5-SEHS Intercom Repl Re-Bid PROJ MANUAL 100% OTB SET.pdf

PDF 21 MB Posted

Attached to
RE-BID SOUTH ELGIN HIGH SCHOOL INTERCOM REPLACEMENT; U-46 Project No. 285-26
Solicitation number
421 - 25/26
Issued by
Kane County, Illinois

About this file

Project Manual Summary: South Elgin High School Intercom Replacement

This is a project manual for a sealed lump sum bid issued by the Board of Education of School District U-46 in Kane County, Illinois, for the complete replacement of the intercom and clock system at South Elgin High School located at 760 E. Main Street, South Elgin, Illinois 60177 (U-46 Project No. 285-26; MSA Project No. 2554). The project involves furnishing and installing a new Telecor eSeries Network-Based microprocessor-switched intercommunications and program system with associated components including network admin control consoles, call-switch units, talkback speakers, digital clocks/message boards, paging amplifiers, low-voltage power supplies, uninterruptible power supplies, conductors and cables, raceways, and connections to existing building systems (fire alarm, access control, intrusion detection, security cameras, and local sound systems). A mandatory virtual pre-bid meeting was scheduled for March 11, 2026, at 10:00 a.m. CT, with a virtual bid opening on March 20, 2026, at 10:30 a.m. CT. The anticipated contract award date is April 27, 2026, with work commencing May 26, 2026, following approval by the Regional Office of Education and submission of required documentation. The project is divided into two phases with substantial completion dates of August 7, 2026 (Phase 1) and December 18, 2026 (Phase 2), with final completion deadlines of August 14, 2026, and December 31, 2026, respectively. The contractor must maintain the existing Simplex intercom/clock system in parallel operation throughout construction and include all costs for overtime, shift work, weekend work, and custodian services required to meet the critical schedule.

A bid guarantee of ten percent of the base bid amount is required, submitted as either a bid bond or cashier's check payable to School District U-46 prior to the virtual bid opening. Performance and Payment Bonds equal to 100 percent of the contract sum are required upon award. The project is subject to the Illinois Prevailing Wage Act (820 ILCS 130), with all contractors and subcontractors required to pay prevailing wages and submit certified payrolls to the Illinois Department of Labor. The base bid includes a $200,000 general allowance, with unit pricing required for intercom and clock unit devices at specified rates per device. Liquidated damages of $1,000 per calendar day are assessed for failure to achieve substantial completion by the specified dates. The contractor must be bondable, maintain a minimum of five years' experience with the Telecor eSeries system, be Telecor-certified, have completed at least three successful Telecor eSeries installations, and provide references. All contractor personnel are required to undergo background checks and be registered in the School District U-46 Raptor system before accessing the site. A two-year warranty on all parts and labor is required, with system manufacturers providing a minimum 25-year warranty on the structured cabling system. The project is funded by School District U-46 and will result in a fully operational network-based communications platform supporting emergency announcements, bell scheduling, zone paging, digital message boards with countdown timers synchronized to the District's NTP signal, and integration with building safety systems.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHOOL DISTRICT U-46

355 East Chicago Street

Elgin, Illinois 60120

111 S. Virginia Street, Crystal Lake, Illinois 60014

Office 815-788-8901 | Fax 815-788-8908 MSA P.N. 2554

PROJECT MANUAL

SOUTH ELGIN HIGH SCHOOL

INTERCOM REPLACEMENT RE-BID

U-46 Project No. 285-26

March 6, 2026

Owner: School District U-46 355 East Chicago Street Elgin, Illinois 60120

Engineer: Mechanical Services Associates Corp.

Mark Carlson 111 S. Virginia Street Crystal Lake, Illinois 60014 815-788-8901

Virtual MANDATORY Pre-Bid Meeting: March 11, 2026, 10:00 a.m. CT School District U-46

Link will be posted on the District’s Bid Portal (Bonfire)

Virtual Bid Opening: March 20, 2026, 10:30 a.m. CT School District U-46 Link will be posted on the District’s Bid Portal (Bonfire)

TABLE OF CONTENTS TOC - 1

SOUTH ELGIN HIGH SCHOOL – INTERCOM REPLACEMENT RE-BID U-46 P.N. 285-26

SCHOOL DISTRICT U-46

SOUTH ELGIN HIGH SCHOOL

INTERCOM REPLACEMENT RE-BID

MSA PROJECT NO. 2554

U-46 PROJECT NO. 285-26

TABLE OF CONTENTS

GENERAL INFORMATION

A1 Advertisement for Bids

A2 Instructions to Bidders

AIA A701 Instruction to Bidders (Latest Edition) (NOT INCLUDED)

A9 Authorization for Criminal Background Investigations

AIA A201 General Conditions of the Contract for Construction

AIA A101 Standard Form of Agreement Between Owner and Contractor (Latest Edition)

(NOT INCLUDED)

AIA A312 Performance Bond and Payment Bond (Latest Edition) (NOT INCLUDED)

BID SUBMITTAL DOCUMENTS

A3 Form of Bid

A4 Bidder Eligibility Certification and Non-Collusion Affidavit Pursuant to

Public Act 85-1295 (720 ILCS 5/33E-1 et seq.)

A5 Prevailing Wage Payment Certification

A6 Certificate of Compliance with Illinois Human Rights Act (775 ILCS 5/1-101 et eq.)

A7 Certificate of Compliance with Illinois Drug-Free Workplace Act

A8 Certificate Regarding Criminal Background Investigations

A10 Asbestos and/or Lead Free Construction Certification

A11 Certification of Sexual Harassment Policy

A12 Certification of Monthly Payroll

AIA A305 Contractor’s Qualification Statement (NOT INCLUDED)

AIA A310 Bid Bond (Latest Edition) (NOT INCLUDED)

SPECIFICATIONS

NOTE: ALL REFERENCES TO "ARCHITECT" WITHIN THE PROJECT DOCUMENTS

SHALL BE REFERRED TO AS "ENGINEER."

