This document is an Amendment (No. 2 - Revision #1) for the VA Dayton Project No. 552-19-102, focused on correcting infrastructure deficiencies in Building 408. The amendment includes revisions to multiple specification sections and drawings, specifically updating Quality Control Organization staffing requirements, modifying the scope and quantities for Traditional Asbestos Abatement, and adding entirely new sections for Subsurface Prep for Floor Finishes, Ceramic & Porcelain Tiling, and Carpeting.

The drawings section of the amendment includes revised sheets for the First Floor Plan (AS102) and First Floor Reflected Ceiling Plan (AS111), with added clouding for specific rooms (Room 101, Rooms 101A and 101C). The amendment is dated 08/26/2025, with revisions marked in blue, indicating ongoing modifications to the project's technical specifications and design documentation for the VA Dayton infrastructure improvement project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA DAYTON PROJECT NO. 552-19-102

CORRECT INFRASTRUCTURE DEFICIENCIES, B408

ADDENDUM NO. #2 - Revision #1

SPECIFICATIONS

ITEM NO. 1 Section 01 45 00 - Quality Control

A. Revise paragraph 3.4 QUALITY CONTROL ORGANIZATION: Staffing Requirements updated for CQC

ITEM NO. 2 Section 02 82 11 - Traditional Asbestos Abatement

A. Modified paragraph 1.1.2 EXTENT OF WORK: tables to update Scope of Work and Quantities.

DRAWINGS

ITEM NO. 1

ITEM NO. 2

ITEM NO. 3

ITEM NO. 4

ITEM NO. 5

Section 09 05 16 - Subsurface Prep for Floor Finishes

A. Add in it's entirety.

Section 09 30 13 - Ceramic & Porcelain Tiling

A. Add in it's entirety.

Section 09 68 00 - Carpeting

A. Add in it's entirety.

Drawing No. AS102, FIRST FLOOR PLAN. Revised sheet attached.

A. Added Clouding for Room 101.

Drawing No. AS111, FIRST FLOOR REFLECTED CEILING PLAN. Revised sheet attached.

A. Added Clouding for Rooms 101A and 101C.

Amendment 0008 08/26/2025 Revisions = Blue