This is a pricing section document for Electrical Contract No. 2026-07B, part of the Raw Sewage Pump Replacement Project issued by Rostraver Township in Pennsylvania. The project involves the replacement of existing raw sewage pumps with new pumps, piping, and valves within the wastewater treatment plant, with an expected duration of 365 days. Sealed bids were required to be submitted electronically via the PennBid Program by October 29, 2026, at 10:00 A.M. local time, with public opening and reading of bids at the Township Office located at 201 Municipal Drive, Rostraver Township, PA 15012. Bidding documents were available at no cost through PennBid at pennbid.bonfirehub.com, and prevailing wage requirements applied to all contractors on the project in accordance with Pennsylvania Department of Labor and Industry regulations.
The pricing section presents bids from five electrical contractors: Bronder Technical Services, Inc. ($109,883.00), Lanco Electric, Inc. ($84,800.00), NexGen Industrial Services Inc. ($114,500.00), Rath Construction Inc. dba Genesis Construction Group ($101,037.00), and Ridgeline Industries ($137,134.00). All bids include two line items: a lump sum bid price for electrical construction and a mandatory $10,000.00 contingency allowance for unforeseen circumstances. The project required compliance with the Public Works Employment Verification Act (Act 127 of 2012) and mandated the use of steel products from specified sources. Awarded bidders were assessed a fee to be confirmed with PennBid upon contract award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Total Cost
# Items Quantity RequiredUnit of MeasureUnit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost
#1-1 Lump Sum Bid Price - Electrical Construction 1 Lump Sum $ 99,883.0 $ 99,883.0 $ 74,800.0 $ 74,800.0 $ 104,500.0 $ 104,500.0 $ 91,037.0 $ 91,037.0 $ 127,134.0 $ 127,134.0
#2-1
Contingency Allowance for Unforeseen Circumstances
(Bidder MUST enter $10,000) 1 Lump Sum $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0
$ 109,883.0 $ 84,800.0 $ 114,500.0 $ 101,037.0 $ 137,134.0
Bronder Technical Services, Inc. Lanco Electric, Inc. NexGen Industrial Services Inc. Rath Construction Inc. dba Genesis Construction Group Ridgeline Industries