Division 00 – Contracting Requirements

Section 003126 Environmental Notes

Division 01 – General Requirements

Section 010200 Completion Date

Section 012100 Allowances

Section 012200 Unit Prices

Section 012500 Substitution Procedures

Section 012600 Contract Modification Procedures

TABLE OF CONTENTS TOC - 2

Section 012900 Payment Procedures

Section 012901 Special Provisions for Predetermined Prevailing Wage

Section 013100 Project Management and Coordination

Section 013200 Construction Progress Documentation

Section 013300 Submittal Procedures

Section 015000 Temporary Facilities and Controls

Section 017300 Execution

Section 017700 Closeout Procedures

Section 017823 Operation and Maintenance Data

Section 017839 Project Record Documents

Section 017900 Demonstration and Training

Division 02 – Existing Conditions

Section 024119 Selective Demolition

Division 07 – Thermal and Moisture Protection

Section 078413 Penetration Firestopping

Section 079200 Joint Sealants

Division 09 – Finishes

Section 092900 Gypsum Board

Section 095123 Acoustical Tile Ceilings

Section 099113 Exterior Painting

Section 099123 Interior Painting

Division 26 – Electrical

Section 260000 Electrical, General

Section 260500 Common Work Results for Electrical

Section 260519 Low-Voltage Electrical Power Conductors and Cables

Section 260523 Control-Voltage Electrical Power Cables

Section 260526 Grounding and Bonding for Electrical Systems

Section 260529 Hangers and Supports for Electrical Systems

Section 260533 Raceway and Boxes for Electrical Systems

Section 260553 Identification for Electrical Systems

Section 262200 Low-Voltage Transformers

Section 262416 Panelboards

Section 262726 Wiring Devices

Section 262813 Fuses

Section 262816 Enclosed Switches and Circuit Breakers

Section 264313 Surge Protective Devices

Division 27 – Communications

Section 270500 Common Work Results for Communications

Section 271100 Communications Equipment Room Fittings

Section 271500 Communications Horizontal Cabling

Section 275123.50 Educational Integrated Electronic Communication System and Wireless Clock

System

TABLE OF CONTENTS TOC - 3

Division 28 – Electronic Safety and Security

Section 280500 Common Work Results for Electronic Safety and Security

Section 280513 Conductors and Cables for Electronic Safety and Security

Section 281300 Access Control

Section 281600 Intrusion Detection

Section 282300 Network Video Surveillance

Section 283111 Digital, Addressable Fire-Alarm System

END OF TABLE OF CONTENTS

ADVERTISEMENT FOR BIDS A1 - 1

BIDDING REQUIREMENTS

SECTION A1 – ADVERTISEMENT FOR BIDS

The Board of Education of School District U-46, Kane County, Illinois, hereby gives notice that sealed lump sum bids will be received for the Intercom Replacement Re-Bid at South Elgin High School, Project No. 285-26. The work includes the replacement of the intercom and clock system and all associated work at South Elgin High School, 760 E. Main Street, South Elgin, Illinois 60177. Refer to

Drawings and Project Manual for full extent of the work required.

CONSTRUCTION BONDS REQUIRED: Upon award of Contract, a Performance Bond and Material

& Labor Payment Bond will be required from the General Contractor for 100% of the contract sum, payable to the Owner.

PREVAILING WAGE LAW: This project is subject to the Illinois Prevailing Wage Act (820 ILCS

130).

PREQUALIFICATION PROCEDURE: All interested bidders are required to complete an AIA

Document A305 Contractor’s Qualification Statement and submit them with all bidding documents at the time of bid.

VIRTUAL MANDATORY PRE-BID MEETING: A Virtual MANDATORY Pre-Bid meeting will be conducted via a Zoom meeting on Wednesday, March 11, 2026, at 10:00 a.m. CT. Zoom credentials

(sign-in) for attendance at this meeting will be posted on the District’s Bid Portal (Bonfire) under “Public

Files.”

BID GUARANTEE: Contractors shall guarantee their submitted Bid Proposal for a ninety (90) day period from the date of Bid Opening.

BID PACKAGE SUBMITTAL: Bids will be due on March 20, 2026, at 10:30 a.m. CT via the School

District’s RFP/Bid Portal (refer to BID DOCUMENTS paragraph below for information on portal).

Contractors will upload all required bid forms and documentation individually to the bidding portal.

Refer to Form of Bid for all required bid documentation.

Receipt of a Bid Bond of ten percent (10%) of the amount of the base bid(s), (including all alternates and allowances) or a Cashier’s Check made payable to School District U-46, is required prior to the time of the virtual bid opening. Contractor shall send the original Bid Bond or Cashier’s Check to School District

U-46 Procurement Office, 1474 Sheldon Drive, Elgin, Illinois 60120, Attn: Danise Smith, via Certified mail, UPS, or FedEx to ensure confirmed delivery prior to the Bid Opening. If Contractor has an electronic certification process, then they will be able to upload the Bid Bond into the bidding portal. Bids will not be accepted without a Bid Bond / Cashier’s Check at Bid Opening. These can be dropped off Monday through Friday, 7:00 a.m. to 4:00 p.m. CT.

A Public Bid Opening will be conducted via a Zoom meeting on the bid’s established bid opening date and time. At that time, the bids will be unsealed and all bid totals will be read aloud and will be able to be visually viewed on the screen. Zoom credentials (sign-in) for attendance at this meeting, along with bid opening date and time, will be posted on the District’s Bid Portal (Bonfire) under “Public Files.” Invites will NOT be provided; therefore, it is the Bidders’ responsibility to obtain these Zoom credentials directly from the Portal prior to the Bid Opening.

BID DOCUMENTS: Bid Documents, including Drawings and Specifications, are available for download from the School District’s RFP/Bid Portal at https://u-46.bonfirehub.com/portal/?tab=login starting on Friday, March 6, 2026, at 8:00 a.m. CT. Registration is required to access the Bid

Documents; however, registration is easy and free!

https://u-46.bonfirehub.com/portal/?tab=login

ADVERTISEMENT FOR BIDS A1 - 2

If needed, registration instructions are available at:

https://customer.eunasolutions.com/public/s/article/vendor-registration

Please direct any questions during bidding through the Bonfire website. Bidders are requested not to contact U-46 Administrators, Staff, or Board Members, etc.

