This is a set of architectural and engineering drawings for a Competitive Sealed Proposal issued by Harris County on behalf of Harris Health Systems for a Room Upgrade and Gamma Camera Replacement project at Lyndon B. Johnson Hospital located at 5656 Kelley Street, Houston, Texas 77026. The project involves the renovation of the Nuclear Medicine Suite on the third floor, encompassing approximately 493 square feet of renovated space within a 3,148-square-foot nuclear medicine department. The scope includes demolition of existing fixtures and systems, installation of new gamma camera equipment with associated structural anchoring systems, replacement of ceiling tiles and grid systems, reconfiguration of partitions, installation of new flooring finishes, and comprehensive updates to mechanical, electrical, plumbing, and fire protection systems. The project is classified as Construction Type IA with Group I-2 institutional occupancy, requiring compliance with 2021 International Building Code standards and applicable local amendments. Equipment installations include a CT gantry, NM gantry, patient table, collimator cart, and associated power distribution and UPS systems furnished by the equipment vendor, with critical coordination requirements for anchor point locations relative to existing structural elements and reinforcement.
The estimated budget for this project is $320,225. The contract documents specify detailed requirements for structural coordination, including post-installed anchors with non-destructive evaluation to locate existing reinforcement, careful sequencing to avoid damage to existing pan-formed beam reinforcement, and submittal of final anchor layouts for review by the architect, structural engineer, and equipment vendor. Mechanical systems require balancing of existing dual-duct VAV terminal units to achieve negative room pressure of -0.02 inches relative to corridor, installation of a new room pressure monitor, and rebalancing of the exhaust system. Electrical work includes extension of critical and normal branch circuits, installation of new lighting fixtures with specific color temperature and lumen requirements, and connection of equipment in accordance with vendor specifications. Fire protection modifications must provide full NFPA 13 compliance with minimum 10 PSI margin of safety, and all work must maintain compliance with Texas Department of State Health Services Hospital Licensing Rules and maintain existing utilities to occupied spaces throughout construction with 72-hour advance notice required for any utility shutdowns or disruptions.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Structural Engineer
401 S. 1st Street , Suite 600 Austin , TX 78704
Martinez Moore Engineering
811 BARTON SPRINGS ROAD, SUITE 900
AUSTIN, TEXAS 78704
Architecture - Engineering - Interiors
4800 FOURNACE PLACE , SUITE 5E
BELLAIRE , TX 77401
HARRIS HEALTH
Healthcare Systems
3615 Willowbend Boulevard Houston , TX 77054
GE
Revisions:
A u s ti n
S a n A n to n io
H o u st o n
B a rt o n
S p ri n g s
R o a d
Su it e
A u st in Te xa s
B ro a d w a y Su it e
S a n A n to n io
Te xa s
F a n n in
S tr e e t, S u it e
H o u st o n
Te xa s p
.4
.7 f
.4
.7 p
.2
.6 f
.2
.6 p
.4
.1 f
.4
.1
25-2MC02328
A u to d e s k D o c s
/H a rr is
H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/
H
H S
L B
J G a m m a
C a m e ra R p lc m n t_ A
R C
H
C e n tr a l.
rv t
/2
/2
:1
:1
P M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K
E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
LBJ SCAN SYS/GAMMA/SINGLE PHOTON EMISSION
5656 KELLEY STREET, HOUSTON, TX 77026
12/23/2025
CONTRACT DOCUMENTS
Mission: We believe every project has a mission and strive to design environments that have a purpose that extends far beyond form and function.
12/23/2025
CONTRACT DOCUMENTS
COVER SHEET
G1.0
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
Project No. 2321.08
NO. DESCRIPTION DATENO. DESCRIPTION DATE
12/22/2025
1. GENERAL NOTES APPLY TO ALL SHEETS.
2. THE CONTRACTOR SHALL FURNISH ALL LABOR, MATERIALS,
TOOLS, EQUIPMENT, AND RELATED ITEMS REQUIRED TO
COMPLETE THE DEMOLITION WORK AS INDICATED BY THE
CONTRACT DOCUMENTS.
3. CONTRACTOR TO VERIFY ALL DIMENSIONS.
4. ALL ACCESSIBLE ROUTES (OTHER THAN RAMPS) SHALL NOT
EXCEED A SLOPE OF 1:20, AND CROSS SLOPES SHALL NOT
EXCEED A SLOPE OF 1:50
5. THE DRAWINGS INDICATE BUILDING CONDITIONS PER
EXISTING DRAWINGS AND ACTUAL PROJECT
INVESTIGATION. THE CONTRACTOR SHALL ANTICIPATE
POSSIBLE SLIGHT DEVIATION FROM THESE DRAWINGS.
REFER TO ARCHITECTURAL & MEP DRAWINGS AND DETAILS
FOR EXTENT OF DEMOLITION.
6. THE CONTRACTOR SHALL SUPERVISE AND DIRECT THE
WORK, USING THEIR BEST SKILL AND ATTENTION. THEY
SHALL BE SOLELY RESPONSIBLE FOR ALL MEANS,
METHODS, TECHNIQUES, SEQUENCES AND PROCEDURES
AND FOR COORDINATING ALL PORTIONS OF THE WORK
UNDER THE CONTRACT.
7. INSTALL TEMPORARY DUST PARTITIONS WITH DOORS FOR
CONSTRUCTION ACCESS AROUND AREAS OF WORK SO
THAT OPERATIONS IN EXISTING ADJACENT AREAS REMAIN
DUST FREE AND ACCESSIBLE TO BUILDING OCCUPANTS.
MAINTAIN IN PLACE UNTIL COMPLETION OF CONSTRUCTION.
8. REMOVE ALL BUILDING PARTS AND/OR OTHER ITEMS TO
ALLOW FOR THE INSTALLATION AND CONNECTION OF NEW
WORK, COORDINATE THE WORK WITH THE HVAC,
PLUMBING AND ELECTRICAL DEMOLITION DRAWINGS.
9. REMOVAL OF THE BUILDING PARTS SHALL BE PERFORMED
IN A SAFE, ORDERLY AND CAREFUL MANNER, WITH THE
CONSIDERATION AT ALL TIMES FOR THE SAFETY AND
WELFARE OF THE OWNER, BLDG. OCCUPANTS, &
PERSONNEL OF THE CONTRACTOR AND/OR
SUBCONTRACTOR.
10. MAINTAIN THE UTILITIES TO OCCUPIED SPACES AT ALL
TIMES. COORDINATE ANY UTILITY DOWNTIMES W/ OWNER.
PROVIDE 72 HOUR ADVANCE NOTICE TO THE OWNER OF
INTENDED UTILITY SHUT DOWN AND/OR DISRUPTION.
11. ANY QUESTIONS CONCERNING OWNERSHIP OF
SALVAGEABLE MATERIAL SHALL BE ANSWERED BY THE
OWNER, OR OWNER'S REPRESENTATIVE. ALL ITEMS OTHER
THAN FINISH MATERIALS TO BE REMOVED AS PART OF THIS
CONTRACT ARE INDICATED WITH DASHED LINES ON
DEMOLITION SHEETS. DISPOSE OF THESE MATERIALS AND
ITEMS AFTER CHECKING WITH OWNER FOR ITEMS TO BE
SALVAGED. SALVAGE ANY ITEMS REQUIRED TO COMPLETE
NEW WORK.
12. REMOVE ALL MISCELLANEOUS DEVICES AS REQUIRED TO
INSTALL NEW FINISHES, INCLUDING BUT NOT LIMITED TO:
PLUMBING FIXTURES, SIGNAGE, SWITCH PLATES,
TELEVISION BRACKETS, WALL OUTLET COVERS, TOILET
ACCESSORIES, CORNER GUARDS, ETC. SAVE FOR
REINSTALLATION AFTER COMPLETION OF FINISH WORK.
13. PROTECT ALL EXISTING FINISHES, DOOR FRAMES,
EQUIPMENT AND MATERIALS THAT ARE TO REMAIN IN
PLACE. DAMAGE TO EXISTING COMPONENTS BY
CONTRACTOR SHALL BE REPLACED WITH NEW MATERIAL
OF LIKE KIND AND QUALITY THAT MATCH THE EXISTING
STANDARDS. THE CONTRACTOR IS RESPONSIBLE FOR
PREPARING EXISTING SURFACES TO RECEIVE NEW
FINISHES SCHEDULED.
14. PROTECT EXISTING VEGETATION, INCLUDING EXISTING
TREES DURING CONSTRUCTION. REVEGETATE DAMAGED
AREAS ADJACENT TO NEW CONSTRUCTION; CONTRACTOR
SHALL MAINTAIN VEGETATED AREAS FOR 3 WEEKS AFTER
INITIAL PLANTING
15. REFER TO MECHANICAL, PLUMBING AND ELECTRICAL
DRAWINGS FOR OTHER WORK.
16. ELECTRICAL AND MECHANICAL INSTALLATIONS MAY
REQUIRE WORK ABOVE EXISTING CEILINGS BOTH IN THE
AREA OF WORK AND IN ADJACENT AREAS (POSSIBLY ON
OTHER FLOORS). REMOVE AND REINSTALL (OR REPLACE)
CEILING TILES AND GRID AS REQUIRED. REMOVE GYPSUM
BOARD AT WALLS AND CEILINGS AND REPLACE AS
REQUIRED.
17. UNLESS NOTED OTHERWISE, ALL EXISTING ELECTRICAL
OUTLETS & FIXTURES IN REMODELED AREAS ARE TO BE
REMOVED & RETURNED TO OWNER. SEE ELECTRICAL
SHEETS FOR DEVICES & CIRCUITS TO BE REUSED.
18. ALL ITEMS AND ASSOCIATED CONNECTIONS ARE TO BE
REMOVED AND TERMINATED AT DESIGNATED POINTS.
SERVICE CONNECTIONS SHALL BE SAFELY REMOVED,
CAPPED OR PLUGGED IN CONFORMITY WITH LOCAL LAWS
AND ORDINANCES, REQUIREMENTS OF PUBLIC UTILITY
COMPANIES, AND OF THE NATIONAL BOARD OF FIRE
UNDERWRITERS, AND IN SUCH MANNER AS NOT TO
INTERFERE WITH THE USE OF THE OCCUPIED SPACES IN
THE BUILDING.
