This document is a Sole Source Justification form (SF 1009) for a brand-name acquisition by the Internal Revenue Service (IRS) under the Department of the Treasury. The procurement is for two Panduit server cabinets (XG84522BS-0051) and two ServerTech power distribution units (C2X36TEDQME2M99/ZW and C2W36TEDQME2M99/ZR) to support the Unified Communications platform. The total quantity is two of each item, with a need date of 5/12/2025.

The justification emphasizes standardization as the primary reason for the brand-name requirement. The IRS Project Response and Incident Management Branch (PRIMB) has established Panduit cabinets and ServerTech PDUs as its standard equipment across enterprise computing centers. Changing to different brands would require extensive retraining of engineers, modify existing cable management infrastructure, and potentially cause operational disruptions. The procurement will be a firm-fixed-price contract, set aside for a small business, with no options. The specific items are detailed with full technical specifications in the document, including cabinet dimensions, power distribution unit features, and configuration details.

View the file

Other files

File Type Posted
Statement of Work Attachment B.pdf PDF
II_RFQ 205AE9-25-Q-00087.pdf PDF
6 LSJ 3182025.pdf PDF
UC Pricing Evaluation Model- Cabinets PDUs_Attachment A.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Treasury Standard Form – 1009 (Rev 10/18)

Prescribed by Treasury: DTAP 1013.106(b)

DEPARTMENT OF THE TREASURY

SF 1009 - FAR 13.106-1(b) SOLE SOURCE JUSTIFICATION FOR

ACQUISITIONS AT OR BELOW THE SIMPLIFIED ACQUISITION THRESHOLD

1. 1. Identification of the requesting activity and contracting activity.

Department of the Treasury/Internal Revenue Service/User and Network Services/Unified Communications; and Office of Chief Procurement Office, Office of Procurement Operations, IT Operations, User & Network Services Branch

2.a A description of the supplies or services required to meet the agency’s needs.

The purpose of this limited-sources justification is to obtain approval to award a firm fixed price (FFP) contract for the purchase of the items described in table below. The need date for these items is by 5/12/2025. See Statement of Work (SOW) attached in the shopping cart 5000206762 for details.

Manufacturer Part Number Description Qty

Panduit

XG84522BS-0051

Panduit Server Cabinet -Pre-Configured FlexFusion™ Cabinet, 800mm x 45RU x 1200mm, Black, Hardware Mount Rail, CoolBoot-Ready Top Cap, Single Hinge Perforated Front Door, Split Perforated Rear Door, Standard Locks, Left and Right Side Panels, One Set Short Cable Mgmt Fingers, Left and Right PDU Brackets, Casters. Installed is 1 PC PN RGS134B-1, Grounding Strip on rear right equipment rail. Bundled with the cabinet are 1 piece PN XG-TCF8W, Top cap fascia Kit and 1 piece PN RGCBNJ660P22, Grounding Jumper Kit

ServerTech

C2X36TE-

DQME2M99/ZW

Switched Expansion PRO2 18xC13 + 18xCx Alt Phase HDOT Outlets, 208V 3PH Delta 6BR 60A 60309 3P+PE Blue IP67 Water-tight Plug 3m/10ft cord, Auto-Orient Mid Display, Bottom End Cord Entry, Doghouse Breakers, Phase Monitoring, WxD = 2.20in x 2.50in, White Highlights Features: 60C, Alt-Phase, Auto- flip LED, Branch Current Monitoring, HDOT, High Retention Outlets, Locking Outlets

ServerTech

C2W36TE-

DQME2M99/ZR

Switched Primary PRO2 18xC13 + 18xCx Alt Phase HDOT Outlets, 208V 3PH Delta 6BR 60A 60309 3P+PE Blue IP67 Water-tight Plug, 3m/10ft cord, Auto-Orient Mid Display, Bottom End Cord Entry, Doghouse Breakers, Phase Monitoring, WxD = 2.20in x 2.50in, Red, Highlights Features: 60C, Alt-Phase, Auto-flip LED, Branch Current Monitoring, HDOT, High Retention Outlets, Locking Outlets

2.b Name and business size of the vendor. TBD

2.c Requisition No. 5000206762

3. IGCE/Estimated dollar value.

4.a Identification of the circumstances that preclude competition (Check the appropriate box that applies).

Urgency Exclusive licensing agreements Brand-name Industrial mobilization.

Othe r

4.b Supporting information and facts (i.e. the details surrounding the requirement that supports the selection made in 4.a).

IRS implements a standard operating procedure (SOP) for the equipment to be used in all its datacenters. The Project Response and Incident Management Branch (PRIMB) which manages the IRS’ Enterprise Computing Centers has extensively built the standards for its resources including cabinets and power distribution unit (PDU) to be used at those centers. The standards of the cabinets have been Panduit cabinets and PDU has been ServerTech. This has allowed our already stretched-thin IRS engineers to be proficient with the management of that equipment; without having to be retrained them with different types of equipment. This in turn results in saving money for the agency and taxpayer. In addition, introducing different brand racks and PDUs would not work with the with the existing cable management infrastructure and other resources in the computing centers. Any deviation from the established standard will require extensive modification and testing of a new configuration of the cable management infrastructure which will cost time and money for the agency to implement. In addition, the non-standard equipment could have negative impacts on the operation of the computing centers. Any interruption could trigger a wide range of outages to systems and applications being impacted by such negative impacts.

5. Any other important information.

6. Certifications and Approvals.

6.a Program Office certification (Requiring Activity). I hereby certify that the supporting information and data provided, and which form the basis for this justification are accurate and complete to the best of my knowledge and belief.

Name: S t e v e n O . R h o d e n Date: 1/29/2025

Signature: Steve O. Rhoden Digitally signed by Steve O. Rhoden

Date: 2025.01.29 15:46:56 -05'00'

6.b Contracting Officer approval. In accordance with FAR 13.106-1(b)(1), as a warranted contracting officer, I hereby determine that the circumstances of the acquisition make only one brand-name or source reasonably available for the reasons provided above;

therefore precluding competition and supporting the Government’s determination to solicit as a brand-name requirement or solicit and award to the vendor stated in section 2.b.

Name: Kayla Dicks Date: 3/18/2025

Signature:

Instructions for SF 1009 - FAR 13.106-1(b) Sole Source Justification for Acquisitions at or below the Simplified Acquisition Threshold

I. General instructions. Each Sole source justifications for acquisitions at or below the SAT shall contain sufficient information and data to justify the proposed action, thereby be able to stand on its own. This type of detail is critical in order to enable a reviewer and/or approver to clearly understand the requirement and the rationale supporting the justification. Simply copying and pasting information from a vendor’s website or marketing literature fails to support the use of such justification. Market research performed by the Requiring Activity and Contracting Activity should be used to support this document.

Given the majority of the information and data necessary to support this type of action resides with the Requiring Activity, they are the primary party responsible for completing this form.

However, the Requiring Activity shall seek assistance and input from the Contracting Activity/Contracting Officer (preferably in advance of submission of the procurement request).

It is also recommended the justification is not signed by the Requiring Activity until such time the Contracting Officer has had an opportunity to review, make necessary revisions and to include other necessary information or data to support the justification.

For Brand-name acquisitions keep in mind the justification is to cover only the portion of the acquisition which is brand-name and that that the document approval requirements only apply to that portion. However, it does not mean that details regarding the overarching requirement (i.e.

in the instance where the brand name is only a portion of an overall requirement) aren’t to be included in the document.

In the event of conflict between this form and applicable regulatory coverage (i.e. FAR and DTAR), the more stringent requirement shall be followed.

If the requirement involves classified or sensitive information, ensure the proper steps are taken to protect the information (e.g. marking).

Prior to distribution for signature: (i) delete all green text (which are examples), and (ii) consider converting the document to .pdf to support electronic signature and ease of retention.

The fields within this form are fluid and will change based upon input, therefore individuals completing this form need to be mindful of formatting prior to converting the document to pdf and submitting it for signature.

II. Field specific instructions.

Section 1. Identification of the requiring activity and the contracting activity. Provide the name of the requiring activity (e.g. BFS’ –IT Office) and the name of the contracting activity (e.g. BFS’s – Contracting Office for IT).

Section 2.a A description of the supplies or services required to meet the agency’s needs.

Provide a clear, concise description of the supplies or services to be procured. Include a statement regarding the delivery schedule and/or the period of performance, inclusive of all option periods and award terms. State the schedule and associated schedule category(ies) the supplies or services are being procured against. For supplies, include details such quantity and a brief description of the items (e.g. twelve (12) laptops).

For brand name, provide the name of the brand, model number and other specific details associated with the brand name item(s) to be procured; name(s) of known sources that can provide the brand name.

For modification describe the purpose of modification, including details such as proposed extension to the period of performance as well as the purpose of and type of the contract.

Section 2.b Name and business size of vendor. If applicable, insert the name of proposed vendor and the vendor’s business size (large or small business) to support whether 6.b is required. Vendor information can be obtained from the SAM database. If not applicable, enter “Not applicable”.

Section 2.c Requisition Number. If known, include the requisition number. If not applicable, enter “Not applicable”.

Section 3 IGCE/Estimated dollar value. Provide the IGCE/estimated dollar value of the anticipated award, inclusive of all options, award terms and any other monetary incentives.

For brand name provide the IGCE/estimated dollar value of the portion of the proposed acquisition, inclusive of all options, award terms and other monetary incentives, that is for the brand name item and the full IGCE/estimated dollar value of the acquisition.

For modifications provide the IGCE/estimated dollar value of the modification and the current total dollar value of the contract.

Section 4.a Identification of the circumstances that preclude competition. Check the applicable circumstance of the action that deems only one source reasonably available (see FAR 13.106-1(b)).

Section 4.b Supporting information and facts (i.e. the details surrounding the requirement that supports the selection made in 4.a). The rationale for the sole source must be thoroughly explained within this section. For example, explain why the vendor is the only one that can provide the product or service if using only one source (e.g. urgency, industrial mobilization, a patent, copyright, proprietary data, or exclusive licensing agreement). If urgency, explain what harm, monetary or schedule wise, (and include dollars that would be lost, time lost, etc.) that will result if an aware is not made to this vendor by a certain date.

For brand name, provide sufficient detail to describe the rationale for the brand name. For example, Why is this particular brand name needed? Why won’t another brand of product work?

For modifications explain why the modification is needed, the circumstances that support the modification, etc.

Section 5 Additional important information. Include, as applicable, any other important information that supports the justification. Note: If a market research summary report (e.g. SF 1010) was completed, this might be a good place to provide a summary of the findings/ determination along with a citation to that document so that a reviewer can refer to that document for greater detail.

Section 6 Certifications/Approvals. Obtain the signatures as indicated.

A supplemental justification is required if any of the following revisions occur between the approval of the original justification and the covered award or modification of the contract: an increase in dollar value beyond the authority approved in the justification; a change in the competitive strategy that further reduces competition; or any type of change in the requirement that affects the basis of the justification.

DEPARTMENT OF THE TREASURY
II. Field specific instructions.
Section 4.a Identification of the circumstances that preclude competition. Check the

File details come from the government source that posted it. Updated .