50-49500-24-01989_50-49500-24-01989 Items List (1).xlsx.XLSX
XLSX spreadsheet 19 KB Posted
- Attached to
- 24-C12 FABRIC HANGAR/PAYLOAD FACILITY – 25-C05 HORIZONTAL LAUNCH AREA SOUTH HANGAR TAXIWAY
- Solicitation number
- 50-49500-24-01989
- Issued by
- San Juan County, New Mexico
About this file
This is a detailed items list or bid schedule for what appears to be an airport construction project involving apron, hangar pad, and taxiway improvements. The project scope encompasses 78 line items divided into several major sections including Apron & Hangar Pad construction, Drainage & Sanitary Sewer Systems, Taxiway improvements, and Temporary Structures. Key elements include the construction of a 156' x 156' fabric hangar, modular office and restroom units, extensive pavement work including cement concrete and asphalt surfaces, installation of water lines, drainage systems, and various site improvements such as fencing, gates, and markings.
The document includes three pre-set allowances: $10,000 for underground utilities relocation, $60,000 for owner's allowance during construction, and $75,000 for testing. Mobilization, insurance, and bonds are set at $162,500, while demobilization and closeout documentation is fixed at $51,500. The bid requires quantities for various materials including approximately 12,820 cubic yards of unclassified excavation, 32,730 square yards of subgrade preparation, and significant amounts of concrete and asphalt paving materials. The total bid amount field is included but not populated in the document.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
| Item No. | Description | Unit | Est. Qty. | Bid Unit Price | Bid Price | ||
| APRON & HANGAR PAD | |||||||
| 1 | Airport Safety and Security, Complete | LS | 1 | ||||
| 2 | Clearing and Grubbing | AC | 4 | ||||
| 3 | Unclassified Excavation, Complete | CY | 9700 | ||||
| 4 | Temporary Pollution / Erosion Control | LS | 1 | ||||
| 5 | Subgrade Preparation, 24" Complete in place | SY | 12850 | ||||
| 6 | Subgrade Preparation, 12", Parking Lot, Complete in place | SY | 4360 | ||||
| 7 | Cement Treated Subgrade 6", Complete in place | SY | 12850 | ||||
| 8 | Crushed Aggregate Base Course, 8", Parking Lot, Complete in place | CY | 970 | ||||
| 9 | Asphalt Mix, 4", Parking Lot, Complete in place | TON | 1940 | ||||
| 10 | Asphalt Base Course, 5", Complete in place | TON | 2910 | ||||
| 11 | Asphalt Base Course, 6", Complete in place | TON | 1000 | ||||
| 12 | Cement Concrete Pavement, 13", Complete in place | CY | 3620 | ||||
| 13 | Cement Concrete Pavement, 10", Complete in place | CY | 800 | ||||
| 14 | Bituminous Prime Coat | GAL | 7750 | ||||
| 15 | Concrete for Miscellaneous Structures, Hangar Foundation, include reinforcing, Complete in place | CY | 55 | ||||
| 16 | Markings, Complete in place | SF | 900 | ||||
| 17 | Gravel, 3" Deep, Complete in place | SY | 15040 | ||||
| 18 | Concrete Sidewalk, Complete in place | SF | 804 | ||||
| 19 | Tie Downs, Complete in place | LS | 1 | ||||
| 20 | High Game Fence, including man-gates, complete in place | LF | 500 | ||||
| 21 | Automatic Rolling Gate, card reader and closure loops, complete in place | LS | 1 | ||||
| 22 | 12" Water line, include all fitting, T&B and Compaction, Complete in place | LF | 800 | ||||
| 23 | 12" Gate Valve with Valve Box, Complete in Place | EA | 1 | ||||
| 24 | 6" Water line, include all fitting, T&B and Compaction, Complete in place | LF | 480 | ||||
| 25 | 6" Gate Valve with Valve Box, Complete in Place | EA | 1 | ||||
| 26 | 2" Water line (HDPE), include all fittings, complete in place | LF | 160 | ||||
| 27 | 2" Water service, including tapping service saddle, corp stop and angle valve (2), complete in place | EA | 1 | ||||
| 28 | Fire Hydrant Assembly, include valve, valve box, complete in place | EA | 1 | ||||
| 29 | 2" Air-Vacuum Station, include manhole & cover, Complete in place | EA | 1 | ||||
| 30 | Connection to existing System, Complete in place | LS | 1 | ||||
| 31 | Base Course, Road Patch, complete in place | SY | 15 | ||||
| 32 | Adjust Manhole ring and cover to grade, complete in place | EA | 1 | ||||
| DRAINAGE & SANITARY SEWER SYSTEMS | |||||||
| 33 | 4" Diameter PVC SDR35 Sewer Pipe, complete in place | LF | 280 | ||||
| 34 | Double Clean-out, both directions, complete in place | EA | 1 | ||||
| 35 | Service connections (stub-outs) for modular units, hangar, complete in place | EA | 5 | ||||
| 36 | Single Clean-out, hangar facility, complete in place | EA | 1 | ||||
| 37 | 1500 Gallon HDPE Septic Tank, Compete in place | EA | 1 | ||||
| 38 | Connection to existing sewer system, 8" PVC, saddle and fittings, complete in place | EA | 1 | ||||
| 39 | Duraslot trench drain and pipe system, with concrete encasement, including grate, cleanout, connections, complete in place. | LF | 152 | ||||
| 40 | 6" HDPE Storm Drain Pipe (n=0.012), complete in place | LF | 252 | ||||
| 41 | 8" HDPE Storm Drain Pipe (n=0.012), complete in place | LF | 510 | ||||
| 42 | 1000 Gallon 2 Baffle Sand/Oil Separator, complete in place | EA | 1 | ||||
| 43 | In-Line drop inlets, complete in place | EA | 2 | ||||
| 44 | 4' Diameter Manhole, complete in place | EA | 3 | ||||
| 45 | Connection to existing system, build manhole over existing line, complete in place. | LS | 1 | ||||
| TAXIWAY | |||||||
| 46 | Clearing and Grubbing | AC | 3 | ||||
| 47 | Unclassified Excavation, Complete | CY | 3120 | ||||
| 48 | Temporary Pollution / Erosion Control | LS | 1 | ||||
| 49 | Subgrade Preparation, 24" Complete in place | SY | 12080 | ||||
| 50 | Cement Treated Subgrade 6", Complete in place | SY | 7800 | ||||
| 51 | Asphalt Mix Pavement Base Course, 5", Complete in place | TON | 2270 | ||||
| 52 | Cement Concrete Pavement, 13", Complete in place | CY | 2820 | ||||
| 53 | Bituminous Prime Coat | GAL | 5440 | ||||
| 54 | Crushed Aggregate Base Course | CY | 720 | ||||
| 55 | Asphalt Mix Pavement 9", Complete in Place | TON | 2240 | ||||
| 56 | 48" Diameter Culverts Drainage Culverts, include headwalls for a double barrel configuration, Complete in place | LF | 480 | ||||
| 57 | Markings, Complete in place | SF | 450 | ||||
| 58 | Relocate existing windsock, including segmented circle, complete in place | EA | 1 | ||||
| Temporary Structures | |||||||
| 59 | 156' x 156' Fabric Hangar (Min R-8-10 Insulation), complete in place | EA | 1 | ||||
| 60 | Hangar Door, completed in place | EA | 1 | ||||
| 61 | Personnel Doors, complete in place | EA | 4 | ||||
| 62 | Termination Bar and Angle Flashing with Sealants, complete in place | LF | 624 | ||||
| 63 | 60' x 24' Office Modular Unit, complete in place | EA | 1 | ||||
| 64 | 24' x 8' Restroom/Shower Modular Unit, complete in place | EA | 2 | ||||
| 65 | Standard Metal Skirting (Per Modular), complete in place | EA | 3 | ||||
| 66 | Pressure-Treated Elevated Decking (Includes Steps & Ramps), complete in place | SF | 960 | ||||
| 67 | Utility Connections for Modular Buildings (Electrical, Plumbing, Sewer), complete in place | LS | 1 | ||||
| 68 | Interior 6" Metal Stud Framing, complete in place | LF | 80 | ||||
| 69 | Drywall, Mud, and Tape, complete in place | SF | 320 | ||||
| 70 | Interior Hollow Metal Doors, complete in place | EA | 2 | ||||
| 71 | Primer/Paint and Floor Base, complete in place | LS | 1 | ||||
| Other Project Construction Requirements | |||||||
| 72 | Mobilization, Insurance, and Bonds. | LOT | 1 | $ 162,500.00 | $ 162,500.00 | ||
| 73 | Demobilization and Submittal of All Closeout Documents. | LOT | 1 | $ 51,500.00 | $ 51,500.00 | ||
| 74 | Prepare and Execute Storm Water Pollution Prevention Plan (SWPPP) Compliance per Requirements in | ||||||
| Section C-102, Including All Materials and Labor, Complete in Place, for Duration of Construction Period. | LS | 1 | |||||
| Item No. | Description | Unit | Est. Qty. | Bid Unit Price | Bid Price | ||
| 75 | Construction Staking Services by New Mexico Registered Surveyor. | LS | 1 | ||||
| 76 | Relocation of Underground Utilities Allowance. | ALLOW | 1 | $ 10,000.00 | $ 10,000.00 | ||
| 77 | Owner's Allowance During Construction. | ALLOW | 1 | $ 60,000.00 | $ 60,000.00 | ||
| 78 | Testing Allowance. | ALLOW | 1 | $ 75,000.00 | $ 75,000.00 | ||
| TOTAL BID AMOUNT (Exclusive of New Mexico Gross Receipts Tax) $ |
File details come from the government source that posted it. Updated .