19. IF A CONDUIT OR UTILITY LINE IS CUT WHILE SLEEVING OR
CUTTING THE SLAB OR REMOVING A PARTITION, THE
CONTRACTOR IS RESPONSIBLE FOR REPAIRING IT
IMMEDIATELY.
20. ANY EXISTING TO REMAIN FIREPROOFING OR FIRE
ASSEMBLIES DAMAGED DURING CONSTRUCTION ARE TO BE
REPAIRED TO ORIGINAL FIRE PROTECTION REQUIREMENTS.
21. IMMEDIATELY SEAL ALL PENETRATIONS IN EXISTING
STRUCTURE OPENED DURING DEMOLITION WITH
FIRESTOPPING MATERIAL AND/OR WATERPROOFING.
22. SEAL ALL PENETRATIONS, NEW AND EXISTING, ABOVE
CEILINGS AT RATED FIRE WALLS IN AREAS OF WORK.
COUNTER MOUNTED DROP-IN SINK
COUNTER MOUNTED UNDER
MOUNT SINK
COUNTER MOUNTED INTEGRAL
SINK
WALL MOUNTED SINK
FLOOR MOUNTED TOILET
WALL MOUNTED TOILET
FLOOR MOUNTED REAR DISCHARGE
TOILET
ACCESSIBLE LOCATION
USE ON PLANS EXAMPLE
WALL MOUNTED URINAL
ABV ABOVE D DRAIN FRT FIRE RESISTANT TREATED M METER PSF POUNDS PER SQUARE FOOT TB TACK BOARD
ACOUS ACOUSTICAL DBL DOUBLE FT FOOT MAS MASONRY PSI POUNDS PER SQUARE INCH TOC TOP OF CURB
ADJ ADJUSTABLE DEMO DEMOLISH, DEMOLITION FURR FURRING MAX MAXIMUM PT PRESSURE TREATED TOSC TOP OF STRUCTURAL CONCRETE
AFF ABOVE FINISH FLOOR DEPT DEPARTMENT FWC FABRIC WALL COVERING MDF MEDIUM DENSITY FIBER BOARD TEL TELEPHONE
ALUM ALUMINUM DF DRINKING FOUNTAIN MED MEDIUM QT QUARRY TILE THK THICK
ALT ALTERNATE DIA or Ø DIAMETER GA GAUGE MEMB MEMBRANE QTB QUARRY TILE BASE TOB TOP OF BEAM
ANOD ANODIZED DIM DIMENSION GALV GALVANIZED MTL METAL TOP TOP OF PAVEMENT
APPROX APPROXIMATELY DIV DIVISION GB GRAB BAR MFGR MANUFACTURER RI RISER TOM TOP OF MASONRY
AWP ACOUSTICAL WALL PANEL DL DEAD LOAD GC GENERAL CONTRACTOR MH MANHOLE R RADIUS TOS TOP OF STEEL (BOTTOM OF ROOF DECK)
DN DOWN GCLU GLAZED CMU MIN MINIMUM RB RUBBER BASE TP TOILET PARTITION
BD BOARD DS DOWN SPOUT GI GALVANIZED IRON MISC MISCELLANEOUS RCP REFLECTED CEILING PLAN TV TELEVISION
BLDG BUILDING DSP DRY STAND PIPE GL GLASS MM MILLIMETER RD ROOF DRAIN TYP TYPICAL
BOT BOTTOM DTL DETAIL GLB GLASS BLOCK MO MASONRY OPENING REF REFERENCE TZ TERRAZZO
BW BOTH WAYS DWG DRAWING GMT GLASS MOSAIC TILE MOD MODULAR REFR REFRIGERATOR TZB TERRAZZO BASE
BM BENCH MARK GMTW GLASS MOSAIC TILE WALL MTD MOUNT(ED) (ING) REINF REINFORCING
E EAST GR GRADE MUL MULLION REQ REQUIRE(D) (ING) UC UNDERCUT
C CHANNEL EA EACH GYP GYPSUM REV REVISION UNO UNLESS OTHERWISE NOTED
CC CUBICAL CURTAIN EF EPOXY FLOOR GYP BD GYPSUM BOARD N NORTH RH RIGHT HAND USC UNDER SEPARATE CONTRACT
CK CORK EFB EPOXY FLOOR BASE NAT NATURAL RM ROOM(S)
CAB CABINET EJ EXPANSION JOINT HC HOLLOW CORE NIC NOT IN CONTRACT ROW RIGHT OF WAY VAR VARNISH
CB CHALK BOARD EG END GUARD HDR HEADER NO or # NUMBER RVWC RIGID VINYL WALL COVERING VB VAPOR BARRIER
CFCI CONTRACTOR FURNISH CONTRACTOR INSTALL EL ELEVATION HDW HARDWARE NOM NOMINAL VB VINYL BASE
CFOI CONTRACTOR FURNISH OWNER INSTALL ET EPOXY TERRAZZO FLOOR HDWD HARDWOOD NRC NOISE REDUCTION COEFFICIENT S SOUTH VCT VINYL COMPOSITION TILE
CFT CUBIC FOOT ETB EPOXY TERRAZZO BASE HGT HEIGHT NTS NOT TO SCALE SB SPLASH BLOCK VERT VERTICAL
CG CORNER GUARD ELECT ELECTRICAL HM HOLLOW METAL SC SOLID CORE VEST VESTIBULE
CL, CENTER LINE EM ENTRANCE MAT HORIZ HORIZONTAL OC ON CENTER SCHED SCHEDULE VT VINYL TILE
CLG CEILING EMER EMERGENCY HP HIGH POINT OD OUTSIDE DIAMETER SECT SECTION VTR VENT THROUGH ROOF
CI CAST IRON ENCL ENCLOSURE HR HANDRAIL OFD OVERFLOW ROOF DRAIN SHR SHOWER VWC VINYL WALL COVERING
CLO CLOSET EP EPOXY PAINT HVAC HEATING VENTILATION AIR CONDITIONING OFF OFFICE SIM SIMILAR
CLR CLEAR EQ EQUAL OFOI OWNER FURNISH OWNER INSTALL SPECS SPECIFICATION(S) W WEST
CMP CROWN MOLDING PAINTED EQUIP EQUIPMENT ID INSIDE DIAMETER OFCI OWNER FURNISH CONTRACTOR INSTALL SPK SPEAKER W/ WITH
CMS CROWN MOLDING STAINED EWC ELECTRIC WATER COOLER INCL INCLUDING OVH OVERHEAD SQ SQUARE WBP WOOD BASE PAINTED
CMT CERAMIC MOSAIC TILE EXP EXPANSION INSUL INSULATION OH OPPOSITE HAND SS STAINLESS STEEL WBS WOOD BASE STAINED
CMTB CERAMIC MOSAIC TILE BASE EXIST EXISTING INT INTERIOR OPNG OPENING
ST STONE
WC WATER CLOSET
CMTW CERAMIC MOSAIC TILE WALL EXT EXTERIOR IPS IRON PIPE SIZE OPP OPPOSITE
STC STONE COUNTERTOP
WD WOOD
CMU CONCRETE MASONRY UNIT
STW STONE WALL
WDS WOOD STAINED
CO CASED OPENING FA FIRE ALARM J JOIST P PAINT(ED)
STB STONE BASE
WIN WINDOW
COL COLUMN FBO FURNISHED BY OTHERS JAN JANITOR PARA PARALLEL
STC STAINED CONCRETE
W/O WITHOUT
CONC CONCRETE FD FLOOR DRAIN JT JOINT PBD PARTICLE BOARD
STD STANDARD
WP WOOD PANELING PREFINISHED
CONST CONSTRUCTION
FE FIRE EXTINGUISHER PCF POUNDS PER CUBIC FOOT
STL STEEL
WPP WOOD PANELING PAINTED
CR
FEC FIRE EXTINGUISHER CABINET KIT KITCHEN PERF PERFORATED
STO STORAGE
WPS WOOD PANELING STAINED
CORR
CHAIR RAIL FFE FINISH FLOOR ELEVATION KO KNOCKOUT PERI PERIMETER
STRUCT STRUCTURAL
WS WATER STOP
CPT
CORRIDOR FHC FIRE HOSE CABINET PFL POUNDS PER LINEAR FOOT
SV SHEET VINYL
WSCT WAINSCOT
CPTB
CARPET FHVC FIRE HOSE VALVE CABINET L LENGTH/LONG PL PLATE
SVB SHEET VINYL COVED BASE
WT WEIGHT
CT
CARPET BASE FE FINISHED END LAB LABORATORY PLAM PLASTIC LAMINATE
SYM SYMMETRICAL
WWF WELDED WIRE FABRIC
CTB
CERAMIC TILE FLR FLOOR LAM LAMINATE PLAS PLASTER
SYS SYSTEM
CTW
CERAMIC TILE BASE FOC FACE OF CONCRETE LH LEFT HAND PLYWD PLYWOOD
CERAMIC TILE WALL FOF FACE OF FINISH LI LINOLEUM PP PORCELAIN PAVER
CTSK COUNTERSINK FOM FACE OF MASONRY LIB LINOLEUM COVED BASE PPB PORCELAIN PAVER BASE
CYD CUBIC YARD FOS FACE OF STUDS LIT LINOLEUM TILE PPW PORCELAIN PAVER WALL
FPRF FIREPROOFING LL LIVE LOAD PR PAIR
CONT CONTINUOUS
SSM SOLID SURFACE MATERIAL
NEW CONSTRUCTION
EXISTING CONSTRUCTION
DEMOLITION
HIDDEN LINE
FIRE/SMOKE BARRIERS
1 HOUR FIRE BARRIER
SMOKE/FIRE BARRIER
2 HOUR FIRE BARRIER
FIRE/SMOKE PARTITIONS
1 HOUR FIRE PARTITION
SMOKE PARTITION
FIRE WALLS
2 HOURS
3 HOURS
1FB
1SB
2FB
1FP
0SP
2FW
3FW
BRICK
CONCRETE
CONCRETE BLOCK
EARTH
INSULATION, BATT
INSULATION, RIGID
METAL
PLYWOOD
FINISH GRADE
HARDWOOD
WOOD FRAMING
THROUGH MEMBER
WOOD FRAMING
INTERRUPTED MEMBER
PARTITION TYPES
DOOR NUMBER
KEY NOTE (NEW)
KEY NOTE (DEMO)
EQUIPMENT / ACCESSORY
WINDOW TAG
COLUMN GRID
ELEVATION HEIGHT
REVISION
INTERIOR
ELEVATION
SECTION
NORTH
ROOM NAME
N
A###
NAME
ROOM NUMBER
REFER TO ROOM NUMBER
FOR TYPICAL INFORMATION
1t
SIM
MATCHLINE
EXTERIOR
ELEVATION
EXTERIOR WALL TYPES-
##'- ##" CEILING HEIGHT
A.F.F.
