4-Pricing Section - General Mechanical Contract No. 2026-07A.pdf
PDF 201 KB Posted
- Solicitation number
- US.254624
- Issued by
- Westmoreland County, Richland Borough, Pennsylvania
About this file
This pricing section document pertains to the Raw Sewage Pump Replacement Project (Contract Nos. 2026-07A & 2026-07B) for Rostraver Township in Pennsylvania. The project involves the replacement of existing raw sewage pumps, piping, and valves within the wastewater treatment plant, with an expected duration of 365 days. Sealed bids were to be received electronically via the PennBid Program until Thursday, October 29, 2026, at 10:00 A.M. local time, with public opening and reading at the Township Office located at 201 Municipal Drive, Rostraver Township, PA 15012. Bidding documents were available at no cost through PennBid at pennbid.bonfirehub.com, with all official notifications and addenda provided exclusively through this designated website.
The pricing table presents bids from seven contractors for the General/Mechanical Construction work. The lump sum bid prices for item #1-1 ranged from $711,232.01 (lowest) to $2,111,000.00, with all bidders required to enter $10,000.00 for item #2-1 (Contingency Allowance for Unforeseen Circumstances). The seven bidding contractors were Verardi Landscapes LLC, Westmoreland Construction Group Inc., FERRI CONTRACTING CO INC, Gildea Group LLC, Greenland Const., Inc., Hogen's Heroes, Inc. dba J5 Construction, and Lone Pine Construction, Inc. The project required compliance with prevailing minimum wage rates as determined by the Pennsylvania Department of Labor and Industry, and all contractors were required to meet the Public Works Employment Verification Act (Act 127 of 2012) requirements. Additionally, any steel products used in contract performance were required to be from approved sources.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Total Cost
# Items Lowest Quantity RequiredUnit of MeasureUnit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost Unit Price Total Cost
#1-1 Lump Sum Bid Price - General/Mechanical Construction $ 711,232.01 Lump Sum $ 725,000.0 $ 725,000.0 $ 769,000.0$ 769,000.0 $ 2,111,000.0 $ 2,111,000.0 $ 1,249,000.0 $ 1,249,000.0 $ 985,678.0 $ 985,678.0 $ 975,000.0 $ 975,000.0 $ 711,232.0 $ 711,232.0
#2-1
Contingency Allowance for Unforeseen Circumstances
(Bidder MUST enter $10,000) $ 10,000.0 1 Lump Sum $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0 $ 10,000.0
Verardi Landscapes LLC Westmoreland Construction Group Inc.
$ 735,000.0 $ 779,000.0 $ 2,121,000.0 $ 1,259,000.0 $ 995,678.0 $ 985,000.0 $ 721,232.0
FERRI CONTRACTING CO INC Gildea Group LLC Greenland Const., Inc. Hogen's Heroes, Inc. dba J5 Construction Lone Pine Construction, Inc.