding and Contract Documents may be examined or obtained via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities, under the respective Project. Contract Documents may be downloaded, viewed, and printed by interested contractors and/or suppliers.
EXPRESSION OF INTEREST
To ensure potential bidders are kept up to date of any new information pertinent to this project, all interested parties should indicate their intent to bid in the Procurement Portal by selecting “yes” under the Intent to Bid section. All Addenda will be posted in the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities, under the respective Project.
PREBID CONFERENCE – Web Conference A prebid conference will be held as discussed in Section 00 21 13 - INSTRUCTIONS TO BIDDERS at the following date, and time via a web conferencing application:
DATE: August 12, 2026 TIME: 10:00 am Invitations with links to the web conferencing application will be distributed directly to those who have submitted an Expression of Interest.
Invitations with links to the web conferencing application will be distributed directly to those who have submitted an Expression of Interest.
mailto:Support@GoBonfire.com
Athletic Field Improvements at: Rockwood, RollingAthletic Field Improvements at: Rockwood, Rolling Hills,CITYHills,CITY OF FORTOF FORT WORTHWORTH Northwest Community, and Gateway kSTANDARD h i d k STANDARD
Revised 2/08/24
Athletic Field Improvements at: Rockwood, Rolling Hills, If a prebid conference is held, the presentation and any questions and answers provided at the prebid conference will be issued as an Addendum to the call for bids. If a prebid conference is not being held, prospective bidders should direct all questions about the meaning and intent of the Bidding Documents electronically through the Vendors discussions section under the respective Project via the Procurement Portal. If necessary, Addenda will be issued pursuant to the Instructions to Bidders.
CITY'S RIGHT TO ACCEPT OR REJECT BIDS
City reserves the right to waive irregularities and to accept or reject any or all bids.
AWARD
City will award a contract to the Bidder presenting the lowest price, qualifications and competencies considered.
FUNDING
Any Contract awarded under this INVITATION TO BIDDERS is expected to be funded from revenues generated from General Funding and reserved by the City for the Project.
ADVERTISEMENT DATES
1st Advertisement July 29, 2026 2nd Advertisement August 5, 2026
00 21 13
INSTRUCTIONS TO BIDDERS
1. Defined Terms
SECTION 00 21 13
1.1. Capitalized terms used in these INSTRUCTIONS TO BIDDERS are defined in Section 00 72 00 - GENERAL CONDITIONS.
1.2. Certain additional terms used in these INSTRUCTIONS TO BIDDERS have the meanings indicated below which are applicable to both the singular and plural thereof.
1.2.1. Bidder: Any person, firm, partnership, company, association, or corporation acting directly through a duly authorized representative, submitting a bid for performing the work contemplated under the Contract Documents.
1.2.2. Nonresident Bidder: Any person, firm, partnership, company, association, or corporation acting directly through a duly authorized representative, submitting a bid for performing the work contemplated under the Contract Documents whose principal place of business is not in the State of Texas.
1.2.3. Successful Bidder: The lowest responsible and responsive Bidder to whom
City (on the basis of City's evaluation as hereinafter provided) makes an award.
2. Copies of Bidding Documents
2.1. Neither City nor Engineer shall assume any responsibility for errors or misinterpretations resulting from the Bidders use of incomplete sets of Bidding
Documents.
2.2. City and Engineer in making electronic Bidding Documents available do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license or grant for any other use.
3. Qualification of Bidders (Prime Contractors and Subcontractors)
3.1. The City reserves the right to require any pre-qualified contractor who is the apparent low bidder for a project to submit each additional information as the
City, in its sole discretion may require, including but not limited to manpower and equipment records, information about key personnel to be assigned to the project, and construction schedule to assist the City in evaluating and assessing the ability of the apparent low bidder to deliver a quality product and successfully complete projects for the amount bid within the stipulated time frame. Based upon the City’s assessment of the submitted information, a recommendation regarding the award of a contract will be made to the City
Council. Failure to submit additional information, if requested, may be grounds for rejecting the apparent low bidder as non-responsive. Affected contractors will be notified by writing of a recommendation to the City Council.