0' - 0"
RAILING TAGHR#-IP
Revisions:
A u s ti n
S a n A n to n io
H o u st o n
B a rt o n
S p ri n g s
R o a d
Su it e
A u st in Te xa s
B ro a d w a y Su it e
S a n A n to n io
Te xa s
F a n n in
S tr e e t, S u it e
H o u st o n
Te xa s p
.4
.7 f
.4
.7 p
.2
.6 f
.2
.6 p
.4
.1 f
.4
.1
25-2MC02328
A u to d e s k D o c s
/H a rr is
H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/
H
H S
L B
J G a m m a
C a m e ra R p lc m n t_ A
R C
H
C e n tr a l.
rv t
/2
/2
:2
:2
P M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K
E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
12/23/2025
Project No. 2321.08
CONTRACT DOCUMENTS
DRAWING INDEX AND
SYMBOLS
G1.1
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
DRAWING INDEX
GENERAL
G1.0 COVER SHEET
G1.1 DRAWING INDEX AND SYMBOLS
G2.1 ADULT TAS ACCESSIBILITY
LIFE SAFETY
LS1.1 CODE INFORMATION
LS1.3 LIFE SAFETY INFORMATION
STRUCTURAL
S1.1 GENERAL STRUCTURAL NOTES AND PARTIAL FRAMING PLAN
ARCHITECTURAL
A2.1 DEMOLITION PLAN
A3.0 COMPOSITE FLOOR PLAN
A3.1 FLOOR PLAN
A7.2 PARTITION TYPES
A7.6 DOOR SCHEDULE & INTERIOR ELEVATIONS
FIRE PROTECTION
P1.1 FIRE PROTECTION AND PLUMBING
MECHANICAL
M1.1 MECHANICAL NOTES, SYMBOLS AND ABBREVIATIONS
M2.1 MECHANICAL DEMOLITION PLAN
M3.1 MECHANICAL DUCTWORK PLAN
M4.1 MECHANICAL DETAILS
ELECTRICAL
E1.1 ELECTRICAL NOTES, SYMBOLS AND ABBREVIATIONS
E2.0 ELECTRICAL OVERALL THIRD FLOOR PLAN
E2.1 ELECTRICAL DEMOLITION PLAN
E3.1 ELECTRICAL POWER PLAN
E4.1 LIGHTING PLAN
E5.1 SPECIAL SYSTEM PLAN
E7.1 ELECTRICAL ONE-LINE DIAGRAM, SCHEDULES, AND DETAILS
GENERAL PROJECT
NOTES
TEXAS MAP
VICINITY MAP
LOCATION MAP
PLUMBING FIXTURES
ARCHITECTURAL ABBREVIATIONS
ARCHITECTURAL
LINETYPES
ARCHITECTURAL
MATERIALS
ARCHITECTURAL
SYMBOLS
HARRIS COUNTY
PROJECT LOCATION
NO. DESCRIPTION DATE
Revisions:
NO. DESCRIPTION DATE
THERMOSTAT
SWITCH6
M
IN
1'-3"
O P
E R
A B
L E
P A
R T
M
A X
T
O H
IG
H
E S
T
4"- 6"
OVERHEAD
CLEARANCE
REF. SECTION 307
TYP SWITCH/
THERMOSTAT/STROBE
/LOCATION
REF. SECTION 309
ELEVATION
LOBBY
DOOR NOTES:
1. DOOR THRESHOLDS: THRESHOLDS AT DOORWAYS SHALL NOT EXCEED 3/4" IN HEIGHT FOR EXTERIOR SLIDING DOORS OR 1/2" FOR OTHER TYPES OF DOORS.
THRESHOLDS AND FLOOR LEVEL CHANGES BETWEEN 1/4" AND 1/2" AT ACCESSIBLE DOORWAYS SHALL BE BEVELED WITH A SLOPE NO GREATER THAN 1:2.
PUSH SIDE
PULL SIDE
PUSH SIDE
PULL SIDE
W/ LATCH
& CLOSER
"M
IN
I F
P A
R A
L L E
L
T O
D O
O R
I S
M
IN
W
C L O
S E
R
L A
T C
H
PUSH SIDE
PULL SIDE
3'-0" MIN.
PARALLEL TO DOOR
2'-8" CLEAR MIN.
2'-8" MIN.
1'-6" MIN.
M
IN
M
IN
1'-0" MIN.
4" U.N.O.
M
IN
W
C
L O
S E
R
M
IN
W
C
L O
S E
R
3'-6" MIN.
PARALLEL TO DOOR
M
IN
IF
P
A R
A L
L E
L T
O D
O O
R I S
M
IN
M
IN
M
A X
2'-0" MIN.
2'-0" MIN.
DOORS
REF. SECTION 404 DOORS
SWINGING DOOR CLEARANCES
(LATCH SIDE APPROACH)
SWINGING DOOR CLEARANCES
(HINGE SIDE APPROACH)
SWINGING DOOR CLEARANCES
(FRONT APPROACH)
CLEAR DOORWAY WIDTHCLEAR DOORWAY DEPTH
PLANPLAN
PLAN
4'-0" MIN.
M
IN
M
IN
5'-0" MIN.
1'-0" MIN.
3'-0" MIN.
1'-0" MIN.
M
IN
M
IN
. 5
M
IN
TURNING SPACE
REF. SECTION 304 TURNING SPACE
CLEAR FLOOR SPACE & DIAMETER
TURNING SPACE
T-TURN CLEAR FLOOR SPACE
ELEVATION
M
IN
" M A
X
AREA
OF
MIN CLEAR
1'-6"
M
IN
C L
E A
R
REFUGE
TACTILE SIGN
REF. SECTION 703.4
PLAN
ELEVATION
M
IN
" M A
X
AREA
OF
REFUGE
TACTILE SIGN
PAIRS OF
DOORS
REF. SECTION 703.4
WALL MOUNTED FIRE ALARM
DEVICE. MOUNT DEVICE SO
THAT THE ENTIRE LENS IS NOT
LESS THAN 80" OR MORE THAN
96" ABOVE FINISH FLOOR
BASELINE OF THE HIGHEST
TACTILE CHARACTER
BASELINE OF THE
LOWEST
TACTILE CHARACTER
LOCATE SIGN ON
LATCH SIDE OF DOOR
ELEVATION
M
IN
"M A
X
AREA
OF
REFUGE
BASELINE OF THE HIGHEST
TACTILE CHARACTER
BASELINE OF THE
LOWEST
TACTILE CHARACTER
LOCATE SIGN TO
RIGHT OF RIGHT
HAND DOOR
BASELINE OF THE HIGHEST
TACTILE CHARACTER
BASELINE OF THE
LOWEST
TACTILE CHARACTER
LOCATE SIGN ON
INACTIVE LEAF
ACTIVE LEAFSINACTIVE LEAF
ACTIVE LEAF
1'-10" MIN.
3'-0" MIN.
X
M
A X
M
IN
(a) (b)
M
A X
20" MAX >20"-25" MAX
M
A X
Figure 308.3.1 Unobstructed Side Reach
10" MAX
M
IN
M
A X
Figure 308.3.2 Obstructed High
Side Reach
(a) (b)
M
A X
10" MAX
M
A X
M
A X
M
A X
>10"-24" MAX
Figure 308.2.1 Unobstructed Front Reach
Figure 308.2.2 Obstructed
Front Reach
REACH RANGES
REF. SECTION 308
1.
DRAWINGS ON THIS SHEET REPRESENT THE REQUIREMENTS
SET BY THE TEXAS ACCESSIBILITY STANDARDS (TAS) OF THE
ARCHITECTURAL BARRIERS ACT ARTICLE 9102, TEXAS CIVIL
STATUTES EFFECTIVE MARCH 15, 2012. THE CONTRACTOR IS
TO COMPLY WITH THESE STANDARDS.
2.
THESE REQUIREMENTS ARE MINIMUMS SET FORTH BY THE
TEXAS ACCESSIBILITY STANDARDS AND MAY NOT REFLECT
THE ACTUAL SCOPE OF WORK. THE CONSTRUCTION
DOCUMENTS SHALL GOVERN OVER THESE STANDARDS
EXCEPT WHERE THE DOCUMENTS DO NOT MEET THE MINIMUM
REQUIREMENTS SHOWN ON THIS SHEET. CONTRACTOR TO
NOTIFY THE ARCHITECT IMMEDIATELY IF ANY CONDITIONS
ARISE THAT DO NOT MEET THESE STANDARDS.
GENERAL NOTES
FINISH FLOOR
C O
U N
T E
R S
H
A F
F
C O
U N
T E
R S
H
A F
F
C
O U
N T
E R
S
H A
F F
LIGHT SWITCH THERMOSTAT ADA DOOR OPERATOR
CARD READER
POWER OUTLET
POWER OUTLET
ABOVE COUNTER
DATA OUTLET
DATA OUTLET
ABOVE COUNTER
EXIT
EXIT SIGN
EXIT
EXIT SIGN
ABOVE DOOR
EMERGENCY
FIRE STORAGE
TYPICAL DEVICE HEIGHTS
Revisions:
A u s ti n
S a n A n to n io
H o u st o n
B a rt o n
S p ri n g s
R o a d
S u it e
A u st in
Te x a s
B ro a d w a y
S u it e
S a n A n to n io
Te x a s
F a n n in S tr e e t, S u it e
H o u st o n
Te x a s p
.4
.7 f
.4
.7 p
.2
.6
.2
.6 p
.4
.1
.4
.1
25-2MC02328
A u to d e s k D o c s
/H a rr is
H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/
H
H S
L B
J G a m m a
C a m e ra R p lc m n t_ A
R C
H
C e n tr a l.
rv t
/2
/2
:1
:1
P M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K
E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
12/23/2025
Project No. 2321.08
CONTRACT DOCUMENTS
ADULT TAS ACCESSIBILITY
G2.1
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
Revisions:
A u s ti n
S a n A n to n io
H o u st o n
B a rt o n
S p ri n g s
R o a d
Su it e
A u st in Te xa s
B ro a d w a y Su it e
S a n A n to n io
Te xa s
F a n n in
S tr e e t, S u it e
H o u st o n
Te xa s p
.4
.7 f
.4
.7 p
.2
.6 f
.2
.6 p
.4
.1 f
.4
.1
25-2MC02328
A u to d e s k D o c s
/H a rr is
H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/
H
H S
L B
J G a m m a
C a m e ra R p lc m n t_ A
R C
H
C e n tr a l.
rv t
/2
/2
:2
:3
P M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K
E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
12/23/2025
Project No. 2321.08
CONTRACT DOCUMENTS
CODE INFORMATION
LS1.1
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
Occupancy Types: Institutional Group I-2, Condition 2 308.3
CHAPTER 3: USE & OCCUPANCY CLASSIFICATION
IBC
Group I-2 Occupancies in group I-2 shall comply with the provisions of sections 407.1 through 407.10 and other applicable provisions of this code. 407
CHAPTER 4: SPECIAL DETAILED REQUIREMENTS BASED ON USE & OCCUPANCY
Roof Construction and associated secondary structural members 1 1/2 hour T601
Floor Construction and associated secondary structural members 2 hour T601
Nonbearing Walls and Partitions (interior) 0 hour T601
Primary Structural Frame 3 Hour T601
Fire Resistance Rating Requirements Construction Type IA 602
CHAPTER 6: TYPES OF CONSTRUCTION
Combustible decorative materials The permissible amount of decorative materials meeting the flame propagation performance criteria of NFPA 701 shall not exceed 10 percent of the specific wall or ceiling area to which it is attached. 806.1.2
In Groups I-1 and I-2, combustible decorative materials shall meet the flame propagation criteria of NFPA 701 unless the decorative materials, including, but not limited to, photographs and paintings, are of such limited that hazard of fire development or spread is not present. 806.1
Decorative Materials and Trim
Insulating Boards Combustible insulation boards not more than 1/2" think and covered with finish flooring are permitted where attached directly to a noncombustible floor assembly or to wood subflooring attached to sleepers as provided for section 805.1.1.
Wood finish flooring Wood finish flooring is permitted to be attached directly to the embedded of fireblocked wood sleepers and shall be permitted where cemented directly to the top surface of fire-resistnace-rated floor assemblies or directly to wood subfloor attached to sleepers as provided for in this Section 805.1.1 805.1.2
Subfloor Floor sleepers, bucks and nailing blocks shall not be constructed of combustible material, unless the space between the fire-resistance rate floor assembly and flooring is either solidly filled with noncombustible materials or fireblocked in accordance with section 718 and provided that such open spaces shall not extend under or through permanent partitions or walls.
Combustible Materials in Type I or II Construction Combustible materials installed on or embedded in floors of buildings shall comply with the following: 805.1
Minimum critical radiant flux The minimum critical radiant flux shall be Class I in Groups I-1, I2 and I-3. 804.4.2
Interior Floor Finish Test Requirement In ALL occupancies, interior floor covering materials shall comply with the requirements of the DOC FF-1 "pill test" (CPSC 16 CFR 1630) or ASTM D2859 804.4.1
Interior Floor Finish Interior floor finish and floor covering materials shall complywith Sections 804.2 and 804.4.2 804.1
Rooms and enclosed spaces= B T803.13
Corridors and enclosure for exit access stairways and ramps= B T803.13
Based on I-2 Occupancy Interior exit stairways and ramps and exit passageway= B T803.13
Interior Wall and Ceiling Finish Requirements Based on Business Occupancy Sprinklered T803.13
Interior wall and ceiling finish material tested in accordance with ASTM E84 or UL723 Interior wall anc ceiling finish materials shall be classified in accordance with ASTM E84 or UL 723. 803.1.2
Interior wall and ceiling finish material tested in accordance with NFPA 286 Interior wall and ceiling finish materail shall be classified in accordance with NFPA 286 and comply Section 803.1.1.1. Materials complying with 803.1.1.1 shall considered to also comply with the requirements of Class A. 803.1.1
Wall and Ceiling Finishes Interior wall and ceiling finish material shall be classified for fire performance and smoke developed in accordance with Section 803.1.1 or 803.1.2. Materials tested in accordance with 803.1.1 shall not be required to be tested in accordance with 803.1.2 803.1
CHAPTER 8: INTERIOR FINISHES
Maximum Travel Distance to Extinguisher 75 Feet
Maximum Floor Area for Extinguisher 11,250 SF
Maximum Area per unit of A 1,500 SF
Minimum Rated Single Extinguisher 2-A
Size and Distribution Hazard Occupancy Moderate T906.3(1)
In Group I occupancies 906.1.1
Portable Fire Extinguishers Portable fire extinguishers shall be installed in all of the following locations 906.1
Automatic Sprinkler Systems Approved automatic sprinkler systems in new buildings and structures shall be provided in the locations described in Sections 903.2.1 through 903.2.12 903.2
CHAPTER 9: FIRE PROTECTION SYSTEMS
Min. Number of Exits per Story Existing to remain. The renovation scope does not impact the occupancy type and occupant load of the space. T1006.3.3
Dead End Corridors 20 ft - Existing 1020.5
Min. Number of Exits per Space 2 exits when over 10 occupants at I-2 occupancy 1006.2.1
Corridor Fire Resistance Rating with Sprinkler System: Not Required at I-2 occupancies T1020.2
Max. Exit Access Travel Distance with Sprinkler System: 200 feet at I-2 T1017.2
Max. Common Path of Egress Travel Distance with Sprinkler System: 75 feet at I-2 T1006.2.1
Accessible Means of Egress Existing 1007.1
Egress Width .2 per occ at I-2 occupancy 1005.3
Outpatient area 100 gross
Max. Floor Area Allowances per Occupant T1004.5
CHAPTER 10: MEANS OF EGRESS
TEXAS ARCHITECTURAL BARRIERS PROJECT #
Building Height 4 Stories
Renovation Gross Area Floor 3 493 SF
Building Construction Type IA
PROJECT SUMMARY
NFPA Code National Fire Protection Association 101
Accessibility Codes 2012 Texas Accessibilities Standards
Energy Conservation Code 2021 International Energy Conservation Code, with Houston Amendments
Fire Code 2021 International Fire Code, with Houston Amendments
Mechanical Code 2021 Uniform Mechanical Code, with Houston Amendments
Plumbing Code 2021 Uniform Plumbing Code, with Houston Amendments
Electrical Code 2023 National Electrical Code with Administrative Code Provisions
Existing Building Code 2021 International Existing Building Code
Building Code 2021 International Building Code
APPLICABLE CODES AND STANDARDS
JURISDICTION: City of Houston
LOCATION: 5656 Kelley St, Houston, Texas 77026
PROJECT: LBJ Gamma Camera
OR PROJECT NUMBER: 2321.08
OWNER: Harris Health Systems
BUILDING CODE ANALYSIS
seismic bracket
OCCUPANT LOAD SERVED
EXIT MARK. REFER TO
SCHEDULE
X X
X X
TRAVEL DISTANCE
97' - 6"
LIFE SAFETY LEGEND
STAIR EXITDOOR EXIT
CIRCLE INDICATES
INCLUDED IN TOTAL
FIRE/SMOKE BARRIERS
1 HOUR FIRE BARRIER
2 HOUR FIRE BARRIER
1FB
2FB
LIFE SAFETY LINETYPES
3148.04 SF
COMMON PATH OF
TRAVEL TO EXIT
17' - 6"
1. LIFE SAFETY PLANS ARE MEANT TO BE
VIEWED AND PRINTED IN COLOR.
2. REFERENCE A3 SERIES FOR FIRE
EXTINGUISHER LOCATIONS.
N
TRUE NORTH
N
PLAN NORTH
379 SF
CORRIDOR
84 SF
RAD HOT
LAB
314 147 SF
STRESS
TEST LAB
300 SF
IMAGING
ROOM 1
324A
366 SF
IMAGING
ROOM 3
105 SF
WK.AREA
PH3100
16 SF
DECAY CL.
138 SF
CORRIDOR
303 SF
IMAGING
ROOM 2
324B
39 SF
HC TLT.
AA3110
35 SF
HC TLT.
AA3109
54 SF
CLEAN
STORAGE
87 SF
CONSULTATION
ROOM
PH3101
ELEC
SP3124
MECHANICAL
SHAFT
SP3125
MECHANICAL
SHAFT
300-M
155' - 0" : 200' - 0"
NUCLEAR MEDICINE SUITE: 3184.04 SF
91 SF
SUB-WAITING
AREA
30 SF
PATIENT
TLT.
3310A
26 SF
UPTAKE
AREA
86 SF
PREP
AREA
141 SF
CORRIDOR
38 SF
RECEPTION
303A
129 SF
WAITING
87 SF
OFFICE
64 SF
UNISEX
STAFF
RESTROOM
78 SF
UNISEX PT.
RESTROOM
DRESS
56 SF
CONTROL
ROOM
59 SF
SUB-WAITING
AREA
40' - 6" : 75' - 0"
Revisions:
A u s ti n
S a n A n to n io
H o u st o n
B a rt o n
S p ri n g s
R o a d
S u it e
A u st in
Te x a s
B ro a d w a y
S u it e
S a n A n to n io
Te x a s
F a n n in S tr e e t, S u it e
H o u st o n
Te x a s p
.4
.7
.4
.7 p
.2
.6
.2
.6 p
.4
.1
.4
.1
25-2MC02328
A u to d e s k D o c s
/H a rr is
H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/
H
H S
L B
J G a m m a
C a m e ra R p lc m n t_ A
R C
H
C e n tr a l.
rv t
/2
/2
:1
:2
P M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K
E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
12/23/2025
Project No. 2321.08
CONTRACT DOCUMENTS
LIFE SAFETY
INFORMATION
LS1.3
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
GENERAL LIFE
SAFETY NOTES
A
KEY PLAN
SCALE: 3/16" = 1'-0"
THIRD FLOOR LIFE SAFETY PLAN
DECAY
CL.
E F
23'-0" (FV)
(F
V
PLAN NOTES:
1. REFER TO ARCHITECTURAL DRAWINGS FOR FULL EXTENT OF WHAT IS IN SCOPE AND WHAT IS NOT. STRUCTURAL SCOPE IS LIMITED.
2. REFER TO GENERAL NOTES, PART III FOR REQUIREMENTS WITH RESPECT TO EXISTING STRUCTURE.
3. EXISTING STRUCTURAL SYSTEM CONSISTS OF A 4 3/4" THICK SLAB, 20 3/4" DEEP PAN FORMED BEAMS (PFB) AT APPROXIMATELY 6'-0" ON CENTER
SUPPORTED BY 20 3/4" DEEP GIRDERS (G).
4. CORES THROUGH EXISTING STRUCTURE SHOULD BE LOCATED IN PAN FORMED SLAB SUCH THAT EXISTING PAN FORM BEAMS ARE NOT
IMPACTED.
E X
IS
T
P F
B
EXIST GIRDER
E X
IS
T
P F
B
E X
IS
T
P F
B
E X
IS
T
B E
A M
EXIST GIRDER
EXIST PAN
FORMED SLAB
EQUIPMENT ANCHORING NOTES:
1. LOCATION OF ALL POST-INSTALLED ANCHORS AND THROUGH BOLTS SHALL BE PER VENDOR DRAWINGS. VENDOR INDICATES ALTERNATIVE
LOCATIONS AS WELL.
2. LENGTH OF THROUGH BOLTS WILL DEPEND ON THE THICKNESS OF THE EQUIPMENT BASE. CONTRACTOR TO COORDINATE BOLT LENGTHS WITH
EQUIPMENT VENDOR REQUIREMENTS.
3. ANCHOR/BOLT TORQUE REQUIREMENTS TO BE COORDINATED WITH VENDOR.
4. CONTRACTOR TO SUBMIT FINAL LAYOUT OF ALL ANCHORS/BOLTS WITH QUANTITIES, SIZES AND LENGTHS TO ARCHITECT, STRUCTURAL
ENGINEER AND VENDOR FOR REVIEW.
5. PER VENDOR DRAWINGS, TABLE ANCHOR (TA) PLATE CAN BE ANCHORED WITH SCREWS THAT ARE SHALLOW ENOUGH TO BE POST-INSTALLED
INTO EXISTING CONCRETE.
6. PER VENDOR DRAWINGS, NM GANTRY (NMG) ANCHOR POINTS WILL REQUIRE M10 THROUGH BOLTS.
7. PER VENDOR DRAWINGS, NM GANTRY NMG* AND NMG# ANCHOR POINTS ARE DIRECTLY OVER EXISTING CONCRETE PAN FORMED BEAM (PFB).
CONTRACTOR TO LOCATE EXISTING REINFORCEMENT USING NON-DESTRUCTIVE EVALUATION (NDE) METHODS AND PROVIDE AS-BUILT LOCATIONS TO ARCHITECT, STRUCTURAL ENGINEER AND VENDOR. IT IS ACCEPTABLE TO POST-INSTALL ANCHORS PER VENDOR THAT IMPACTS THE EXISTING SLAB REINFORCEMENT OR AN EXISTING PFB STIRRUP. IT IS ASSUMED THAT ONLY ONE SUCH REINFORCING BAR WOULD BE IMPACTED IN EACH CASE. POST-INSTALLED ANCHORS PER VENDOR MAY BE INSTALLED INTO EXISTING PAN-FORMED BEAMS (PFB) PROVIDED THAT THE INSTALLATION DOES NOT DAMAGE THE EXISTING PFB TOP LONGITUDINAL REINFORCEMENT FOR NMG#. IT MAY BE ACCEPTABLE THAT THE INSTALLATION MAY IMPACT THE EXSITING PFB TOP LONGITUDINAL REINFORCEMENT FOR NMG*. IT IS ALSO POSSIBLE TO CONSIDER ONE OF THE ALTERNATIVE ANCHOR LOCATIONS SUCH AS ALT# PER THE VENDOR REQUIREMENTS, CONTRACTOR TO COORDINATE.
8. PER VENDOR DRAWINGS, TRANSPORTER CT GANTRY (TCTG) ANCHOR POINTS WILL REQUIRE M10 THROUGH BOLTS.
9. PER VENDOR DRAWINGS, CT SERVICE PLATE (CTSP) ANCHOR POINTS WILL REQUIRE M10 THROUGH BOLTS.
10. PER VENDOR DRAWINGS, SERVICE LEAD (SL) ANCHOR POINTS WILL REQUIRE M10 THROUGH BOLTS.
E X
IS
T
P F
B
C L E
A R
S P
A N
.3 x
C L E
A R
S P
A N
.3 x
C L E
A R
S P
A N
TA
TA
TA
TA
TA
TA
ANCHORS FOR COLLIMATOR
POSITIONING PLATE PROVIDED BY
VENDOR, REFER TO NOTES
NMG
ALT
ALT
NMG
NMG*
ALT#
TCTG
ALT
TCTG
CTSP
ALT
NMG#
TCTG
CTSP
ALT
SL
SL
TCTG
ALT
TCTG
CTSP
CTSP
ALT
ALT
CL THROUGH
BOLT
CL THROUGH
BOLT
WHERE EXISTING CLEARANCES DO NOT ALLOW
FOR THE INSTALLATION OF THE BOLT, NUT OR
WASHER, CONTRACTOR TO NOTIFY ARCHITECT,
SEOR AND VENDOR (REFER TO EQUIP
ANCHORING NOTES). THIS MAY REQUIRE USE
OF AN ALTERNATIVE ANCHOR LOCATION.
THROUGH BOLT DIAMETER PER
VENDOR DRAWINGS WITH
CORRESPONDING NUTS AND
WASHERS (TOP AND BOT)
B A
S E
T H
K E
Q U
IP
POST-INSTALLED ANCHOR
PER VENDOR DRAWINGS
(REF NOTES)
EXISTING #3@12"
SLAB REINF
EXISTING PFB TOP
LONGITUDINAL REINF
(DO NOT DAMAGE)
EXISTING PFB STIRRUPS
NOTES:
1. CONTRACTOR TO COORDINATE THROUGH ANCHOR/BOLT LOCATIONS
WITH EQUIPMENT VENDOR DRAWINGS.
N
N
A
KEY PLAN
Revisions:
A u st in
S a n A n to n io
H o u s to n
B a rt o n
S p ri n g s
R o a d
S u it e
A u st in Te xa s
B ro a d w a y S u it e
S a n A n to n io
Te xa s
F a n n in
S tr e e t, S u it e
H o u st o n Te xa s p
.4
.7 f
.4
.7 p
.2
.6 f
.2
.6 p
.4
.1 f
.4
.1
TRUE NORTH PLAN NORTH
02/27/2026
A u to d e s k D o c s /H a rr is H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/ Y
H
H S
L B
J G a m m a
C a m e ra
S T
R .r v t
/2
/2
:1
:2
P
M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
S Y
S
TE
M
12/22/2025
Project No. 2321.08
CONTRACT DOCUMENTS
GENERAL STRUCTURAL
NOTES AND PARTIAL
FRAMING PLAN
S1.1 1/2" = 1'-0"12
THIRD LEVEL PARTIAL FRAMING PLAN
A. GENERAL BUILDING CODE
1. International Building Code 2021.
GENERAL STRUCTURAL NOTES
PART I - DESIGN CRITERIA
A. SUBMITTAL LIST AND SCHEDULE
1. The General Contractor shall prepare a detailed list and schedule of all submittal items to be sent to the Structural Engineer prior to the start of construction. This list shall be updated and revised and kept current as the job progresses. The submittal list shall be organized as shown below:
a. Shop Drawings
b. Design Calculations
c. Product Data, Certificates, Reports, and Other Literature
B. SUBMITTALS TO BE PROVIDED TO STRUCTURAL ENGINEER
1. Deferred Submittals:
a. Equipment Vendor drawings (REC)
Notes:
(S&S)Items marked thus shall have the shop drawings and delegated design submittals (including calculations) sealed per the project specifications by an engineer registered in the state where the project is located.
(REC)Items marked thus shall be submitted to Engineer for Record
Only and will not have the Engineer’s shop drawing stamp affixed.
2. Submittal Requirements:
a. All shop drawings must be reviewed and electronically stamped by the General Contractor prior to submittal.
b. Contractor shall submit three sets of prints for all shop drawings specified to be returned by the Engineer.
c. Contractor shall provide the submittal in electronic portable document format (PDF) per the Specifications.
d. The omission from the shop drawings of any materials required by the Contract Documents to be furnished shall not relieve the
Contractor of the responsibility of furnishing and installing such materials, regardless of whether the shop drawings have been reviewed and approved.
C. REPRODUCTION
1. The use of electronic files or reproductions of these contract documents by any contractor, subcontractor, erector, fabricator, or material supplier in lieu of preparation of shop drawings signifies their acceptance of all information shown hereon as correct, and obligates themselves to any job expense, real or implied, arising due to any errors that may occur hereon.
PART II - SUBMITTALS
A. CONTRACT DOCUMENTS
1. It is the responsibility of the General Contractor to obtain all
Contract Documents and latest addenda and to submit such documents to all subcontractors and material suppliers prior to the submittal of shop drawings, fabrication of any structural members, and erection in the field.
2. The contract structural drawings and specifications represent the finished structure, and, except where specifically shown, do not indicate the method or means of construction. The Contractor shall supervise and direct the work and shall be solely responsible for all construction means, methods, procedures, techniques, and sequence.
3. Openings through floors, roofs, and walls for ducts, piping, and/or conduit shall be coordinated by the contractor. Contractor shall verify sizes and locations of holes and openings with the
Mechanical, Electrical, Plumbing, and Fire Protection drawings and the respective subcontractors.
4. Refer to drawings other than Structural for complete information including: Types of floor slab finishes and their locations, floor slab depressions and curbs, openings in structural walls, roofs and floors required by Architectural and MEP features, stairs, ramps, etc.
5. Where member locations are not specifically dimensioned, members are either located on columns lines or are equally spaced between located members.
6. If certain features are not fully shown or specified on the drawings or in the specifications, their construction shall be of the same character as shown or specified in similar conditions.
B. DRAWING CONFLICTS
1. The General Contractor shall compare the Architectural and
Structural drawings and report any discrepancy between each set of drawings and within each set of drawings to the Architect and
Engineer prior to the fabrication and installation of any structural members.
C. CONFLICTS IN STRUCTURAL REQUIREMENTS
1. Where conflict exists among the various parts of the structural contract documents, structural drawings, general notes, and specifications, the strictest requirements, as indicated by the
Engineer, shall govern.
D. EXISTING CONDITIONS
1. The General Contractor shall verify all dimensions and conditions of the existing building at the job site and report any discrepancies from assumed conditions shown on the drawings to the Architect and
Engineer prior to the fabrication and erection of any members.
2. Work shown on the drawings is New, unless noted as Existing.
3. Existing construction shown on the drawings was obtained from existing construction documents and limited site observation.
These drawings of existing construction are available for contractor use. However, the available drawings of existing construction are not necessarily complete. The contractor shall field verify all pertinent information.
4. Demolition, cutting, drilling, etc. of existing work shall be performed with great care so as not to jeopardize the structural integrity of the existing building. If any architectural, structural, or MEP members not designated for removal interfere with the new work, the Architect shall be notified immediately and approval obtained prior to removal of those members.
5. The contractor shall safely shore existing construction wherever existing supports are removed to allow the installation of new work.
All shoring methods and sequencing of demolition shall be the responsibility of the contractor and their engineer.
6. The contractor shall verify the location of existing utilities prior to the start of construction and take care to protect existing utilities that are to remain in service.
7. The contractor shall repair all damage caused during construction with similar materials and workmanship to restore conditions to levels acceptable to the Architect.
PART III - MISCELLANEOUS
A. THE STRUCTURAL ENGINEER'S ROLE DURING CONSTRUCTION
1. The Engineer shall not have control nor charge of, and shall not be responsible for, construction means, methods, techniques, sequences, or procedures, for safety precautions and programs in connection with the work, for the acts or omission of the Contractor, Subcontractor, or any other persons performing any of the work, or for the failure of any of them to carry out the work in accordance with the contract documents.
2. Periodic site observation by field representatives of Martinez
Moore Engineers, LLC is solely for the purpose of becoming generally familiar with the progress and quality of the Work completed and determining, in general, if the Work observed is being performed in a manner indicating that the Work, when fully completed, will be in accordance with the structural contract documents. This limited site observation should not be construed as exhaustive or continuous to check the quality or quantity of the work, but rather periodic in an effort to keep the Owner reasonably informed about the progress and quality of the portion of the structure completed.
PART IV - STRUCTURAL ENGINEER'S ROLE
3/4" = 1'-0"4
TYPICAL EQUIPMENT BASE THROUGH BOLTS
1 ADDENDUM 01 02/27/26
1. THE CONTRACTOR SHALL FURNISH ALL LABOR,
MATERIALS, TOOLS, EQUIPMENT AND RELATED ITEMS
REQUIRED TO COMPLETE THE DEMOLITION WORK AS
INDICATED BY THE CONTRACT DOCUMENTS
2. THE CONTRACTOR SHALL SUPERVISE AND DIRECT THE
WORK, USING THEIR BEST SKILL AND ATTENTION. THEY
SHALL BE SOLELY RESPONSIBLE FOR ALL DEMOLITION
MEANS, METHODS, TECHNIQUES, SEQUENCES AND
PROCEDURES. AND FOR COORDINATING ALL PORTIONS
OF THE WORK UNDER THE CONTRACT.
3. THE CONTRACTOR SHALL PAY FOR ALL PERMITS, FEES
AND INSPECTIONS REQUIRED FOR THE EXECUTION OF
THE WORK
4. SERVICE CONNECTIONS SHALL BE SAFELY REMOVED,
CAPPED OR PLUGGED IN CONFORMITY WITH LOCAL
LAWS AND ORDINANCES, REQUIREMENTS OF LOCAL
UTILITY COMPANIES, AND THE NATIONAL BOARD OF
FIRE UNDERWRITERS, AND IN SUCH MANNER AS TO
NOT TO INTERFERE WITH USE OF THE OCCUPIED
SPACES IN THE BUILDING
5. REMOVE ALL MISCELLANEOUS DEVICES AS REQUIRED
TO INSTALL NEW FINISHES, INCLUDED BUT NOT LIMITED
TO PLUMBING FIXTURES, SIGNAGE, SWITCH PLATES,
TELEVISION BRACKETS, WALL OUTLET COVERS, ETC.
SAVE FOR REINSTALLATION AFTER COMPLETION OF
FINISH WORK
6. CONTRACTOR TO COORDINATE WITH OWNER'S
REPRESENTATIVE FOR INFECTIOUS CONTROL
MEASURES DURING CONSTRUCTION
7. DASHED LINES INDICATE WALLS, DOORS, FIXTURES,
CASEWORK, ETC. TO BE REMOVED IN THEIR ENTIRETY,
U.N.O.
8. ANY QUESTIONS CONCERNING OWNERSHIP OF
SALVAGEABLE MATERIAL SHALL BE ANSWERED BY THE
OWNER, OR THE OWNER'S REPRESENTATIVE
9. INSTALL TEMPORARY DUST PARTITIONS WITH DOORS
FOR CONSTRUCTION ACCESS AROUND AREAS OF
WORK SO THAT OPERATIONS IN EXISTING ADJACENT
AREAS REMAIN DUST FREE. MAINTAIN IN PLACE UNTIL
COMPLETION OF CONSTRUCTION
10. IMMEDIATELY SEAL ALL PENETRATIONS IN EXISTING
SLAB OPEN DURING DEMOLITION WITH FIRESTOPPING
MATERIAL AND WATERPROOFING
11. SEAL ALL PENETRATIONS, NEW AND EXISTING, ABOVE
CEILING AT FIRE RATED AND SMOKE PARTITIONS IN
AREAS OF WORK AS REQUIRED TO MAINTAIN RATING
12. PATCH AND REPAIR AS REQUIRED ANY EXISTING
PARTITIONS TO REMAIN WHERE ADJACENT PARTITIONS
ARE BEING DEMOLISHED.
13. PREPARES FLOORS FOR NEW FINISHES AT
DEMOLISHED FLOOR FINISHES.
N
TRUE NORTH
N
PLAN NORTH
CLEAN
STORAGE
MECHANICAL
SHAFT
300-M
IMAGING
ROOM 1
324A
IMAGING
ROOM 2
324B
RAD HOT LAB
STRESS TEST
LAB
CORRIDOR
CORRIDOR
DECAY CL.
IMAGING
ROOM 3
PAT. WAIT
ELEC
SP3124
MECHANICAL
SHAFT
SP3125
WK.AREA
PH3100
CONSULTATION
ROOM
PH3101
HC TLT.
AA3109
HC TLT.
AA3110
CORRIDOR
AA3118
SUB-WAITING
AREA
PATIENT TLT.
3310A
UPTAKE AREA
PREP AREA
UNISEX PT.
RESTROOM
DRESS
UNISEX STAFF
RESTROOM
308OFFICE
WAITING
RECEPTION
303A
CORRIDOR
A2.1
CORRIDOR
DECAY CL.
IMAGING
ROOM 3
PAT. WAIT
318 ELEC
SP3124
221221
212232
Revisions:
A u s ti n
S a n A n to n io
H o u st o n
B a rt o n
S p ri n g s
R o a d
S u it e
A u st in
Te x a s
B ro a d w a y
S u it e
S a n A n to n io
Te x a s
F a n n in S tr e e t, S u it e
H o u st o n
Te x a s p
.4
.7
.4
.7 p
.2
.6
.2
.6 p
.4
.1
.4
.1
25-2MC02328
A u to d e s k D o c s
/H a rr is
H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/
H
H S
L B
J G a m m a
C a m e ra R p lc m n t_ A
R C
H
C e n tr a l.
rv t
/2
/2
:1
:2
P M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K
E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
12/23/2025
Project No. 2321.08
CONTRACT DOCUMENTS
DEMOLITION PLAN
A2.1
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
GENERAL
DEMOLITION NOTES
KEYNOTE LEGEND
203 EXISTING ELECTRICAL PANEL TO BE REMOVED. RE:
ELECT.
210 REMOVE AND SALVAGE OWNER EQUIPMENT FOR
REINSTALLATION.
212 REMOVE EXISTING UPPER CABINETS
214 REMOVE EXISTING CASEWORK AND PLUMBING
FIXTURES. SALVAGE ANY WALL MOUNTED EQUIPMENT
FOR REINSTALLATION. RE: EQUIPMENT DWGS
221 REMOVE EXISTING FLOORING, WALL BASE, WALL
PROTECTION, CEILING TILE, AND CEILING GRID WHERE
INDICATED BY HATCH. EXISTING SLAB SHALL BE
PREPPED FOR INSTALLATION OF NEW WORK
232 REMOVE EXISTING SINK
234 REMOVE EXISTING CURTAIN AND TRACK
253 REMOVE PORTION OF EXISTING PARTITION AS
REQUIRED FOR NEW CONSTRUCTION. REFER TO
FLOOR PLAN FOR EXACT DIMENSIONS AND LOCATION.
A
KEY PLAN
SCALE: 3/16" = 1'-0"
OVERALL NUCLEAR MEDICINE SUITE DEMOLITION PLAN
SCALE: 1/4" = 1'-0"
ENLARGED NUCLEAR MEDICINE SUITE DEMOLITION PLAN
OFFICE 3310A
ST. TLT.
ST. LKRS.
PAT. SUB
WAIT
DECAY
CL.
FEC
IPP
IPP
IPP
IPP IPP
IPP
IPP
IPP
Video Intercom
O 2 A V
FEC
COURTYARD
COURTYARD
COURTYARD
PA3166
JAN
Courtyard #4
AA3114
MECH
SA3103
ELEC
SN3162
JAN
SP3125
MECH
AA3115
MECH
SU3106
OR MGR.
SU3174
STAFF LOUNGE
SU3161
ELEC
SU3173
JAN
SU3171
ON-CALL
AA0006
STAIRS
AA0007
STAIRS
PA3159
CYTOLOGY
PA3130
CHEMO
IMMUNO
PA3101
ADMIN SECYS.
PA3148
HEMATOLOGY
PA3125
ELEC
AA0008
STAIRS
AA0003
STAIR F
AA0001
STAIRS
SP3107
ON CALL
DT3100
ELECTRICAL
CLOSET
AA3106E
ELEV
SP3100
M. ST. TLT.
SP3113
OFFICE
SP3112
OFFICE
AA3111E
ELEVS
#8,9
AA3103
HC TLT
SA3106
SOILED LIFT
VEST
300-E
ELEVATORS
#1,2,3
300-E2
ELEVATORS
# 4,5,6,7
300-M
MECHANICAL
SHAFT
SA3100
ELEC
SN3100A
IS
SN3119
NOURISH
SN3167
NOURISH
SN3150
ELEC
3C51024
NOURISH
3C51002
JAN
SA3105
ELEC
SP3114
ON-CALL
IC3108
ON-CALL
SA3108
ELEC
IC3146
JAN
IC3125
JAN
SU3120
JAN
SU3180
JAN
PA3167
MECH
EE3111
JAN
BS3100
CART PARK
SN3145
CASE MGMT
OFFICE
SN3147
ST. TLT.
3B31014B
STAFF LOUNGE
PA3107
STAFF LOUNGE
SU3121
W. LKRS.
SU3183
ON-CALL
IC3148
STAFF LOUNGE
IC3152
IC3154
ON-CALL
ST. LKRS.
RT3105
ST. LKRS.
3G3006B
STAFF LOUNGE
SN3103
STAFF TLT
3C51018
STAFF LOUNGE
PA3106
CONFERENCE
ROOM
PA3128
PATH
SIGN-OUT
SN3140
STORAGE
SU3131
M. LKRS.
SU3127
W. LKRS.
SU3111
RESIDENT
TEAM ROOM
SU3110
DR. LOUNGE
SN3184
TEAM
ROOM
3C51051
TEAM
ROOM
IC3126
TEAM
ROOM
EE3114
INTERP. READING
ROOM
IC3149
RESIDENT LOUNGE/
CONFERENCE ROOM
SP3120
RESIDENT
OFFICE
SP3119
RESIDENTS
PLASTIC SURGERY
AA0005
STAIRS
AA3103E
ELEVATORS
# 12, 13
MN3100
FAMILY
WAITING
SN3100
IDF
SN3101
STOR.
SN3105
TLT.
TAS/ADA
SN3104
PAT RM. 3A 01
TAS/ADA
SN3141
NURSE MGR.
SN3139
SOILED
UTILITY
SN3106
CLEAN LIN.
SN3196
CLEAN SUPL.
SN3138
TLT.
TAS/ADA SN3137
ISOL. RM. 3A 12
TAS/ADA
SN3136
ANTE
SN3135
ISOL. RM.
3A 11
SN3134
TLT.
SN3133
TLT.
SN3132
ISOL. RM.
3A 10
SN3142
NURSE STA.
SN3143
CLEAN
SUPPLY
SN3144
MEDS RM.
SN3192
CORR. 51
SN3108
TLT.
SN3107
PAT RM.
3A 02
SN3109
TLT.
SN3110
PAT RM.
3A 03
SN3191
CORR. 52
SN3193
CORRIDOR
SN3112
STAFF LOUNGE
SN3114
PAT. RM.
3A 04
SN3115
TLT.
SN3116
TLT.
SN3117
PAT. RM.
3A 05
SN3120
PAT. RM.
3A 06
SN321
TLT.
SN3122
TLT.
SN3124
WC SHWR.
SN3123
PAT. RM.
3A 07
SN3125
NURSE CLIN.
EDUCATOR
SN3126
ANTE
SN3127
ISOL. RM.
3A 08
SN3128
TLT.
SN3129
SN3130 TLT.
ISOL. RM.
SN3131
3A 09
ANTE
SN3185
EQUIP. STOR.
SN3168
NURSE MGR.
SN3169
ANTE
SN3170
ISOL. RM.
3B 08
SN3171
TLT.
SN3172
TLT. SN3173
ISOL. RM.
3B 09
SN3174
ANTE SN3187
PHYS. CHART
SN3166
PAT. RM.
3B 07
SN3163
WC SHWR.
SN3165
TLT.
SN3164A
TLT.
SN3164
PAT. RM.
3B 06
SN3160
PAT. RM.
3B 05
SN3161
TLT.
SN3159
TLT.
SN3158
PAT. RM.
3B 04
SN3155
PAT. RM.
3B 03
SN3156
TLT.
SN3190
CORRIDOR
SN3186
REPORT
ROOM
SN3152
TLT.
SN3151
PAT. RM.
3B 02
SN3188
CORR. 31
SN3189
CORR. 32
SN3183
N. STA./CHART/
MEDS.
SN3195
CLN.
SUPL.
SN3194
CLN.
LIN.
SN3149
PAT. RM. 3B 01
TAS/ADA
SN3148
TLT.
TAS/ADA
SN3182
SOILED
UTILITY
SN3181
TLT.
TAS/ADA
SN3180
ISOL. RM. 3B 12
TAS/ADA
SN3178
ISOL. RM.
3B 11
SN3177
TLT.
SN3176
TLT.
SN3175
ISOL. RM.
3B 10
SN3179
ANTE
AA0002
STAIR
MN3122
EQUIP.
STOR.
AA0004
STAIR
AA0009
STAIR
AA3109
HC TLT.
AA3110
HC TLT.
SN3111
TUB RM.
WAITING
309A
RECEPT.
PT. TLT./
DRESS.1
PT. TLT./
DRESS 2
PREP.
RAD HOT
LAB
309 CORRIDOR
CORRIDOR
STRESS TEST
LAB
3SP3002C
EXAM 6
3SP3002B
EXAM 5
3G3006K
EXAM 4
3G3006J
EXAM 3
3G3006H
EXAM 2
3G3006G
PT. TLT. 3G3006F
EXAM 1
3G3006E
VITALS
3G3006
WAITING
3G3006D
NURSE STA.
3G3006C
ST. TLT.
3G3006L
CORRIDOR
SP3108
TLT.
SP3109
TLT.
SP3110
ON-CALL
EE3105
ECHO TEST.
EE3104
ST. WK./
READING
EE3103
TREADMILL
ROOM
EE3102
EQUIP.
STOR.
EE3100
RECEPT./
WAITING
EE3118
SECY./FILES
SUPL./CHART.
EE3101
CORRIDOR
EE3119
SUPPLY
EE3117
READING
ROOM
EE3116
EKG TEST.
EE3112
TLT.
EE3113
EGG TEST.
EE3115
CTRL.
EE3109A
EE3109ST. TLT.
LKRS.
EE3108
CORR.
EE3107
OFFICE
EE3106
HOLTER
EXAM
BS3102
LOUNGE
BS3101
TLT.
SP3101
W. ST. TLT.
SA3106A
CART
LIFTS
SA3107
CLEAN
CARTS
PA3104
CHIEF TECH.
PA3103
QUAL. CTRL.
PA3102
LAB MGR.
PA3105
SUPPLY
RECORDS
SU3134
TLT./SHWR.
SU3133
W. LKRS.
SU3132
TLT./SHWR.
SU3128
TLT./SHWR.
SU3130
TLT./SHWR.
SU3129
M. LKRS.
SU3122
TLT./SHWR.
SU3123
M. LKRS.
SU3124
TLT./SHWR.
SU3105
OFFICE
SU3104
OFFICE
IC3153
TLT.
IC3155
TLT.
IC3156
TLT.
IC3164
ST. LKRS.
RT3106
TLT.
SP3115
TLT.
SP3116
ON-CALL
IC3109
TLT.
IC3160
OFFICE
IC3159
DIRECTOR
IC3158
OFFICE
RT3107
CHARTING/
CONF./LIB.
RT3110
EQUIP. STOR./
REPAIR
IC3157
HALL
IC3151
SUPPLIES
RECEIVING
IC3147
EQUIP.
STOR.
IC3150
CORR.
RT3101
PULMONARY
FUNCTION
RT3102
SUPVR.
RT3103
TECH. DIR.
RT3108
EQUIP.
DECON.
RT3109
EQUIP.
ASSEMBLY
NS3101
DISCHRG.
PLAN
NS3100
CONF. RM.
NS3102
ASSOC.
DIR.
SP3117
PULM. FCTN.
TESTING
SP3118
CONSULT.
RT3104
CORR.
RT3100
WAITING/
SECY./FILES
SP3121
PHYS. OFC.
IC3104
SURGERY
LIBRARY
IC3105
PULMONARY
FELLOWS
SP3122
CORRIDOR
SP3123
OFC. MGR./
SECY.
OS3103
SURG. DIR.
OS3104
PHYS. OFC.
IC3123
ISOLATION
IC3124
TLT.
IC3122
ANTE RM.
IC3120
ISOLATION
IC3119
1-BED RM.
IC3118
1-BED RM.
IC3117
1-BED RM.
IC3128
NURSE STA.
IC3129
CORR.
IC3130
ST. TLT.
IC3132
HC TLT.
IC3134
SUPPLY
RM.
IC3135
REPORT
RM.
IC3136A
MED. EMERG.
CART
IC3136
N. STA./MON./
EDP/CHART
IC3116
TLT.
IC3115
1-BED RM.
IC3114
TLT.
IC3113
1-BED RM.
IC3111
1-BED RM.
IC3139
ISOLATION
IC3141
ANTE RM.
IC3140
TLT.
IC3143
TLT.
IC3142
ISOLATION
IC3138
CORRIDOR
IC3144
CLEAN
UTIL.
IC3145
SOILED
UTILITY
IC3137
CORRIDOR
IC3106
CLN. LIN./
STOR.
IC3110
DIALYSIS
SUPL.
IC3100
CORR.
IC3107
CORR.
IC3102
FAMILY
WAITING
IC3101
ELECTRICAL
IC3103
NRS. MGR.
IC3107A
PT. SHWR.
IC3112
TLT.
IC3127
SICU
IC3121
TLT.
SU3172
TLT.
SU3184
TLT.
PA3158
SUPVR.
PA3160
PATH. OFC.
PA3126
CORRIDOR
PA3119
MICRO./TB
PA3118
MEDIA
PREP
PA3117
CLEAN-UP
PA3109
M. LKRS./
TLT.
PA3108
W. LKRS./
TLT.
PA3153
HISTOLOGY
PA3157
HISTOLOGY
PA3156
LOG-IN
PA3154
PARAFFIN BLK.
SLIDE STOR.
PA3155
INTERCHANGE
PA3132
PATHOLOGIST
PA3129
RESIDENT
SUPVR.
PA3114A
PA3114AA
PA3114
HALL
PA3116
FLAM.
PA3111
SUPPLY
TECH
PA3112
DISP.
PA3113
INVENTORY
STOR.
PA3133
CORE LAB
PA3140
WORKROOM
PA3134
EQUIPMENT
ROOM
SU3138
SCRUB
ALCOVE
SU3139
OPERATING
ROOM 6
SU3143
SCRUB
ALCOVE
SU3145
ELEC
SU3137
CORR.
SU3144
OPERATING
ROOM 5
SU3142
SUBSTERILE
SU3140
SUBSTERILE
SU3168
ORTHO/
PLASTER
SU3190
SUBSTERILE
SU3160
EQUIP.
SU3167
OPERATING
ROOM 1
SU3159
STERILE CORE
SU3166
SCRUB
ALCOVE
SU3169
CORR.
SU3188
STRTCR.
ALCOVE
SU3163
OPERATING
ROOM 2 SU3162
SCRUB
ALCOVE
SU3164
STERILE
SU3170
OR STOR.
SU3158
HALL
SU3157
NURSE STA./
MED/REF
SU3155
CYSTOLOGY
OR 3
SU3151
SUBSTERILE
SU3154
SUBSTERILE
SU3150
OPERATING
ROOM 4
SU3159A
LIFT
SU3149
SCRUB
ALCOVE
SU3152
WORK RM.
SU3146
ANESTH.
WK. RM.
SU3147
STORAGE
SU3148
ANESTH.
CLEAN-UP
SU3156
EQUIP.
SU3125
HALL
SU3126
CLEAN-UP
DISPATCH
SU3135
BLOOD PASS
ACCESS
SU3119
HALL
SU3108
OR STOR.
SU3107
HALL
SU3119A
SU3112
SU3118 HALL
ANESTH.
SU3117
ANESTH.
SU3116
ANESTH.
SU3113
ANESTH.
DIRECTOR
SU3114
SECY.
SU3186
CORRIDOR
SU3185
NURSE STA.
(BOOK'G)
SU3189
ASST. DIR.
SU3103
CORR.
SU3187
PRE-OP HOLD
AS3112
OUTPATIENT
RECOVERY
SU3192
ANESTH./EQUIP.
IC3162A
OR BIO-WASTE
IC3162
CORRIDOR
AS3113
N. STA./MEDS.
NOUR./CL. UTIL.
AS3115
NURSE MGR.
AS3110
PT. TLT.
AS3111
ST. TLT.
AS3109
SOILED
UTILITY
AS3108
JAN
AS3117
WAITING
ELEC
AA3102
STAFF/PAT.
ELEV. LOBBY AA3111
ELEV.
LOBBY
AA3106
STAFF/PAT.
ELEV. LOBBY
AA3100
ELEV.
LOBBY
AA3118
CORRIDOR
AA3112
CORRIDOR
AA3113
CORRIDOR
AA3117
CORRIDOR
AA3116
CORRIDOR
AA3108
CORRIDOR
AA3107
CORRIDOR
AA3101
CORRIDOR
SP3111
CLASSROOM
3C51003
CENTRAL
MONITORING
3C51004
ST. TLT.
3C51010
CL. LIN.
3C51030
WC SHWR.
3C51028
PAT. RM.
3C 07
3C51028B
TLT.
3C51026B
TLT.
3C51026
PAT. RM.
3C 06
3C51022
PAT. RM.
3C 05
3C51022B
TLT.
3C51020B
TLT.
3C51020
PAT. RM.
3C 04
3C51013
TUB RM.
3C51011B
TLT.
3C51011
ISOL. RM.
3C 08
3C52011
ANTE
3C51009
MEDS. RM. 3C51007
CLEAN
SUPPLY
3C51052
CORR. 52
3C51016
PAT. RM.
3C 03
3C51016B
TLT.
3C51014B
TLT.
3C51014
PAT. RM. 3C 02
3C51005
TAS/ADA
NURSE STA.
3C51053
CORR. 51
3C52009B
TLT.
3C52009
ISOL. RM.
3C 09
3C52007B
TLT.
3C52007
ISOL. RM.
3C 10
3C52005
ANTE
3C51012
CL. SUPL.
3C51051
CORRIDOR
3B31014
DIR. NURSING
EE3100A
VACANT
EE3100A
VACANT
MM3100
PHARMACY
OFFICE
PA102A
PATHOLOGY
OFFICE
PA103
PATHOLOGY
SIGN-OUT
PA104
ADMIN
ASSISTANT
PA102B
PATHOLOGY
OFFICE PA105
PATHOLOGY
OFFICE
PA106
CYTOLOGY
TECHS
PA108
TRANSCRIPTION
PA110
RESTROOM
PA111
RESTROOM
PA109
STORAGE
PA101
RECEIVING/PROCESSING
SEND OUT
PA100
AUTO
CHEM/IMMUNO
PA107
HISTOLOGY
OFFICE
1 2 3 4 5
PA3110
CORRIDOR
COAG/
URINALYSIS
AUTO HEM
EQUIPMENT
STORAGE
BCA COMPUTER + PRINTER
CPU CPU
FUTURE CPU FUTURE CPU
CPU
CPU
PASS
THRU
REF.
PASS
THRU
REF.
PASS
THRU
REF.
PASS
THRU
REF.
CPU CPU
CPU
CPU
CPU CPU
CPU CPU
CPU CPU
CPU
CPU
324A
GAMMA CAMERA
CLEAN
SUPPLY
N
TRUE NORTH
N
PLAN NORTH
A3.1
A3.1
A3.1
Revisions:
A u s ti n
S a n A n to n io
H o u st o n
B a rt o n
S p ri n g s
R o a d
S u it e
A u st in
Te x a s
B ro a d w a y
S u it e
S a n A n to n io
Te x a s
F a n n in S tr e e t, S u it e
H o u st o n
Te x a s p
.4
.7
.4
.7 p
.2
.6
.2
.6 p
.4
.1
.4
.1
25-2MC02328
A u to d e s k D o c s
/H a rr is
H e a lt h
L
B J G a m m a
C a m e ra R e p la c e m e n t/
H
H S
L B
J G a m m a
C a m e ra R p lc m n t_ A
R C
H
C e n tr a l.
rv t
/2
/2
:1
:2
P M
L B
J S
C A
N S
Y S
/G A
M M
A /S
IN
G
L E
P H
O T
O N
E M
IS
S
IO
N
K
E
LL
E Y
S
TR
E E T, H O
U S
TO
N
TX
H A
R R
IS
H
E A
LT
H
12/23/2025
Project No. 2321.08
CONTRACT DOCUMENTS
COMPOSITE FLOOR
PLAN
A3.0
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
O
'C O
N N
E L L
R O
B E R
TS
O
N
IN
C
A
KEY PLAN
SCALE: 1/16" = 1'-0"
COMPOSITE THIRD FLOOR PLAN
N
TRUE NORTH
N
PLAN NORTH
1. ALL ACCESSIBLE FIXTURES AND ACCESSORIES TO BE
MOUNTED AT ADULT MOUNTING HEIGHTS U.N.O.
2. REFER TO A7 SERIES FOR DOOR SCHEDULE AND FRAME
TYPES
3. REFER TO SHEET A7.2 FOR PARTITION TYPES
4. FLOOR PLAN DIMENSIONS ARE TO THE FINISHED FACE OF
PARTITIONS UNLESS NOTED OTHERWISE
GENERAL FLOOR
PLAN NOTES
STRESS TEST
LAB
ELEC
SP3124
IMAGING ROOM
DECAY CL.
CORRIDOR
IMAGING
ROOM 2
324B
CONTROL
ROOM
SUB-WAITING
AREA
ALIGN
EQ-04
EQ-06EQ-14EQ-07
EQ-08
EQ-09
EQ-10
EQ-05
TA-11
TA-10
EQ-18
M
1'-6" 6'-8 3/8"
OF GAMMA CAMERA
/8
OF GAMMA
CAMERA
M
SA
1'-6"
EQ-19
EQ-01
EQ-02
EQ-03
EQ-13
EQ-16EQ-16
EQ-17
EQ-12
EQ-11
EQ-20
EQ-21
EQ-22
EQ-23
EQ-24
EQ-25
CC-3,
CUBICLE
CURTAIN &
TRACK
IMAGING ROOM
ELEC
SP3124
CONTROL
ROOM
SUB-WAITING
AREA
CORRIDOR
DECAY CL.
IMAGING
ROOM 2
324B
STRESS TEST
LAB
2'-9"
ALIGN
800800
6'-8 3/8"
/8
OF GAMMA CAMERA
OF GAMMA
CAMERA
1. CEILING HEIGHT IS 8'-0" ABOVE FINISHED FLOOR UNLESS
NOTED OTHERWISE.
2. CEILING TYPE IS ACT1 UNLESS NOTED OTHERWISE.
3. PAINT DESIGNATIONS AT GYP CEILINGS AND FURR
DOWNS APPLY TO ALL EXPOSED GYP U.N.O. GYP
CEILINGS AND FURR DOWNS TO BE PT2 U.N.O.
4. NOT ALL CEILING DEVICES ARE SHOWN ON THE
ARCHITECTURAL REFLECTED CEILING PLAN, DEVICES
ARE SHOWN TO REPRESENT THE DESIRED LOCATION
AND IMPACT ON DESIGN INTENT.
5. REFERENCE MEP DRAWINGS FOR FINAL LOCATION.
EXISTING 2' X 2' ACT
2' X 2' ACT
PAINTED GYPSUM WALL BOARD
1. REFER TO THE ROOM FINISH SCHEDULE FOR ALL FINISH
DESIGNATIONS. FINISH PLANS TO BE USED WHEN MORE
THAN ONE FINISH IS USED IN A ROOM.
2. REFER TO A7 SERIES FOR INTERIOR ELEVATIONS
3. PT-10 AT ALL WALLS U.N.O.
4. DOOR FRAMES TO BE PAINTED TO MATCH ADJACENT
WALL COLOR U.N.O.
5. "PT" INDICATES MULTIPLE WALL FINISHES WITHIN A ROOM.
PT-10 AT WALLS WHERE A WALL FINISH IS NOT INDICATED
U.N.O.
6. "RSF" INDICATES MULTIPLE FLOOR FINISHES WITHIN A
ROOM. REFER TO FINISH LEGEND FOR FLOORING HATCH
DESIGNATION.
7. "RSC" INDICATES MULTIPLE COVE FINISHES WITHIN A
ROOM. COVE BASE TO MATCH ADJACENT FLOORING.
REFER TO FINISH LEGEND FOR FLOORING HATCH
DESIGNATION.
ALIGN FINISH
XX EXTENTS OF FINISH
ROOM NAME
ROOM #
FLOOR FINISH
BASE FINISH
WA…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .