This is a bid tabulation sheet for the City of Burleson, Texas, prepared by Baird, Hampton & Brown for Project No. 2025.013.174, titled "Burleson Generator Replacements." The project encompasses two separate locations: the Service Center at 725 SE John Jones Drive and City Hall at 141 W. Renfro Street. Both bid tabs contain identical line items for the supply and installation of 175kW generators with fuel tanks, automatic transfer switches, docking stations, duct and exhaust work, electrical additions to operations centers and administrative buildings, and lift station site work. Each project scope includes demolition of existing equipment, labor and services, insurance, permits and bonds, and contingency line items. The bid sheet is structured to accommodate four contractors (Contractor A, B, C, and D), with columns for unit quantities and unit bid amounts, though all monetary values currently display as zero, indicating this is a template or blank bid form awaiting contractor submissions.
The bid tabulation format provides for both a subtotal and total base bid calculation, followed by a tax total bid amount line for each location. The document structure suggests a comparative bidding process where multiple contractors will submit pricing on identical scope items, allowing the City to evaluate competitive proposals based on unit pricing and total project costs. The file contains no information regarding bid due dates, award timelines, incumbent contractors, funding sources, or contract terms, as these details would typically be specified in the accompanying request for proposals (RFP 2026-012) rather than the bid tabulation sheet itself.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Service Center
| BID TABULATION |
| Company Name: Baird, Hampton & Brown Project No.: 2025.013.174 |
Project Name: Burleson Generator Replacements Location: 725 SE John Jones, Dr., BURLESON, TEXAS 76028 Architect: Bid Date:
| Engineer's Estimate | CONTRACTOR A | CONTRATOR B | CONTRACTOR C | CONTRACTOR D | |||||||||
| BID QUANTITIES | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | |||
| Ref # | Bid Item # | Item Description | Qty. | ||||||||||
| 1 | 1.010 | Demolition | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 2 | 1.020 | 175kW Generator w/fuel tank | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 3 | 1.030 | Automatic Transfer Switch | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 4 | 1.040 | Docking Station | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 5 | 1.050 | Duct/Exhaust Work | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 6 | 1.060 | Electrical Additions (Ops Center, Admin Bldg) | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 7 | 1.070 | Lift Station Site Work | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 8 | 1.080 | Labor & Services | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 9 | 1.090 | Subtotal | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 10 | 1.100 | Insurance | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 11 | 1.110 | Permits, bonds | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 12 | 1.120 | Contingency | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| TOTAL BASE BID | $ - | $ - | $ - | $ - | $ - | ||||||||
| TAX | |||||||||||||
| TOTAL BID AMOUNT | $ - | $ - | $ - | $ - | $ - |
City Hall
| BID TABULATION |
| Company Name: Baird, Hampton & Brown Project No.: 2025.013.174 |
Project Name: Burleson Generator Replacements Location: 141 W. Renfro St., BURLESON, TEXAS 76028 Architect: Bid Date:
| Engineer's Estimate | CONTRACTOR A | CONTRATOR B | CONTRACTOR C | CONTRACTOR D | |||||||||
| BID QUANTITIES | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | |||
| Ref # | Bid Item # | Item Description | Qty. | ||||||||||
| 1 | 1.010 | Demolition | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 2 | 1.020 | 175kW Generator w/fuel tank | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 3 | 1.030 | Automatic Transfer Switch | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 4 | 1.040 | Docking Station | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 5 | 1.050 | Duct/Exhaust Work | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 6 | 1.060 | Electrical Additions (Ops Center, Admin Bldg) | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 7 | 1.070 | Lift Station Site Work | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 8 | 1.080 | Labor & Services | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 9 | 1.090 | Subtotal | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 10 | 1.100 | Insurance | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 11 | 1.110 | Permits, bonds | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| 12 | 1.120 | Contingency | 1 | $ - | $ - | $ - | $ - | $ - | |||||
| TOTAL BASE BID | $ - | $ - | $ - | $ - | $ - | ||||||||
| TAX | |||||||||||||
| TOTAL BID AMOUNT | $ - | $ - | $ - | $ - | $ - |
image1.png
File details come from the government source that posted it. Updated .