3.2. Additional requirements for qualification may be required within various sections of the Contract Documents.
Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
Revised/Updated September 1, 2025
4. Examination of Bidding and Contract Documents, Other Related Data, and Site
4.1. Before submitting a Bid, each Bidder:
4.1.1. Shall examine and carefully study the Contract Documents and other related data identified in the Bidding Documents (including "technical data" referred to in Paragraph 4.2. below). No information given by City or any representative of the City other than that contained in the Contract Documents and officially promulgated addenda thereto, shall be binding upon the City.
4.1.2. Should visit the site to become familiar with and satisfy Bidder as to the general, local and site conditions that may affect cost, progress, performance or furnishing of the Work.
4.1.3. Shall consider federal, state and local Laws and Regulations that may affect cost, progress, performance or furnishing of the Work.
4.1.4. Is advised that, City, in accordance with Title VI of the Civil Rights Act of
1964, 78 Stat. 252, 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal
Regulations, Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Nondiscrimination in Federally-assisted programs of the Department of
Transportation issued pursuant to such Act, hereby notifies all bidders that it will affirmatively insure that in any contract entered into pursuant to this advertisement, minority business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration of award.
4.1.5. Shall study all: (i) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground
Facilities) that have been identified in the Contract Documents as containing reliable "technical data" and (ii) reports and drawings of Hazardous
Environmental Conditions, if any, at the Site that have been identified in the
Contract Documents as containing reliable "technical data."
4.1.6. Is advised that the Contract Documents on file with the City shall constitute all of the information which the City will furnish. All additional information and data which the City will supply after promulgation of the formal Contract
Documents shall be issued in the form of written addenda and shall become part of the Contract Documents just as though such addenda were actually written into the original Contract Documents. No information given by the City other than that contained in the Contract Documents and officially promulgated addenda thereto, shall be binding upon the City.
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
4.1.7. Should perform independent research, investigations, tests, borings, and such other means as may be necessary to gain a complete knowledge of the conditions which will be encountered during the construction of the project. For projects with restricted access, upon request, City may provide each Bidder access to the site to conduct such examinations, investigations, explorations, tests and studies as each Bidder deems necessary for submission of a Bid.
Bidder must fill all holes and clean up and restore the site to its former conditions upon completion of such explorations, investigations, tests and studies.
4.1.8. Shall determine the difficulties of the Work and all attending circumstances affecting the cost of doing the Work, time required for its completion, and obtain all information required to make a proposal. Bidders shall rely exclusively and solely upon their own estimates, investigation, research, tests, explorations, and other data which are necessary for full and complete information upon which the proposal is to be based. It is understood that the submission of a proposal or bid is prima-facie evidence that the Bidder has made the investigations, examinations and tests herein required.
4.1.9. Shall promptly notify City of all conflicts, errors, ambiguities or discrepancies in or between the Contract Documents and such other related documents. The
Contractor shall not take advantage of any gross error or omission in the
Contract Documents, and the City shall be permitted to make such corrections or interpretations as may be deemed necessary for fulfillment of the intent of the Contract Documents.
4.1.10. Indicate their intent to bid by selecting “yes” in the Procurement
Portal under the Intent to Bid section. You must indicate your intent to bid to be able to submit a bid to the City.
4.2. Reference is made to Section 00 73 00 – Supplementary Conditions for identification of:
4.2.1. those reports of explorations and tests of subsurface conditions at or contiguous to the site which have been utilized by City in preparation of the
Contract Documents. The logs of Soil Borings, if any, on the plans are for general information only. Neither the City nor the Engineer guarantee that the data shown is representative of conditions which actually exist.
4.2.2. those drawings of physical conditions in or relating to existing surface and subsurface structures (except Underground Facilities) which are at or contiguous to the site that have been utilized by City in preparation of the
Contract Documents.
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
4.2.3. copies of such reports and drawings will be made available by City to any
Bidder on request. Those reports and drawings may not be part of the Contract
Documents, but the "technical data" contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.02. of the General Conditions has been identified and established in Paragraph SC 4.02 of the Supplementary
Conditions. Bidder is responsible for any interpretation or conclusion drawn from any "technical data" or any other data, interpretations, opinions or information.
4.2.4. Standard insurance requirements, coverages and limits.
4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder:
(i) that Bidder has complied with every requirement of this Paragraph 4, (ii) that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and applying the specific means, methods, techniques, sequences or procedures of construction (if any) that may be shown or indicated or expressly required by the Contract Documents, (iii) that Bidder has given City written notice of all conflicts, errors, ambiguities and discrepancies in the
Contract Documents and the written resolutions thereof by City are acceptable to
Bidder, and when said conflicts, etc., have not been resolved through the interpretations by City as described in Paragraph 6., and (iv) that the Contract
Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
4.4. The provisions of this Paragraph 4, inclusive, do not apply to Asbestos, Polychlorinated biphenyls (PCBs), Petroleum, Hazardous Waste or Radioactive
Material covered by Paragraph 4.06. of the General Conditions, unless specifically identified in the Contract Documents.
5. Availability of Lands for Work, Etc.
5.1. The lands upon which the Work is to be performed, rights-of-way and easements for access thereto and other lands designated for use by Contractor in performing the
Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by City unless otherwise provided in the Contract Documents.
5.2. Outstanding right-of-way, easements, and/or permits to be acquired by the City are listed in Paragraph SC 4.01 of the Supplementary Conditions. In the event the necessary right-of-way, easements, and/or permits are not obtained, the City reserves the right to cancel the award of contract at any time before the Bidder begins any construction work on the project.
5.3. The Bidder shall be prepared to commence construction without all executed right-of-way, easements, and/or permits, and shall submit a schedule to the City of how construction will proceed in the other areas of the project that do not require permits and/or easements.
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
6. Interpretations and Addenda
6.1. All questions about the meaning or intent of the Bidding Documents are to be directed to City electrically through the Vendor Discussions section under the respective Project via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities on or before 2 p.m., the FRIDAY prior to the Bid opening. Questions received after this day may not be responded to. Interpretations or clarifications considered necessary by City in response to such questions will be issued by Addenda. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
6.2. Addenda may also be issued to modify the Bidding Documents as deemed advisable by City.
6.3. Addenda or clarifications shall be posted under the respective Project via the
Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities
6.4. A prebid conference may be held at the time and place indicated in the
Advertisement or INVITATION TO BIDDERS. Representatives of City will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. City will transmit to all prospective Bidders of record such Addenda as City considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.
7. Bid Security
7.1. Each Bid must be accompanied by a Bid Bond made payable to City in an amount of five (5) percent of Bidder's maximum Bid price, on the form attached or equivalent, issued by a surety meeting the requirements of Paragraph 5.01 of the General
Conditions.
7.2. The Bid Bonds provided by a Bidder will be retained until the conditions of the
Notice of Award have been satisfied. If the Successful Bidder fails to execute and return the Contract Documents within 14 days after the Notice of Award conveying same, City may consider Bidder to be in default, rescind the Notice of Award and act on the Bid Bond. Such action shall be City's exclusive remedy in the event
Bidder is deemed to have defaulted.
8. Contract Times
The number of days within which, or the dates by which, Milestones are to be achieved in accordance with the General Requirements and the Work is to be completed and ready for Final Acceptance is set forth in the Agreement or incorporated therein by reference to the attached Bid Form.
9. Liquidated Damages
Provisions for liquidated damages are set forth in the Agreement.
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
10. Substitute and "Or-Equal" Items
The Contract, if awarded, will be on the basis of materials and equipment described in the
Bidding Documents without consideration of possible substitute or "or-equal" items.
Whenever it is indicated or specified in the Bidding Documents that a "substitute" or "or-equal" item of material or equipment may be furnished or used by Contractor if acceptable to City, application for such acceptance will not be considered by City until after the Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by City is set forth in Paragraphs 6.05A., 6.05B. and 6.05C. of the General Conditions and is supplemented in Section 01 25 00 of the General Requirements.
11. Subcontractors, Suppliers and Others
11.1. In accordance with the City’s Small Business Ordinance No. 27832-08-25, the
City has established a goal for the participation of small businesses for City contracts $100,000 or greater. See Section 00 45 41 for the Project Goal and additional requirements. Failure to comply may render the Bidder non-responsive.
11.2. No Contractor shall be required to employ any Subcontractor, Supplier, other person or organization against whom Contractor or City has reasonable objection.
12. Bid Form
12.1. The Bid Form is included with the Bidding Documents.
12.2. All blanks on the Bid Form must be completed and the Bid Form signed electronically or signed in ink and scan. A Bid price shall be indicated for each Bid item, alternative, and unit price item listed therein. In the case of optional alternatives, the words "No Bid," "No Change," or "Not Applicable" may be entered.
Bidder shall state the prices for which the Bidder proposes to do the work contemplated or furnish materials required.
12.3. Bids by corporations shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign. The corporate seal shall be affixed. The corporate address and state of incorporation shall be shown below the signature.
12.4. Bids by partnerships shall be executed in the partnership name and signed by a partner, whose title must appear under the signature accompanied by evidence of authority to sign. The official address of the partnership shall be shown below the signature.
12.5. Bids by limited liability companies shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.
12.6. Bids by individuals shall show the Bidder's name and official address.
12.7. Bids by joint ventures shall be executed by each joint venture in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
12.8. All names shall be typed or printed in ink below the signature.
12.9. The Bid shall contain an acknowledgement of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
12.10. Postal and e-mail addresses and telephone number for communications regarding the
Bid shall be shown.
12.11. Evidence of authority to conduct business as a Nonresident Bidder in the state of
Texas shall be provided in accordance with Section 00 43 37 – Vendor Compliance to State Law Non Resident Bidder.
13. Submission of Bids
Bids shall be submitted electronically in the Procurement Portal on the prescribed Bid
Form, provided with the Bidding Documents, prior to the time indicated in the
Advertisement or INVITATION TO BIDDERS.
14. Withdrawal of Bids
14.1. Bids submitted electronically may be withdrawn prior to the time set for bid opening via the Procurement Portal https://fortworthtexas.bonfirehub.com/portal/?tab=openOpportunities.
15. Opening of Bids
Bids will be opened and read aloud publicly. An abstract of the amounts of the base Bids and major alternates (if any) will be made available to Bidders after the opening of Bids.
16. Bids to Remain Subject to Acceptance
All Bids will remain subject to acceptance for a minimum of 90 days or the time period specified for Notice of Award and execution and delivery of a complete Agreement by
Successful Bidder. City may, at City's sole discretion, release any Bid and nullify the Bid security prior to that date.
17. Evaluation of Bids and Award of Contract
17.1. City reserves the right to reject any or all Bids, including without limitation the rights to reject any or all nonconforming, nonresponsive, unbalanced or conditional Bids and to reject the Bid of any Bidder if City believes that it would not be in the best interest of the Project to make an award to that Bidder. City reserves the right to waive informalities not involving price, contract time or changes in the Work and award a contract to such Bidder. Discrepancies between the multiplication of units of
Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
17.1.1. Any or all bids will be rejected if City has reason to believe that collusion exists among the Bidders, Bidder is an interested party to any litigation against City, City or Bidder may have a claim against the other or be engaged in litigation, Bidder is in arrears on any existing contract or has defaulted on a previous contract, Bidder has performed a prior contract in an unsatisfactory manner, or
Bidder has uncompleted work which in the judgment of the City will prevent or hinder the prompt completion of additional work if awarded.
17.2. In addition to Bidder’s relevant prequalification requirements, City may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work where the identity of such
Subcontractors, Suppliers, and other persons and organizations must be submitted as provided in the Contract Documents or upon the request of the City. City also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award.
17.3. City may conduct such investigations as City deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers and other persons and organizations to perform and furnish the Work in accordance with the Contract
Documents to City's satisfaction within the prescribed time.
17.4. Contractor shall perform with his own organization, work of a value not less than
35% of the value embraced on the Contract, unless otherwise approved by the City.
17.5. If the Contract is to be awarded, it will be awarded to lowest responsible and responsive Bidder whose evaluation by City indicates that the award will be in the best interests of the City.
17.6. Pursuant to Texas Government Code Chapter 2252.001, the City will not award contract to a Nonresident Bidder unless the Nonresident Bidder’s bid is lower than the lowest bid submitted by a responsible Texas Bidder by the same amount that a
Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a comparable contract in the state in which the nonresident’s principal place of business is located.
17.7. A contract is not awarded until formal City Council authorization. If the Contract is to be awarded, City will award the Contract within 90 days after the day of the Bid opening unless extended in writing. No other act of City or others will constitute acceptance of a Bid. Upon the contract award, a Notice of Award will be issued by the City.
17.7.1. The contractor is required to fill out and sign the Certificate of Interested
Parties Form 1295 and the form must be submitted to the Project Manager before the contract will be presented to the City Council. The form can be obtained at https://www.ethics.state.tx.us/data/forms/1295/1295.pdf
17.8. Failure or refusal to comply with the requirements may result in rejection of Bid.
https://www.ethics.state.tx.us/data/forms/1295/1295.pdf
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 105169 & 105170Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills,CITY OF FORT WORTH Northwest Community, and Gateway ParksSTANDARD CONSTRUCTION SPECIFICATION DOCUMENT Project Number 106160Revised/Updated September 1, 2025
Athletic Field Improvements at: Rockwood, Rolling Hills, Northwest Community, and Gateway Parks
Project Number 105169, 105170, & 105868
CITY OF FORT WORTH
18. Signing of Agreement
18.1. When City issues a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Project Manual. Within 14 days thereafter, Contractor shall sign and deliver the required number of counterparts of the Project Manual to City with the required Bonds, Certificates of Insurance, and all other required documentation.
18.2. City shall thereafter deliver one fully signed counterpart to Contractor.
00 35 13
CONFLICT OF INTEREST STATEMENT
Each bidder, offeror or respondent to a City of Fort Worth procurement is required to complete a Conflict of Interest Questionnaire or certify that one is current and on file with the City Secretary's Office pursuant to state law.
If a member of the Fort Worth City Council, any one or more of the City Manager or Assistant City Managers, or an agent of the City who exercise discretion in the planning, recommending, selecting or contracting with a bidder, offeror or respondent is affiliated with your company, then a Local Government Officer Conflicts Disclosure Statement (CIS) may be required.
You are urged to consult with counsel regarding the applicability of these forms and Local Government Code Chapter 176 to your company.
Form CIQ (Conflict of Interest Questionnaire) (state.tx.us) https://www.ethics.state.tx.us/data/forms/conflict/CIS.pdf
CIQ Form does not apply
CIQ Form is on file with City Secretary
CIQ Form is being provided to the City Secretary
CIS Form does not apply
CIS Form is on File with City Secretary
CIS Form is being provided to the City Secretary
BIDDER:
By:
Signature:
Title:
The referenced forms may be downloaded from the links provided below.
