595-26-204 DB SOW - Replace Chillers Bldgs 1-2-104.docx

DOCX document 336 KB Posted

Attached to
Z1DA--595-26-204 Replace Chillers Buildings 1, 2, and 104 DB (VA-26-00013164)
Solicitation number
36C24426R0020
Issued by

About this file

This document is a Statement of Work (SOW) for a Design-Build (DB) project to replace chillers at the Lebanon VA Medical Center in Lebanon, PA. The project involves replacing end-of-lifecycle chillers in Buildings 1, 2, and 104, including mechanical and electrical system upgrades, building automation system modifications, and comprehensive design and construction services. Key scope elements include replacing standby chillers, modifying chilled water piping, integrating campus chilled water systems, replacing controls, and upgrading electrical infrastructure, with all work to comply with NFPA, VA, and OSHA standards.

The project timeline requires construction documents to be completed within 90 days after Notice to Proceed (NTP), with construction to be finished by 280 days after NTP. The Design-Build (DB) team is responsible for comprehensive services including site investigations, professional design, architectural and engineering services, construction documentation, and construction period services. The procurement will be a Best Value tradeoff two-phase design-build solicitation, managed by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4 (VISN 04), with a Firm-Fixed-Price contract anticipated.

View the file

Other files

File Type Posted
595-26-204 Instructions to Offerors PDF.docx DOCX document
013526 Lebanon Safety Requirements Spec 20240516.docx DOCX document
P03 07.08.2025 Service Determination.pdf PDF
Davis-Bacon Act WD PA20250093 10.3.25.pdf PDF
36C24426R0020_1.docx DOCX document
Bldg 2 - PH-ME.pdf PDF
Bldg 2 - B - ME.pdf PDF
RM Language for Contracts.docx DOCX document
230923 HVAC Controls Specification.docx DOCX document
010000 Lebanon General Requirements Spec.docx DOCX document
LB-104-0RME.pdf PDF
LB-01-02ME.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lebanon VA Medical Center Lebanon, PA 17042 Design/Build (DB) Scope of Work Replace Chillers Buildings 1, 2 and 104 595-26-204 Construction Documents Ready by: 90 days after Notice to Proceed (NTP) issued Construction Complete by: 280 days after NTP issued Contracting Officer: Elijah McIntosh Contracting Officers Representative (COR) Matthew Donmoyer

· Provide all labor, materials, tools and equipment, and design-build services necessary for design and construction of a project described here in other specific tasks as further defined by this request for proposal (RFP) of Project No. 595-26-204 Replace Chillers Building 1, 2 and 104. The project scope is to replace Building 2 chillers 1 and 2, mechanical piping modifications in the basement to incorporate campus chilled water for backup, and to remove chiller 3; replace Building 1 standby chiller; replace and relocate Building 104 operating room back up chiller and additional piping to relocated chiller to roof of building 104. The resultant contract of this procurement is to provide required design and perform construction of completed design work. Project shall be designed and completed in accordance with VA Criteria, NFPA (National Fire Protection Association), EPA (Environmental Protection Agency) requirements, and VA Specifications developed for the project.

· This Request for Proposal (RFP) document is intended to generally define the scope and design parameters to be included in the project. It is the Design Build (DB) Team’s responsibility to provide a complete set of design documents in a manner consistent with VA guidelines, specifications, and design standards in order to complete construction within the 280-day schedule.

· Offeror shall be prepared for a 280-day schedule as indicated below in the Project Schedule. Offeror may propose an alternate schedule, in addition to the 280-day schedule, which will be reviewed by the VA. Schedules shall indicate the following:

o Design period and provisions for VA reviews.

o Phasing plans for coordination of any site utility relocation work.

o Construction period services including:

· Mobilization

· Demolition

· Excavation

· Enclosure

· Interior Construction

· Procurement and installation of equipment

· Provisions for overtime or shift work shall be included in the contract offer.

· Site utilities, temporary stairs, roadway realignments, and other site differing conditions as encountered during construction.

· Equipment unloading, placing, inspection, testing, commissioning, and reports.

PROVIDE:

Professional Design/Build (DB) and healthcare planning services to include but not limited to:

· Site investigation – architectural, civil, structural, electrical, mechanical and any other engineering services as needed, environmental studies, and materials testing.

· Contract drawings and specifications for construction.

· Construction period services for DB A/E - review of shop drawing submissions, provide recommendations regarding contractor change proposals and requests for information (RFI), DB A/E shall visit site per VA's request, add to drawings as-built conditions from contractor's record drawings; DB A/E shall respond on site within a two-hour period when requested.

· Construction of the replacement chillers for building 1,2 and 104, including all Management, Supervision, Labor, Transportation, Equipment and Materials and perform work to include demolition, general construction, alterations, mechanical and electrical work, and certain other items as required by project drawings and specifications to create a complete and useable facility.

-- Project Scope --

GENERAL:

Provide a full set of construction documents for a project that shall replace the failing end of lifecycle chillers at building 1, 2 and building 104, at the Lebanon VA Medical Center. The offeror should be prepared to conduct site investigations to verify existing conditions, all dimensions (existing and proposed) and constructability.

The offeror shall be prepared to make layout changes, calculations, and provide documentation to support their design to replace the chillers per the specifications and drawings approved through the Design and Project Design Team (PDT) process.

SPECIFICS:

The project to replace the end of lifecycle chillers at buildings 1, 2 and 104 shall include the following:

· The project shall replace the standby chiller located on the roof of building 1 above the kitchen.

· Replace building 2 chillers 1 and 2, modifications to chilled water piping in basement to utilize campus chilled water as backup and remove chiller 3.

· Replace building 104 operating room backup chiller and relocate to roof of building 104, to include additional piping to relocate chiller to roof.

· Replace the end-of-life cycle Delta Controls building automation system in Building 2 and replace with Distech Controls and integrate to campus Tridium Niagara building automation system.

· Hot Water System

· Chilled Water System

· Quantity of 5 Air Handlers

· Quantity of 66 VAV boxes

· Quantity of 4 Fan Coil Units

· Modify chilled water program to incorporate campus chilled water as backup to building 2.

· Replace deteriorated piping, valves, insulation, and appurtenances on remaining piping as necessary.

· Provide a structural analysis for each chiller location that is stamped by a licensed structural engineer. Perform any improvements required by that analysis.

· Replace deteriorated wiring. Existing wiring can be used if it meets NEC standards.

· Do not use existing boxes or controllers as Junction Boxes. They all shall be removed.

· Any factory controls where necessary to meet modern standards and must integrate via Bacnet/IP or Bacnet/MSTP into new Distech Tridium server.

· All work shall comply with the National Fire Protection Association (NFPA) 70 (National Electrical Code), 70B, 70E, 72, 99, 101, and 13, the VA Electrical, HVAC and Plumbing Design Manuals and Occupational Safety and Health Administration (OSHA) regulations.

· Everything that controls, consumes, or is capable of consuming electric shall have a label. Label shall have circuit identification, panel it is fed from, and where the panel is located.

· Layout of the space shall maximize staffing efficiencies. Installation will be required to occur during times that will minimize impact to the patients, staff and hospital in general.

· Utilities are to be separate from the medical center.

· Collaboration between Design-Build team, COR and Lebanon VAMC Air Conditioning shop will be greatly encouraged during the project.

Construction shall be addressed in phases to allow operations to continue during construction. Heating and cooling shall be maintained for the building at all times. Phasing shall be determined during the 35% design review. Phasing must work within budget and allow the VA to continue operations at minimal interference.

The DB A/E is responsible for providing certified industrial hygiene services to perform asbestos survey investigations, bulk sampling, development of specifications and drawings, and construction period services. All designs shall be accomplished in accordance with VA guidelines and specifications, which are available on the Internet at http://www.cfm.va.gov/til/. DB A/E shall pay attention to NFPA, BOCA, VA Handbook 7610 space criteria and VA program guide PG-18-14.

The DB A/E shall provide professional architectural and engineering and construction services for the project and is responsible for providing all services necessary for design of this project – i.e. mechanical, electrical, asbestos sampling and monitoring, structural, fire alarm and suppression, communications, cable tv, etc.

The DB construction contractor shall provide all Management, Supervision, Labor, Transportation, Equipment and Materials and perform work to include demolition, general construction, alterations, mechanical and electrical work, and certain other items as required by project drawings and specifications complete the chiller replacements at buildings 1, 2 and 104.

-- Site Investigations --

EXPECTATION: The DB A/E shall make site visits as necessary to survey existing conditions.

Make site visits as required to determine existing as-built conditions affecting this project. NOTE: Information including drawings and other documentation provided to the DB A/E is used as reference only. All additional references and specifications are available in VHA’s Technical Information Library at address: http://www.cfm.va.gov/til/. AutoCAD background drawings will be provided by the VA upon request. The DB A/E shall field verify all dimensions. The DB A/E shall field verify every aspect that relates to the project. Coordinate site visits with the Contracting Officer Representative (COR) as determined after award.

-- Project Schedule --

EXPECTATION: Submit review packages so they are received on the noted day

SUBMISSIONS:

Submit review packages so they are received on the noted day (calendar days after NTP) or earlier:

Initial PDT Meeting0 days
Design Development Documents (35%)40 days
(PDT Meeting)45 days
Design Development Documents (100%)65 days
(PDT Meeting)70 days
Construction Documents90 days

(3 Sets of Drawings and Specifications)

Begin Construction on or before120 days
Complete Construction on or before280 days

Note: The issuance of the Notice to Proceed (NTP) for design will be at the first Project Design Team (PDT) Meeting. The Design-Build Team Contractor shall be required to attend and take minutes of each PDT meeting. Minutes shall be submitted electronically to the Project Manager and Contracting Officer within three calendar days of each meeting for approval and to be added to the official contract file.

-- Design Requirements/Submissions --

EXPECTATIONS: Submit complete review package in accordance with the following requirements and guidelines outlined in http://www.cfm.va.gov/til/aeDesSubReq.asp Please pay specific attention to the schematic, design and construction submission requirements. As appropriate and depending upon the complexity of the design, the DB A/E may elect to delete individual submissions where not required (i.e. Do not address Site Development, Landscaping for interior renovation projects)

DELIVER:

All design packages directly to the Contracting Officer and Project Engineer on the established dates to allow the VA to review. Include all information as follows and as outlined in the attachments for each submission. Information required for each submittal is outlined in Program Guide PG-18-15 Volume C November 2008. The manual is available at the following address: http://www.cfm.va.gov/til/aeDesSubReq.asp Area of Construction: Building 1, Building 2 and Building 104, See Attachment A.

Design Development 35%: Attachment “B” 35% Submission Requirements

· Requirements for the 35% Design Development Documents Submission.

· Define the design elements based on the presented option and submit all information required by the PG-18-15 (35% Design Development).

· Identify Working Drawings scope within the construction budget.

· Identify all design calculations.

· Identify impact of existing asbestos.

· Develop plans and marked up specifications to meet all applicable federal and state

· codes/requirements, including but not limited to PENDOT, OSHA, DER, EPA, NEC, NFPA 101 Life Safety Code.

· Identify all design calculations.

· Identify all existing utilities and utilities requirements.

· Identify all potential bid deduct alternatives.

· Identify all phasing requirements for construction.

· Develop Infection Control Risk Assessment (VA EC-43)

Design Development 100%: Attachment “C” 100% Submission Requirements

· Requirements for the 100% Design Development Documents Submission.

· Address all comments from the 75% review.

· Consolidate all necessary submittals by specification section on an Excel spreadsheet. Checklist to be utilized to track/monitor submittal process.

· Revise and update cost estimate.

· Preparation of project scope for CBD/ negotiated advertisement and account for any bid deduct alternatives developed in the 75% design submission

· Finalize all design calculations.

· Finalize all potential bid deduct alternatives.

· Finalize all phasing requirements for construction.

· Finalize impact of existing asbestos.

· Finalize Infection Control Risk Assessment (VA EC-43)

· Address all comments from the VISN Safety & Fire Protection Review.

Construction Documents (CD): Attachment “D” Construction Documents Submission Requirements Submit a complete set of documents of all contract requirements. The Cover Page shall be submitted for approval signatures. If necessary, update and submit until approved by the VA.

-- Construction Period Services --

Expectations: Respond to submittals and other requests in a timely manner.

PROVIDE:

· Review all shop drawing submissions and provide recommendations to the VA within five calendar days upon request.

· Make site visits on requests of the VA and prepare written reports to include agreed upon changes in design as determined necessary during the construction. Visits made based on errors and omissions in design shall be at no cost to the VA.

· Participate in partial and/or final acceptance inspections as scheduled and generate punch list items for completion. The punch list shall reference the contract documents for specific deficiencies (i.e. specification section, drawing detail, etc.)

· Prepare as-built drawings on original set with DB A/E’s stamp, based on record drawings that the contractor kept during construction. Transpose contractor’s as-built’s to AutoCAD 2007 – 2014 and in PDF form and provide a set of updated as-built’s on CD within 30 days to the COR

ATTACHMENT “A”

Building 2- The A/E is responsible for checking all information and providing new solutions

Building 1- The A/E is responsible for checking all information and providing new solutions

Building 104- The A/E is responsible for checking all information and providing new solutions

ATTACHMENT “B”

Design Development 35% Submission Requirements Deliver the following (labeled with 35% submission) and include this attachment as a checklist with your submission:

q 3 copies of a narrative report forwarding the design develop 75% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager, and any design calculations or analysis.

q 3 sets of all drawings updating all previous comments required by project and produced in AutoCAD 2007 – 2014 and in PDF form.

q 2 copies of updated itemized cost estimate by spec section or trade (labor, material and equipment) and by VA criteria, NRM, Minor, BSER and BSEA.

q 3 copies of custom edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.

q 1 set of all drawings and specifications, to send for 3rd party Life Safety Review.

q 1 copy of drawings in AutoCAD 2007 – 2014 and in PDF form and specifications in Microsoft Word 2007 or higher on (CD)

ATTACHMENT “C”

Design Development 100% Submission Requirements

Deliver the following (labeled with 100% submission) and include this attachment as a checklist with your submission:

q 3 copies of a narrative report forwarding the design develop 100% submission addressing items listed in the design requirements and any additional A/E recommendations. The report should include identifying potential bid deduct alternatives, recommended construction phasing based upon discussions with the program manager and any design calculations or analysis.

q 2 sets of all drawings updating all previous comments required by project produced in AutoCAD 2007 – 2014 and in PDF form.

q 3 copies of the proposed construction schedule.

q 2 copies of final itemized cost estimate by spec section or trade (labor, material and equipment) and by VA criteria, NRM, Minor, BSER and BSEA.

q 2 copies of final edited VA Master Specifications of sections to be used for this project and a master submittal list identifying all the submittals required to be submitted by the contractor for review.

q 1 CD containing q All drawings in AutoCAD 2007 - 2014 and in PDF form.

q All specifications in Microsoft Word 2007 or higher on (CD)

ATTACHMENT “D”

Expectation: Submit complete contract documents for final review prior to Notice to Proceed for Construction. Continue to submit contract documents until all changes are incorporated by the DB A/E for final signature prior to Notice to Proceed for Construction. Upon approval duplicate copies as required.

Deliver the following (labeled with Contract Documents Submission) and include this attachment as a checklist with your submission:

Contract Document Submission Requirements q 1 copy of the Cover Sheet (AutoCAD) for final VA signatures.

q 2 sets of all drawings updating all previous comments required by project, produced in AutoCAD 2007 – 2014 and in PDF form – for final VA review. If approved final sets to be submitted with signed off cover sheet.

q 3 copies of final project specification (two bounds; one loose) prepared in Microsoft Word 2007 or higher. Include a master submittal list in the specifications.

q 1 CD containing q All drawings in AutoCAD 2007 – 2014 and in PDF.

q All specifications in Microsoft Word 2007 or higher.

q Submittal Spreadsheet – identifying all the submittals required to be submitted by the contractor for review. The list shall be organized by division and specification.

q Upon signature approval, provide three (3) sets of final Contract Documents (complete with VA signed Cover Sheet). Provide two (2), half (1/2) size sets of final drawings.

ATTACHMENT “E”

Specifications (All downloadable from the VA Technical Information Library (www.cfm.va.gov/TIL) unless otherwise noted)

01 00 00Lebanon General Requirements (attached)
01 35 26Lebanon Safety Requirements (attached)
01 33 23Shop Drawings, Product Data, and Samples
01 45 00Quality Control
01 45 29Testing Laboratory Services
01 91 00General Commissioning Requirements
02 41 00Demolition
03 30 00Cast-in-place Concrete
07 84 00Firestopping
23 05 11Common Work Results for HVAC
23 05 12General Motor Requirements for HVAC
23 05 41Noise and Vibration Control for HVAC Piping and Equipment
23 05 93Testing, Adjusting, and Balancing for HVAC
23 07 11HVAC Insulation
23 08 00Commissioning of HVAC Systems
23 09 23Direct-Digital Control System for HVAC (attached)
23 25 00HVAC Water Treatment
23 81 46Water-Source Unitary Heat Pumps
23 81 49Ground Source Heat Pumps
26 05 11Requirement for Electrical Installations
26 05 19Low-Voltage Electrical power Conductors and Cables
26 05 26Grounding and Bonding for Electrical Systems
26 05 33Raceway and Boxes for Electrical Systems

image1.emf image2.emf image3.emf image4.emf