END OF ADVERTISEMENT FOR BIDS

https://customer.eunasolutions.com/public/s/article/vendor-registration

INSTRUCTIONS TO BIDDERS A2 - 1

BIDDING REQUIREMENTS

SECTION A2 – INSTRUCTIONS TO BIDDERS

Notice is hereby given by the Board of Education of School District U-46 in Kane County, Illinois that sealed lump sum bids will be received for the following:

Project: School District U-46

South Elgin High School

Intercom Replacement Re-Bid

760 E. Main Street

South Elgin, Illinois 60177

U-46 Project No. 285-26

Owner: School District U-46

355 East Chicago Street

Elgin, Illinois 60120

847-888-5000

Engineer: Mechanical Services Associates Corp.

111 S. Virginia Street

Crystal Lake, Illinois 60014

815-788-8901

PROJECT DESCRIPTION

The work includes, but is not limited to, the Intercom System Replacement Re-Bid and all associated work at

South Elgin High School, 760 E. Main Street, South Elgin, Illinois 60177. Refer to the Drawings and Project

Manual for the full extent of the Work.

** CONSTRUCTION SCHEDULE IS CRITICAL** Contractor shall commence work on the dates shown in the table on page 2 and shall complete all work in a diligent and professional manner by the dates indicated in the schedule on page 2. Any and all possible overtime, first and second shift work, and weekend work in order to accomplish completion of project in accordance with the construction schedules shall be included in the Contractor’s Bid. No extension of time or additional costs will be accepted after Contract Award.

Owner needs to be notified immediately of any known equipment delivery delays pertaining to this project which may affect substantial completion. Identify any known equipment delivery delays on

Section A3, Form of Bid.

PROJECT SCHEDULE

A Letter of Intent to Proceed, if deemed necessary, is anticipated to be issued by the School District on

April 14, 2026.

Project is broken out into two Phases. Contractor may work during the School Year during non-occupied hours, keeping the existing system operative and not affected by work being performed. Original system must be maintained during the entire project.

INSTRUCTIONS TO BIDDERS A2 - 2

Phase 1 Work:

A. Installation of all intercom/clock network cabling throughout the building. Cabling to be coiled up and supported above ceilings or in existing clock/speaker enclosures so as to be ready for new intercom/clock device installation.

B. Replacement of all intercom/clock devices in Area G Athletic Areas of the building including:

gymnasiums, pool, locker rooms, weight rooms, fitness rooms, wrestling rooms, training rooms, etc., and all corridors throughout the building (A thru G) and all exterior speakers.

C. Installation of new Telecor Admin Phones at (8) locations as selected by the Owner. Main office to include digital clock/message board for call-ins to be identified.

D. Two parallel systems (old and new systems) will be required to be operational until the new system is fully operational. All network switches, Telecor head end components, software, and programming will need to be installed for the above areas noted, for the new system to be operational.

E. Owner training will need to be provided on the new system. Intercom installation logs will need to be provided on a daily basis identifying what intercom components are on the old and new system.

Phase 2 Work:

A. Installation of all other remaining new intercom/clock system devices not previously completed under

Phase 1 work.

B. Removal of all existing/remaining intercom/clock system devices and cabling.

C. Final Owner training on the system and completing all final system adjustments as requested by the

Owner.

The construction schedule is as follows:

CONSTRUCTION SCHEDULE

April 14, 2026

Possible Letter of Intent/Notice to Proceed to be Issued.

• Start Shop Drawings and submit to Engineer within one week of receipt of Letter of Intent.

• Generate Construction Schedule for each school awarded and submit with signed AIA Contract

April 27, 2026

Anticipated Award of Contract by School District U-46 Board of

Education. Contract to be issued immediately the next day, April 28, 2026.

May 26, 2026

Work shall commence once: project is approved by the ROE;

Contractor has submitted signed Contract, Performance &

Payment Bonds, and Certificate of Insurance; AND receipt of

U46 Executed AIA Contract. Contractor may not start work on site until notified by Engineer.

INSTRUCTIONS TO BIDDERS A2 - 3

CONSTRUCTION SCHEDULE

August 7, 2026

Substantial Completion – Phase 1. Phase 1 work has been reviewed by the authorities having jurisdiction, Regional Office of Education (ROE), manufacturer’s representative and Engineer, all system certifications have been provided and all electrical devices connected and safe. Punchlist inspection has been requested and performed by the Engineer.

August 14, 2026

Final Completion – Phase 1 (This means that all Punchlist items for Phase 1 work shall be completed and all required closeout documents for Phase 1 work shall be submitted no later than this date.)

December 18, 2026

Substantial Completion – Phase 2. All remaining work has been reviewed by the authorities having jurisdiction, Regional

Office of Education (ROE), manufacturer’s representative and

Engineer, all system certifications have been provided and all electrical devices connected and safe. Punchlist inspection has been requested and performed by the Engineer.

December 31, 2026

Final Completion – Phase 2 (This means that all Punchlist items shall be completed and all closeout documents and final pay application shall be submitted no later than this date.)

The schedule of construction shall be closely coordinated with individual schools’ ongoing activities, sporting events, concerts, etc. The contractor will be required to coordinate site access and actual schedule of working dates.

The Contractor shall schedule work to achieve Substantial Completion, including working overtime, shift work, and/or weekends to complete work on the scheduled target dates and to not adversely inconvenience the

District in noted areas of work. Any and all possible overtime/second shift premium for this work in order to accomplish completion of project in accordance with the construction schedule shall be included in the

Contractor’s Bid.

CONSTRUCTION HOURS

Contractor to work with the School District in order to prioritize areas of the building to be completed first.

Areas with known intercom issues shall be completed first. All athletic areas and corridors must be completed first, PRIOR to the start of the 2026/2027 School Year. The goal is to have all cabling systems installed prior to the start of the 2026/2027 School Year. Substantial and Final Completion Dates for Summer 2026 work and Fall 2026 work are identified in the Bid Documents and specification section 010200 Completion Date.

During Summer Break 2026: Contractor may work all shifts while school is not in session, but must avoid areas where there may be summer school or athletic activities.

School Year 2026/2027: Once school is in session, the contractor will only be allowed to work during non-occupied hours (i.e., weekends, holidays, after school hours approximately after 4:00 p.m., etc.). Contractor must avoid areas where after school activities or athletic activities are happening. Refer to the School

District’s School Calendar on their website, www.u-46.org, for dates when school is in session.

Contractor must work with the School District for scheduling work after-school and on weekends, so as not to interrupt areas of the building being used for after school activities. Work shall be performed in those areas of the building when activities aren’t scheduled.

http://www.u-46.org/

INSTRUCTIONS TO BIDDERS A2 - 4

Contractor will be required to pay the School District for custodian straight time and overtime when working beyond normal school hours, or if working on Sundays or Holidays, at the following rates.

• Contractor will be charged for 3-hour minimum for out-of-hours work per occurrence.

• All Schools Weekdays after 10:00 p.m.: $71.33 per hour

• High Schools Saturdays after 3:00 p.m.: $71.33 per hour

• Elementary and Middle Schools Saturdays: $71.33 per hour

• All Schools Sundays and Holidays: $95.11 per hour

By submitting a bid, the Contractor guarantees he can meet this time schedule. No extension of time or additional costs will be accepted after Contract Award.

RADAR SCANNING

Radar Scan all floors before coring or saw cutting. Notify GC, Owner and Engineer of findings and if new work will conflict with any existing conduit or piping that may have been discovered in the floor system. If radar scans are not performed, the contractor will be responsible for all repair work needed to return the existing systems back to an operational condition.

PROTECTION OF OWNER’S BUILDING, EQUIPMENT, FURNITURE, ETC.

Contractor must provide masonite floor protection boards, taped at seams, to protect Owner’s flooring from damage from equipment, lifts, etc. In addition, contractor shall use Visqueen to cover/protect Owner’s equipment, furniture, lockers, cubbies, etc. from dust and debris. The contractor will be responsible for all repair work needed due to damage from lack of adequate protection.

DAILY SITE CLEAN UP:

Contractor shall protect the work area from all garbage/debris and clean up site at the end of the shift so that area is clean and ready for staff/students in the morning. Contractors shall cooperate with the Owner at all times and coordinate construction work to maintain the safety, health, and welfare of students, staff, workers and other contractors.

SCHOOL DISTRICT U-46 RAPTOR SYSTEM:

All staff will be required to sign in daily. All on-site personnel are required to be run through School District

U-46 Raptor System. This will need to be scheduled through BASCO as appointments are required.

Appointments can be scheduled from 6:30 a.m. to 10:30 a.m. CT and from 1:00 p.m. to 2:30 p.m. CT, Monday through Friday. Contact Jolene Linneman, Construction Project Coordinator at School District U-46, at 847-888-5000, ext. 2269, with any questions or concerns.

WARRANTY:

Warranty Letters will be required by all Contractors / Sub-contractors showing minimum 2 years coverage, or greater if specified in the Plans and Specifications. Submit with Close Out Documentation.

CLOSE OUT DOCUMENTATION:

Two sets of all close out documentation shall be required, including O&M’s, As-Built Drawings, Warranty

Letters, etc., saved on two USB flash drives. Refer to Division 01 Specifications for additional requirements.

INSTRUCTIONS TO BIDDERS A2 - 5

BACKGROUND CHECKS

Prior to the Pre-Construction meeting, Contractor is required to submit all background checks for each employee working on the project site, including employees of all subcontractors on the project. Refer to the

Project Manual Specification Section A8, Certificate Regarding Criminal Background Investigations for information on background checks.

LIQUIDATED DAMAGES

If the Contractor has not reached Substantial Completion on the dates as identified, it is the intent of the

School District to assess liquidated damages from the Contractual Substantial Completion dates until the actual Substantial Completion dates. Refer to the Project Manual for complete information regarding the specified Liquidated Damages: AIA A201 General Conditions of the Contract, and Specification Section

010200 Completion Date.

PRE-BID MEETING

There shall be a Virtual MANDATORY Pre-Bid meeting conducted via a Zoom meeting on Wednesday, March 11, 2026, at 10:00 a.m. CT. Zoom credentials (sign-in) for attendance at this meeting will be posted on the District’s Bid Portal (Bonfire) under “Public Files.”

PROPOSALS

Bids are invited from qualified Contractors for the complete construction of this Project, under one General

Contract (AIA A101), including all trades as specified in the Project Manual.

Bids will be due on Friday, March 20, 2026, at 10:30 a.m. CT via the School District’s RFP/Bid Portal (as explained in the Advertisement for Bids). Contractors will upload all required bid forms and documentation individually to the bidding portal. Refer to Form of Bid for all required bid documentation.

Receipt of a Bid Bond of ten percent (10%) of the amount of the base bid(s), (including all alternates and allowances) or a Cashier’s Check made payable to School District U-46, is required prior to the time of the virtual bid opening. Contractor shall send the original Bid Bond or Cashier’s Check to School District U-46

Procurement Office, 1474 Sheldon Drive, Elgin, Illinois 60120, Attn: Danise Smith, via Certified mail, UPS, or FedEx to ensure confirmed delivery prior to the Bid Opening. If Contractor has an electronic certification process, then they will be able to upload the Bid Bond into the bidding portal. Bids will not be accepted without a Bid Bond / Cashier’s Check at Bid Opening. These can be dropped off Monday through

Friday, 7:00 a.m. to 4:00 p.m. CT.

A Public Bid Opening will be conducted via a Zoom meeting on the bid’s established bid opening date and time. At that time, the bids will be unsealed and all bid totals will be read aloud and will be able to be visually viewed on the screen. Zoom credentials (sign-in) for attendance at this meeting, along with bid opening date and time, will be posted on the District’s Bid Portal (Bonfire) under “Public Files.” Invites will NOT be provided; therefore, it is the Bidders’ responsibility to obtain these Zoom credentials directly from the Portal prior to the Bid Opening.

Contractors shall guarantee their submitted proposal for a ninety (90) day period from Date of Bid Opening.

BID GUARANTEE

Bid Guarantee via Bid Bond / Cashier’s Check shall be submitted with the understanding that it shall guarantee that:

INSTRUCTIONS TO BIDDERS A2 - 6

1. The Bidder will not withdraw his Bid within 90 days after the date of the opening of Bids.

2. That the successful Bidder will enter into a formal Contract with the Owner and give such bonds as are required by the GENERAL CONDITIONS and SUPPLEMENTARY

GENERAL CONDITIONS.

3. In the event the Bid is withdrawn within the 90-day period after the date of the Bid opening, the Bidder shall be liable to the Owner for the full amount of the Bid Bond, and the Owners shall have the right to retain the proceeds of said Bid Bond to apply on the account of damages and excess costs which they may incur because of such withdrawal.

4. In case the Bid Guarantee is in the form of a Certified Check or Bank Draft, the Owner may make such disposition of same as will accomplish the purpose for which submitted.

Certified checks or Bank Drafts of all but the three lowest Bidders will be returned as soon as practicable after the opening of the Bids.

BID DOCUMENTS

Bid Documents, including Drawings and Specifications, are available for download from the School

District’s RFP/Bid Portal at https://u-46.bonfirehub.com/portal/?tab=login starting on Friday, March 6, 2026, at 8:00 a.m. CT. Registration is required to access the Bid Documents; however, registration is easy and free!

If needed, registration instructions are available at:

https://customer.eunasolutions.com/public/s/article/vendor-registration

Please direct any questions during bidding through the Bonfire website. Bidders are requested not to contact

U-46 Administrators, Staff, or Board Members, etc.

QUESTION & ANSWERS

No oral interpretations will be made to any Bidder as to the meaning of the Specifications or the Drawings.

Every request for an interpretation shall be made through Bonfire “Opportunity Q&A”.

Deadline to submit questions in Bonfire will be Friday, March 13, 2026, by 10:00 a.m. CT. All questions will be responded to by Tuesday, March 17, 2026, 10:00 a.m. CT, and posted in the form of an Addendum.

No questions will be responded through district email or by phone call.

All Addenda will be issued via Bonfire. Contractor will be required to sign and submit all Addenda acknowledgement pages (last page of Addenda) as part of their Bid Package.

QUALIFICATION FORMS

Contractors submitting bids on the above project must submit a completed AIA Document A305 General

Contractors Qualification Form (furnished by Contractor) with the Bid Documents. Form must include names and telephone numbers of architects, owners, and contact persons for each project listed. See Supplemental

Contractor Qualification Statement for more information. Contractor qualifications may be a determining factor in identifying the lowest responsible bidder.

AWARD OF CONTRACTS: REJECTION OF BIDS

Contract will be awarded to the responsible Bidder submitting the lowest proposal complying with the conditions of the Bidding Documents, provided their Bid is reasonable and it is to the best interest of the

Owner to accept it. The Bidder to whom the Contract is awarded will be notified at the earliest practicable date. The Owner, however, reserves the right to reject any and all Bids and to waive any informality, https://u-46.bonfirehub.com/portal/?tab=login https://customer.eunasolutions.com/public/s/article/vendor-registration

INSTRUCTIONS TO BIDDERS A2 - 7

irregularity, or qualifications in the Bids received whenever such rejection or waiver is in the best interest of the Owner.

The Owner also reserves the right to reject the Bid of any Bidder who:

▪ Has previously failed to perform properly.

▪ Has failed to complete on time Contracts of similar nature.

▪ Is not in a position to perform the work required promptly.

▪ Has habitually, and without just cause, neglected the payment of bills or otherwise disregarded his obligations to subcontractors, materialmen and/or employees.

In determining the lowest responsible Bidder, the following elements, in addition to those heretofore mentioned, will be considered, whether the Bidder involved:

▪ Maintains a permanent place of business.

▪ Has adequate plant, equipment and men available to do the work properly and expeditiously.

▪ Has suitable financial resources to meet the obligations incidental to the work.

▪ Has the appropriate technical experience, qualified project management and project superintendent personnel.

The Owner reserves the right to consider as unqualified to perform the General Contract Work any Bidder who does not habitually perform with his own forces at least one major trade (e.g., cast-in-place concrete;

carpentry; demolition; general laborers; masonry).

The ability of a Bidder to obtain a Performance and Payment Bond shall not be regarded as the sole test of such Bidder’s competency or responsibility.

EXECUTION OF CONTRACT

Subsequent to the award and within ten days after the Agreement forms are presented for signature, successful

Bidder shall sign the Agreement and deliver it to the Owner via Mechanical Services Associates Corp. in such number of counterparts as the Owner may require. The Agreement will be on AIA Document A101, 2017

Edition.

Having satisfied all conditions of the award as set forth elsewhere in these Documents, successful Bidders shall, within the ten days specified above, furnish a Performance and a Labor and Material Payment bond each in the amount of the Contract as awarded, as a security for the faithful performance of the Contract, and for the Payment of all persons, firms, or corporations to whom the Contractor may become legally indebted for labor, materials, tools, equipment, or services, of any nature, employed or used by him in performing the work. Such bonds shall be in the form of AIA Document A312 and shall bear the same date as, or a date subsequent to date of Contract Agreement.

Each Bidder must be bondable at time bids are due, and he shall so state in his bid. The failure of successful

Bidders to execute such Contract and to supply the required Bonds within ten days after the prescribed forms are presented for signature or if bonding company finds that a Bidder is NOT bondable, shall constitute a default, and the Owner may either award the Contract to the next responsible Bidder or re-advertise for Bids, and may charge against such Bidder the difference between amount of his Bid and amount for which the

Contract for the work is subsequently executed, irrespective of whether the amount thus due exceeds amount of his Bid Guarantee.

END OF INSTRUCTIONS TO BIDDERS

AUTHORIZATION FOR CRIMINAL BACKGROUND INVESTIGATIONS A9 - 1

BIDDING REQUIREMENTS

SECTION A9 – AUTHORIZATION FOR CRIMINAL BACKGROUND INVESTIGATIONS

NOTE: This form is not required for submittal with bid. This is the form referred to in Section A8 for use with employment applications.

AUTHORIZATION FOR CRIMINAL BACKGROUND INVESTIGATION INFORMATION

The undersigned hereby authorizes the Board of Education, School District U-46, Kane County, Illinois, to request a criminal background investigation from the Illinois State Police, pursuant to Section 5/1-21.9 of the

School Code of Illinois, 105 ILCS 5/10-21.9 and to receive criminal history record information thereto.

By: _________________________________________________________________________

Printed Name of Applicant Employee

Signature of Applicant Employee

Date

END OF SECTION A9

FORM OF BID A3 - 1

BIDDING REQUIREMENTS

SECTION A3 – FORM OF BID

Bid To: Board of Education

School District U-46

355 East Chicago Street

Elgin, Illinois 60120

Bid From:

Bidder’s Name

Bidder’s Street Address

Bidder’s City, State, Zip Code

Telephone No. Fax No.

Primary Contact Name / Email Address

The Undersigned:

1.1 ACKNOWLEDGES RECEIPT OF

A. Project manual/drawings for the Intercom Replacement Re-Bid and all associated work at

South Elgin High School, located at 760 E. Main Street, South Elgin, Illinois 60177.

1. U-46 Project No. 285-26; MSA Project No. 2554.

2. Out-to-Bid Date: March 6, 2026.

3. A Virtual MANDATORY Pre-Bid meeting will be conducted via a Zoom meeting on

Wednesday, March 11, 2026, at 10:00 a.m. CT.

4. Virtual Bid Opening: March 20, 2026, 10:30 a.m. CT.

B. Warranty Requirements: Warranty Letters will be required by all Contractors / Sub-contractors showing minimum 2 years coverage, or greater if specified in the Plans and Specification.

Submit with Close Out Documentation.

C. Close Out Documentation Requirements: Two sets of all close out documentation shall be required, including O&M’s, As-Built Drawings, Warranty Letters, etc., also saved on two USB flash drives. Refer to Division 01 Specifications for additional requirements.

1.2 Has examined the site(s) where the work is to be executed and has become familiar with local conditions as they might in any way affect the cost and/or execution of this work, and has carefully examined the bidding documents and addenda thereto.

1.3 AGREES

A. That this bid may not be withdrawn until 90 calendar days after bid opening date without permission of Owner.

FORM OF BID A3 - 2

B. To accept the provisions of the Instructions to Bidders regarding disposition of bid security and project requirements.

C. To enter into the execution of a contract with School District U-46, if awarded on the basis of this bid and in connection therewith to:

1. Letter of Intent, if needed, is scheduled to be issued on April 14, 2026. Contractor shall complete and submit shop drawings to Architect/Engineer within one week of receipt of Letter of Intent.

2. Furnish all bonds and insurance and certification required by the bidding documents.

3. Accomplish the work in accordance with the contract and provide all labor, materials, equipment, transportation and other facilities as necessary and/or required for the completed and satisfactory execution of the work for each Base Bid.

4. Any and all fees related to overtime work, second shift work premiums, etc., in order to accomplish completion of project in accordance with the construction schedule, are included in the Contractor’s Bid. No extension of time or additional costs will be accepted after Contract Award. Refer to Specification Section A2

Instructions to Bidders for details.

5. Complete the work within the contract time herein specified. Refer to Specification

Section 010200 “Completion Date” for more information.

a. Contract Date: April 28, 2026.

b. Estimated Start Date is May 26, 2026. Work shall commence once: project is approved by the ROE; Contractor has submitted signed Contract, Performance &

Payment Bonds, and Certificate of Insurance; AND receipt of U46 Executed AIA

Contract. Contractor may not start work on site until notified by Engineer.

c. Substantial Completion Date – Phase 1: August 7, 2026. Phase 1 work has been reviewed by the authorities having jurisdiction, Regional Office of Education

(ROE), manufacturer’s representative and Engineer, all system certifications have been provided and all electrical devices connected and safe. Punchlist inspection has been requested and performed by the Engineer.

d. Final Completion Date – Phase 1: August 14, 2026. This means that all Punchlist items for Phase 1 work shall be completed and all required closeout documents for

Phase 1 work shall be submitted no later than this date.

e. Substantial Completion Date – Phase 2: December 18, 2026. All remaining work has been reviewed by the authorities having jurisdiction, Regional Office of

Education (ROE), manufacturer’s representative and Engineer, all system certifications have been provided and all electrical devices connected and safe.

Punchlist inspection has been requested and performed by the Engineer.

f. Final Completion and Closeout Date – Phase 2: December 31, 2026. This means that all Punchlist items shall be completed and all closeout documents and final pay application shall be submitted no later than this date.

FORM OF BID A3 - 3

6. Base Bid A: Replace existing intercom and clock system as identified and provide all associated trades work at South Elgin High School, U-46 P.N. 285-26, as identified on the plans and specifications.

**Contractor’s dollar amounts below MUST MATCH the dollar amounts

Contractor enters in the Pricing Spreadsheet on the Bid Portal. If numbers do not match, Bid may be rejected.**

Bidder agrees to perform all work as set forth in the bidding documents for the sum of:

Sub-Total Base Bid A: $

General Allowance: $ 200,000.00

TOTAL BASE BID A: $

7. Unit Pricing for Intercom and Clock Unit Devices, per device, as follows. For each device, include raceway stubs and wiring for up to 200 feet.

a. Unit Price 1: Custom coverplate with combination speaker and digital clock/message board $ /device

b. Unit Price 2: Recessed mounted network ceiling talk-back speaker with back can and support bars $ /device

c. Unit Price 3: Surface mounted network talk-back speaker $ /device

d. Unit Price 4: Recessed mounted analog paging speaker with back can and support bars $ /device

e. Unit Price 5: Surface mounted analog paging speaker $ /device

f. Unit Price 6: Exterior rated analog weatherproof paging speaker $ /device

g. Unit Price 7: Network pair of call-back switches

(with Normal and Emergency Call switch) $ /device

h. Unit Price 8: Network volume control switch with priority over-ride $ /device

i. Unit Price 9: Network zone page amplifier $ /device

j. Unit Price 10: Network status light $ /device

k. Unit Price 11: Telecor network digital clock/message board with backbox. $ /device

l. Unit Price 12: Pro-Lite network digital clock/message board

(Large) with mounting bracket $ /device

m. Unit Price 13: Network double-sided digital clock/message board with status light with mounting brackets for corridors $ /device

n. Unit Price 14: 50-watt analog amplifier for paging speakers $ /device

o. Unit Price 15: System Administrative control console $ /device

FORM OF BID A3 - 4

p. Unit Price 16: Network switch 24 port $ /device

q. Unit Price 17: Network switch 48 port $ /device

8. Bid Security for 10% of TOTAL base bids, including allowances, and any alternate bids, must be submitted to School District U-46 prior to Bid Opening.

D. Identify below any known equipment delivery delays pertaining to this project which may affect substantial completion:

E. In case the contractor fails or neglects to appear within the specified time to execute the contract, the contractor will be considered as having abandoned the project. The bid security accompanying this proposal will be forfeited to the Owner as liquidated damages for the delay and loss caused to the Owner by reason of such failure on the part of the contractor.

F. Prior to the Pre-Construction meeting, Contractor is required to submit all background checks for each employee working on the project site, including employees of all subcontractors on the project. Refer to the Project Manual Specification Section A8, Certificate Regarding Criminal

Background Investigations for information on background checks.

G. Failure to complete the work by the scheduled completion date (refer to Section 010200) will result in the work being rescheduled and will result in liquidated damages to the contractor

(refer to Section 010200 for details).

H. Surety: The contractor has notified a surety company of the bid for work to be performed on the project. The surety company has agreed to issue a Performance Bond and Labor and Material

Payment Bond for the work for each school/contract awarded if the bid is accepted.

I. Availability: The number and amount of other contracts and awards pending which the contractor will become obligated to perform, now and during the course of the work on this project will not interfere with or hinder the timely prosecution of the work.

J. Material or equipment substitution sheet: The following is a schedule of substitute materials or equipment bidder proposes to furnish on this project with the difference of price being added to or deducted from the base bid. The base bid is understood to include only those items which are definitely specified by trade or brand names.

1. Bidder understands that the selection of materials is optional with the Owner and approval or rejection of the substitutions below will be indicated prior to execution of the contract.

Manufacturer’s Name and Product Add Deduct

FORM OF BID A3 - 5

2. Cost of investigating or approving substitutions by the Architect, Engineer, Owner, or

Owner’s Attorneys shall be borne by the Bidder proposing the substitution.

K. Bidder must provide the following required bid documentation:

1. Receipt of a Bid Bond of ten percent (10%) of the amount of the base bid(s), (including all alternates and allowances) or a Cashier’s Check made payable to School District

U-46, is required prior to the time of the virtual bid opening. Contractor shall send the original Bid Bond or Cashier’s Check to School District U-46 Procurement Office, 1474 Sheldon Drive, Elgin, Illinois 60120, Attn: Danise Smith, via Certified mail, UPS, or FedEx to ensure confirmed delivery prior to the Bid Opening. If Contractor has an electronic certification process, then they will be able to upload the Bid Bond into the bidding portal. Bids will not be accepted without a Bid Bond / Cashier’s Check at Bid

Opening. These can be dropped off Monday through Friday, 7:00 a.m. to 4:00 p.m. CT.

2. The following documentation shall be INDIVIDUALLY uploaded to the Bid Portal:

a. Completed AIA Document A305 Contractor’s Qualification Statement. Form must include names and telephone numbers of architects, owners and contact persons for each project listed.

b. All Signed Addenda.

c. Project Manual Forms (Provided in Project Manual):

1) Form A3, Form of Bid

2) Form A4, Bidder Eligibility Certification and Non-Collusion Affidavit

Pursuant to Public Act 85-1295 (720 ILCS 5/33E-1 et seq.)

3) Form A5, Prevailing Wage Payment Certification

4) Form A6, Certificate of Compliance with Illinois Human Rights Act

(775 ILCS 5/1-101 et seq.)

5) Form A7, Certificate of Compliance with Illinois Drug-Free Workplace Act

6) Form A8, Certificate Regarding Criminal Background Investigations

7) Form A10, Asbestos and/or Lead Free Construction Certification

8) Form A11, Certification of Sexual Harassment Policy

9) Form A12, Certification of Monthly Payroll

3. The successful bidder for the project will be required to enter into a Performance Bond, for each AIA Contract/school award, equal to one hundred percent (100%) of the amount of the bid, with sureties to be approved by the Owner, which surety bond shall be conditioned upon proper and faithful performance by the contractor of the work specified in accordance with the plans and specifications therefore, and according to the time and terms and conditions of the contract, and also that the bidder and contractor shall properly pay all debts incurred by him in the prosecution of the work, including those for labor and material furnished.

4. The contractor shall be required to furnish sufficient insurance of guarantee to indemnify the School District U-46, Architect/Engineer and their consultants against any and all claims which might arise from damages caused to persons or property due to the negligence or accidents caused by himself, his employees or agents, during the construction of said improvements and until the said improvements have been finally accepted as complete by School District U-46.

FORM OF BID A3 - 6

L. Contractor shall include contingency allowances in the respective amounts shown and shall be included in the Base Bids as follows:

1. Base Bid A General Allowance: .................................................................... $ 200,000.00

Use of any portion of the allowance shall be by an approved U-46 Allowance or Credit

Authorization form only. Any portion of the contingency allowance not used in construction phase shall be deducted from Contract via AIA G701 Change Order.

1.4 CONSIDERATION:

A. Contract will be awarded to the responsible Bidder submitting the lowest proposal complying with the conditions of the Bidding Documents, provided their Bid is reasonable and it is to the best interest of School District U-46 to accept it. The Bidder to whom the Contract is awarded will be notified at the earliest practicable date. School District U-46, however, reserves the right to reject any and all Bids and to waive any informality, irregularity, or qualifications in the Bids received whenever such rejection or waiver is in the best interest of School

District U-46.

B. Any bidder challenging bids by other contractors or bid award by School District U-46 will be responsible for all costs to School District U-46, Architect, Engineer, and their Attorneys to investigate and defend such challenges.

C. School District U-46 also reserves the right to reject the Bid of any Bidder who:

1. Has previously failed to perform properly.

2. Has failed to complete on time Contracts of similar nature.

3. Is not in a position to perform the work required promptly.

4. Has habitually, and without just cause, neglected the payment of bills or otherwise disregarded his obligations to subcontractors, materialmen and/or employees.

D. In determining the lowest responsible Bidder, the following elements, in addition to those heretofore mentioned, will be considered, whether the Bidder involved:

1. Maintains a permanent place of business.

2. Has adequate plant, equipment and manpower available to do the work properly and expeditiously.

3. Has suitable financial resources to meet the obligations incidental to the work.

4. Has the appropriate technical experience, qualified project management and project superintendent personnel.

5. Has a minimum of five (5) years’ experience operating under current company name with multiple similar projects successfully completed with equal or greater value.

6. Is licensed and/or certified to complete work associated with this bid.

E. School District U-46 reserves the right to consider as unqualified to perform the General

Contract Work any Bidder who does not habitually perform with his own forces at least two major trades. Examples include Cast-in-Place Concrete, Carpentry, Demolition, General

Laborers and Masonry.

F. The ability of a Bidder to obtain a Performance Bond shall not be regarded as the sole test of such Bidder’s competency or responsibility.

FORM OF BID A3 - 7

1.5 BIDDER REPRESENTATION: In proposing the material and equipment substitutions herein the bidder represents:

A. He has personally investigated the proposed substitutions and has determined that it is equal or superior in all respects to the specified.

B. He will provide the same guarantee for the substitution as for the item specified.

C. He will coordinate installation of an accepted substitution into the work, making all such changes as may be required for the work to be complete in all respects.

D. He waives all claims for additional costs related to the substitution.

E. Cost data is complete and includes all related costs under his contract and will pay all required architect/engineer's redesign costs.

F. Contract award will not be based on substitute cost difference.

G. All permit fees (if applicable) are included in this bid.

1.6 GENERAL STATEMENT

A. The undersigned has checked all of the figures contained in this proposal and further understands that School District U-46 will not be responsible for any errors or omissions made therein by the undersigned. This bid constitutes all work.

B. It is understood that the right is reserved by School District U-46 to reject any or all proposals and to waive all informalities in connection therewith.

C. The undersigned declares that the person(s) signing this bid is/are fully authorized to sign on behalf of the named firm and to fully bind the named firm to all the conditions and provisions thereof.

D. It is agreed that no person(s) or company other than the firm listed below or as otherwise indicated hereinafter has any interest whatsoever in this proposal or the contract that may be entered into as a result thereof, and that in all respects the proposal is legal and fair and submitted in good faith without collusion or fraud.

E. It is agreed that the undersigned has complied and/or will comply with all requirements concerning licensing and with all other local, state and national laws, including prevailing wages of the county working in, and that no legal requirement has been or will be violated in making or accepting this bid, in awarding the contract to him, and/or in the prosecution of the work required thereunder.

F. Contractor and all sub-contractors must pay prevailing wages to all employees working on public funded projects during the course of this project. Prevailing wage shall be as scheduled by the county for which the work is contracted. Payment of Prevailing Wages must conform to the Illinois Prevailing Wage Act, 820 ILCS section 130/0.01 and all related sections.

Additionally, Contractors and sub-contractors must enter ALL Certified Payrolls for all employees for this project via the Illinois Department of Labor (IDOL) website at:

https://www2.illinois.gov/idol/Laws-Rules/CONMED/Pages/Prevailing-Wage-Portal.aspx

FORM OF BID A3 - 8

Certified Payrolls are NOT to submitted with Applications for Payment. The primary

Contractor shall have the responsibility to be sure all Certified Payrolls related to this project have been uploaded to the IDOL website.

G. All bidders must comply with applicable Illinois Statutory requirements regarding labor including equal employment opportunity laws. Per Employment of Illinois Workers on Public

Works Projects Act (30 ILCS 570/3), Ch. 48, par. 2203, Sec. 3: Whenever there is a period of excessive unemployment in Illinois, every person who is charged with the duty, either by law or contract, of constructing or building any public works project or improvement or for the clean-up and on-site disposal of hazardous waste for the State of Illinois or any political subdivision, municipal corporation or other governmental unit thereof shall employ only Illinois laborers on such project or improvement, and every contract that such labor be used: Provided, that other laborers may be available, or are incapable of performing the particular type of work involved, if so certified by the contractor and approved by the contracting officer.

1.7 LITIGATION

A. Previous Litigation, Past Five (5) Years:

1.

Status:

2.

B. Current Litigation:

1.

2.

FORM OF BID A3 - 9

1.8 SIMILAR PROJECT EXPERIENCE

A. Client: Contract Amount:

1.

2.

3.

Respectfully submitted this ____________________ day of ____________________________, 20_____.

Firm Name of Bidding Contractor Printed Name of Authorized Agent of Contractor

By:

Signature of Authorized Agent of Contractor Title

END OF SECTION A3

Subscribed and sworn to before me this ____________ day of

____________________, 20_____.

Notary Public Signature

SSSTTTAAAMMMPPP

ELIGIBILITY CERTIFICATION AND NON-COLLUSION AFFIDAVIT PURSUANT A4 - 1

TO PUBLIC ACT 85-1295 (720 ILCS 5/33E-1 et seq.)

SOUTH ELGIN HIGH SCHOOL – INTERCOM REPLACEMENT RE-BID U-46 P.N. 285-26

BIDDING REQUIREMENTS

SECTION A4 – BIDDER ELIGIBILITY CERTIFICATION AND NON-COLLUSION AFFIDAVIT

PURSUANT TO PUBLIC ACT 85-1295 (720 ILCS 5/33E-1 et seq.)

The following certification must be completed, signed, and submitted with the Bidder’s Form of Bid.

FAILURE TO DO SO WILL RESULT IN DISQUALIFICATION OF THE BIDDER.

_______________________________________________, as part of its bid on a contract for:

(Firm Name of Bidding Contractor)

School District U-46

South Elgin High School

Intercom Replacement Re-Bid

760 E. Main Street

South Elgin, Illinois 60177

U-46 Project No. 285-26 hereby certifies that the bidding part/contracting party is not barred from bidding on the aforementioned contract as a result of a violation of Section 33E-3, Section 33E-4, or the Act.

AFFIDAVIT: The undersigned further certifies and affirms that this proposal was prepared independently for this project and that it contains no fees or amounts other than for the legitimate execution of this work as specified and that it includes no understandings or agreements in restraint of trade.

By: ______________________________________________ Signature of…