CONFLICT OF INTEREST STATEMENT
SECTION 00 35 13
END OF SECTION
CITY OF FORT WORTH
Revised September 19, 2025 00 41 00 Bid Proposal Workbook_CPN. 105169, 105170, & 105868).xlsx
00 41 00
BID FORM
TO:
2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
a.
b.
SECTION 00 41 00
BID FORM
Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
Bidder has not solicited or induced any individual or entity to refrain from bidding.
Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract.
For the purposes of this Paragraph:
"corrupt practice" means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process.
"fraudulent practice" means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of City (b) to establish Bid prices at artificial non-competitive levels, or (c) to deprive City of the benefits of free and open competition.
2. BIDDER Acknowledgements and Certification
In submitting this Bid, Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and INSTRUCTIONS TO BIDDERS, including without limitation those dealing with the disposition of Bid Bond.
The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with City in the form included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.
Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will provide a valid insurance certificate meeting all requirements within 14 days of notification of award.
Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.
The Purchasing Manager
1. Enter Into Agreement
100 Fort Worth Trail City of Fort Worth, Texas 76102 c/o: The Purchasing Division
Units/Sections: UNIT 1 - ROCKWOOD PARK IMPROVEMENTS FIELD NO. 4
UNIT 2 - ROLLING HILLS SOCCER COMPLEX IMPROVEMENTS
UNIT 9 - ALTERNATE ROCKWOOD PARK IMPROVEMENTS FIELD NO. 1,2,3,&4
UNIT 3 - NORTHWEST COMMUNITY PARK IMPROVEMENTS
UNIT 4 - GATEWAY PARK IMPROVEMENTS
UNIT 5 - ALTERNATE ROCKWOOD PARK IMPROVEMENTS
UNIT 6 - ALTERNATE ROCKWOOD PARK IMPROVEMENTS FIELD NO. 1
UNIT 7 - ALTERNATE ROCKWOOD PARK IMPROVEMENTS FIELD NO. 2
UNIT 8 - ALTERNATE ROCKWOOD PARK IMPROVEMENTS FIELD NO. 3
FOR:
City Project No.:
Athletic Field Improvements at: Rockwwod, Rolling Hills, Nortwest Community, & Gateway Parks
105169, 105170 & 105868
UNIT 10 - ALTERNATE ALLOWANCE BID ITEMS
CITY OF FORT WORTH
Revised 9/19/2025 00 41 00 Bid Proposal Workbook_CPN. 105169, 105170, & 105868 .xlsx c.
d.
a.
b.
c.
d.
e.
f.
g.
h.
4.1. 120 Cal.
4.2.
a.
b.
c.
d.
e.
f.
g.
This Bid Form, Section 00 41 00
Proposal Form, Section 00 42 43
Required Bid Bond, Section 00 43 13 issued by a surety meeting the requirements of Paragraph
5.01 of the General Conditions.
Small Business Forms (required at time of bid)
"collusive practice" means a scheme or arrangement between two or more Bidders, with or without the knowledge of City, a purpose of which is to establish Bid prices at artificial, non-competitive levels.
Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work {and/or achievement of Milestones} within the times specified in the Agreement.
Qualification Statement, Section 00 45 12
Conflict of Interest Affidavit, Section 00 35 13
5. Attached to this Bid
The following documents are attached to and made a part of this Bid:
*If necessary, CIQ or CIS forms are to be provided directly to City Secretary
Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37
3. Qualification
4. Time of Completion
The Work will be complete for Final Acceptance within
"coercive practice" means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
The Bidder acknowledges that the following work types must be performed only by qualified contractors and subcontractors:
days after the date when the the Contract Time commences to run as provided in Paragraph 2.03 of the General Conditions.
CITY OF FORT WORTH
h.
6.1.
6.2.
6.3.
Title:
Company:
Address:
Email:
Phone:
END OF SECTION
Any additional documents that may be required by Section 12 of the Instructions to Bidders
6. Total Bid Amount
It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is subject to verification and/or…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .