This statement of work outlines requirements for a construction project on Cottonwood Road between mileposts 16.31 and 20.80 on the Stanislaus National Forest. Work will include slide stabilization, pavement rehabilitation and repairs, material removal, riprap ditch construction, pavement removal and replacement, drainage repairs, and traffic control. The project is located on the MiWok and Groveland Ranger Districts in California. Specifications include the 2014 FHWA Standard Specification and Forest Service Supplemental Specifications. The solicitation requests sealed offers due by May 12, 2020 to perform work which includes slide material removal, aggregate base, asphalt concrete, drainage repairs, and traffic control. Submittals such as erosion control plans, traffic control plans, and material certifications must be provided within specified timeframes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Official Responses.pdf | ||
| A00002 - RFIs.pdf | ||
| A00001 - Time Extension - Site Visit.pdf | ||
| 4. Schedule of Items.pdf | ||
| 3. Supplemental Fire Plan.pdf | ||
| 2. Cottonwood Road Repairs Plans – Final.pdf | ||
| 1. Supplemental Specifications.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 6. WD # CA20200018.pdf | ||
| 129JGP20R0017 - Cottonwood Road Repairs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cottonwood Road Repairs 2020
Individual Project Task Order Page 1 of 2
SECTION C – STATEMENT OF WORK
C-1 PROJECT SCOPE
Work will consist of slide stabilization and pavement rehabilitation and repair on road 1N04
(Cottonwood) between mileposts 16.31 and 20.80. Work will also include, but is not limited to: slide material removal, riprap ditch construction, pavement removal, subgrade or base reconditioning, aggregate base, asphalt conrete, asphalt curbs, pavement striping, repairing drainage pipes, patching asphalt, erosion control and traffic control.
C-2 PROJECT LOCATION
This project is located on the Miwok and Groveland Ranger Districts on the Stanislaus National Forest.
From Sonora CA, head south on S Washington St for 0.5 mi, then turn left on Restano Way then immediately right on Mono Way and head east for 2.0 mi, then turn right on Tuolumne Road and head east for 6.9 mi, then turn left on Carter Street and head northeast for 0.3 mi, then turn right on Buchanan
Road and follow east for 16.2 mi to the the project area and Site #1.
C-3 SPECIFICATIONS APPLICABLE TO THIS INDIVIDUAL PROJECT
[X] FHWA Standard Specification 2014 applies
[_] FHWA Standard Specification 2003 Metric applies
The attached “Forest Service Supplemental Specifications” apply. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.
C-4 PRODUCTS SAMPLES AND/OR SUBMITTALS
Title Referenced by Contract clause or Specification No.
Time of Government
Approval After
Submittal
Soil Erosion & Pollution Control Plan
(California Construction General
Permit)
Plans, Sheet G2 10 days
Temporary Traffic Control Plan FP-14 156 10 days
Cottonwood Road Repairs 2020
Individual Project Task Order Page 2 of 2
C-5 MATERIAL CERTIFICATIONS AND TESTING REPORTS
Title
Referenced by Contract clause or Specification No.
Time of
Government
Approval
After
Submittal
Aggregate base CalTrans Standard Specifications Section 26 10 days
Asphalt concrete CalTrans Standard Specifications Section 39 10 days
Riprap rock FP-14 705.02 10 days
Geotextile filter FP-14 714.01(a) 10 days
Temporary rolled erosion control product
FP-14 713.17 10 days
Pavement markings FP-14 634 10 days