5. Forest Service Supplemental Specifications.pdf
PDF 865 KB Posted
- Solicitation number
- 127EAW22R0055
- Issued by
-
Department of Agriculture Forest Service
About this file
This federal contract solicitation is for the Pine Canyon Water System Upgrades project located on the Los Padres National Forest. The project scope involves well and wellhead improvements, replacing water supply and distribution piping, and optionally constructing a new utility building. The total value of the contract is estimated between $250,000 to $500,000. The solicitation is a total small business set aside issued by the USDA Forest Service. Requests for information are due by July 7, 2022. The pre-proposal site visit is optional as the project locations are open for prospective offerors to view.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3. Schedule.docx | DOCX document | |
| 127EAW22R0055.pdf | ||
| 4. Pine Canyon Water System Plans - 10 June.pdf | ||
| 1. Statement of Work.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 2. Fire Plan.pdf | ||
| 6. Davis-Bacon Act WD # CA20220014.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Forest Service
Los Padres National Forest
PINE CANYON WATER SYSTEM
UPGRADES
Technical Specifications
LIST OF TECHNICAL SPECIFICATIONS
010100 SUMMARY OF WORK
011250 MEASUREMENT AND PAYMENT
011900 MOBILIZATION
013300 SUBMITTALS
015500 GOVERNMENT FURNISHED MATERIALS
017320 SELECTIVE DEMOLITION
133400 PRECAST CONCRETE UTILITY BUILDING
221100 WATER DISTRIBUTION SYSTEMS
221103 PLUMBING APPURTENANCES
221120 SUBMERSIBLE WELL PUMPS
260500 COMMON WORK RESULTS FOR ELECTRICAL
260519 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
262726 WIRING DEVICES
312000 EARTHWORK
321216 ASPHALT PAVING
013300 - 1
SUBMITTAL PROCEDURES
USDA FOREST SERVICE, R-5
PINE CANYON WATER SYSTEM UPGRADES
SECTION 013300- SUBMITTAL PROCEDURES
PART 1- GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.
1.2 DEFINITIONS
A. Informational Submittals: Written information that does not require CO's approval.
Submittals may be rejected for not complying with requirements.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. CO reserves the right to withhold action on a submittal requiring coordina-tion with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for resub-mittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 10 days for initial review of each submittal. Allow addi-tional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial sub-mittal.
3. Allow 10 days for processing each resubmittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place title block on each submittal for identification.
1. Include the following information on label for processing and recording action taken:
a. Project name.
013300 - 2
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. Other necessary identification.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
PART 2 – PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise in-dicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of con-struction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are ap-plicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Compliance with recognized trade association standards.
f. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
013300 - 3
c. Fabrication and installation drawings.
d. Notation of dimensions established by field measurement.
D. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors available.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit two copies of each submittal, unless otherwise indi-cated. CO will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes sig-nature of entity responsible for preparing certification. Certificates and certifi-cations shall be signed by an officer or other individual authorized to sign doc-uments on behalf of that entity.
B. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operat-ing a product or equipment. Include name of product and name, address, and tele-phone number of manufacturer.
PART 3 – EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
END OF SECTION 01330
May 2021
SUMMARY OF WORK SECTION 010100- 1
PINE CANYON WATER SYSTEM UPGRADES
SECTION 010100 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Work for this project involves well and well head improvments, replacement of water supply and distribution piping at the Pine Canyon Work Center with options to construct a new utility building with new power service and plumbing, and install a water tanker fill station. The Pine Canyon Work Center water system serves 2 buildings containing both office and crew quarters space. There are multiple other out buildings onsite. This work shall include the following:
BASE ITEMS
1. 11900 Mobilization, Demobilization, and Bonding. This Item includes transport of all equipment, labor, and materials to and from the site; and bonding. Contractor shall pothole all potential conflicts and utility crossings incidental to this item and report any issues to the CO.
2. 221120-A Well Head Upgrades. This item includes all well head improvements including new well seal; vent; waterline; electrical J-box; conduit with airline and submersible well pump conductors; well head enclosure; concrete collar replacement; selective demolition of all existing wiring, piping and appurtenances at the well head; earthwork; and all piping, conductor, conduit, fittings and appurtenances from the well head to the utility building.
3. 221120-B Well Casing Liner Installation. This item includes installation of casing liner, both slotted and blank, installation of a watertight packer to block sediment from upper zone from entering the well, and reinstallation of the existing submersible well pump and drop pipe.
4. 221103-D Well Modification and Water System Construction Permit Coordination. Contractor shall work with the Forest Service and Santa Barbara County to coordinate the well modification permit and the water system construction permit. The Forest Service will provide completed application documents. Contractor shall cover fees of $721, and $1604 respectively, submit construction reports, and arrange county inspections as necessary.
SUMMARY OF WORK SECTION 010100- 2
5. 13340-A Precast Concrete Utility Building Installation. Installation of a 10.5’
X 12’ manufactured concrete utility building. Contractor shall complete utility building stubs within 5’ of the building, subgrade preparation, bedding, and coordinate setting of the structure by the manufacturer, and placement of concrete slab at building entry all incidental to this pay item.
6. 221103-E Utility Building Plumbing. Utility building plumbing shall include new water meter, chlorine injection equipment, water filtration, and all valving, piping, and plumbing appurtenances, and fittings within 5’ of the utility building.
7. 26050-A New Power Service. This item includes the coordination of new power service to the new utility building. Contractor shall fully coordinate new service with Pacific Gas and Electric. Once fees are known, actual costs shall be modified into this item.
8. 26050-B Utility Building Electrical. Utility building electrical shall include a contractor furnished power service entrance panel with main disconnect, and wiring of a GFM pump control panel with float switch activated control. Contractor shall provide all enclosures, luminare, receptacles, wiring, conduit, electrical appurtenances, and fittings within 5’ of the utility building to complete a fully functional and automatic system.
9. 26050-C New Power Service Lateral. Power Service Lateral shall include all trenching, conduit, and electrical line installation between the PGE service drop and the utility building.
OPTION ITEM
Bid Option #1
10. 221100-A 1-1/2” HDPE Waterline Installation. Installation of 1.25” HDPE water line. Incidental to this item is all waterline fittings and appurtencances; line marker posts, wire, and tape; all earthwork including bedding and backfill material, and care taken to preserve vegetation onsite; and final hydrostatic testing and disinfection.
11. 221100-B 1-1/2” HDPE Curb Valve and Box Installation. Installation of 1. 5” poly curb valve, and valve boxes. Incidental to this are all line; fittings and appurtenances; box insulation; and all other work within 5’ of valve boxes.
12. 221100-C 3” HDPE Waterline Installation. Installation of 3” HDPE water line.
Incidental to this item is all waterline fittings and appurtencances; line marker posts, wire, and tape; all earthwork including bedding and backfill material, and care taken to preserve vegetation onsite; and final hydrostatic testing and disinfection.
13. 221100-D 3” HDPE Curb Valve and Box Installation. Installation of 3” poly curb valve, and valve box. Incidental to this are all line; fittings and appurtenances;
box insulation; and all other work within 5’ of valve boxes.
14. 221103-B New Service Connection. Replacement of water service lateral connections to two buildings. Work includes tie-in of new 1.5” HDPE piping with existing PVC piping within 5’ of the buiding foundations. Incidental to this work are all pipe, fittings, and appurtanances; and all other work within 5’ of tie-in.
Service connections shall include a one way check valve.
SUMMARY OF WORK SECTION 010100- 3
15. 221103-C, Daylight Drain Assembly Installation. Includes all earthwork, piping, fittings, appurtenances and rip rap within 10’ of termination.
documents. Contractor shall cover fees of $721, and $1604 respectively, submit construction reports, and arrange county inspections as necessary.
16. 321216-A Asphalt Paving Resurfacing. This item includes replacement of hot mix asphalt paving disturbed by waterline trench excavation. Incidental to this item is all materials, labor, equipment required to install new asphalt pavement to specification.
1.2 LOCATION
A. The Pine Canyon Work Center is located 15 miles NE of Santa Maria, CA on Highway-
CA-166.
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The elevation of the work Center is approximately 841’ feet above mean sea level. The construction site is an administrative compound in a rural setting and experiences mild winters and rare snow fall.
B. In-depth soil surveys have not been performed; however, rocks at the ground surface are evident tin areas area. Blasting of rocks will not be permitted.
C. In-depth water table surveys have not been performed. The Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property.
1.4 USE OF PREMISES
A. General: Contractor shall have full access to grounds for construction operations during construction period, and limited access to facilities. Contractor's use of premises is limited by the Government's right to perform work or to retain other contractors on portions of Project site. Crew housing buildings will not be available other than for construction access. Building access shall be coordinated with CO.
B. Contractor shall conduct his operations to ensure the least inconvenience to the public and employees. Work is limited to the hours of 7am-8pm to accommodate FS personnel living onsite.
C. Notify Contracting Officer at least 72 hours prior to start of work. Provide 24 hours notice prior to any work occurring within buildings onsite.
D. Confine storage of equipment and materials to areas as approved by the CO.
E. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of work area.
SUMMARY OF WORK SECTION 010100- 4
F. Preservation of Natural Features: Confines all operations to work limits of the project.
Prevent damage to natural surroundings. Restore damaged areas, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with CO and remove agreed-on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
G. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.
1. Contractor shall be responsible for locating and preventing damage to known utilities. Call the CA USA North 811 at 1-800-642-2444. Atleast 2 business days in advance of excavation for the marking of underground utilities. If damage occurs, repair utility at no additional expense to the Government.
2. Interruption of Existing Utility Service: Notify CO, 48 hours in advance of any interruption of existing utilities.
3. Water service interruption shall be minimized and approved by the Contracting Officer in the construction schedule.
1.5 MEALS AND LODGING
A. Meals and lodging are commercially available in the city of Santa Maria area within 15 miles of the construction site. Meals or lodging will not be available at Forest Service facilities.
1.6 CAMPING
A. With approval by the Santa Lucia Ranger District, National Forest Service lands may be used by the Contractor to have one fully contained recreation vehicle which may remain at this site for security.
1.7 CONSTRUCTION SEQUENCE
A. Contractor shall provide construction sequencing in the schedule that reduces service interruption to the work center.
B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
C. The Contractor may use water (currently non potable) and power utilities available onsite.
1.8 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering materials.
SUMMARY OF WORK SECTION 010100- 5
1.9 PERMITS
A. Special permits for electrical work, water system work, well head work, or any other permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 010100
June 2022
MEASUREMENT AND PAYMENT 011250- 1
PINE CANYON WATER SYSTEM UPGRADES
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Each (EA): One complete unit, which may consist of one or more parts.
2. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
1. Square Foot (SF): Measurement of work along its length from point-to-point;
multiplied by its width from point-to-point. Do not measure overlaps.
2. Lump Sum (LS): One complete unit.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
MEASUREMENT AND PAYMENT 011250- 2
2. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
May 2021
GOVERNMENT FURNISHED MATERIALS (GFM) SECTION 01550-1
PINE CANYON WATER SYSTEM UPGRADES
SECTION 015500 - GOVERNMENT FURNISHED MATERIALS (GFM)
PART 1 - GENERAL
1.1 SUMMARY
A. Applies to materials that shall be provided by the Government and installed by the Contractor.
1.2 INSPECTION
A. The Contractor shall notify the Contracting Officer (CO) at least 5 calendar days prior to picking up or returning Government-furnished materials.
1. The Contractor and the CO shall jointly inspect all materials during the loading operation at the storage area.
1.3 LIABILITY
A. The Contractor's liability for Government-furnished material shall start at the time he accepts the materials at the storage area, and shall terminate upon completion and final acceptance of the work.
1. It shall be implied that the Contractor has accepted Government-furnished from the storage area to the worksite.
2. The Contractor shall provide all labor, equipment, and incidental necessary materials between the worksite and specified storage area.
1.4 REPLACEMENT AND/OR SUPPLEMENTAL MATERIALS
A. Any defective materials discovered prior to the Contractor's acceptance of the materials will be replaced by the Government.
B. If the quantity of Government-furnished material accepted by the Contractor is insufficient to complete the specified work, supplemental materials complying with these specifications shall be provided by the Government at no expense to the Contractor.
C. The Government shall not replace any materials that, in the opinion of the CO, are damaged or lost due to the Contractor's negligence after the Contractor accepts the materials. Such materials shall be replaced at the Contractor's expense.
1.5 SURPLUS MATERIAL
A. After completion and final acceptance of the work, surplus Government-furnished materials shall be returned to the specified storage area in the same mechanical and physical condition as originally accepted.
GOVERNMENT FURNISHED MATERIALS (GFM) SECTION 01550-2
B. Damaged surplus materials shall be replaced at the Contractor's expense.
C. The Contractor's liability for surplus materials shall terminate upon unloading and storage at the storage area.
PART 2 - PRODUCTS
2.1 GOVERNMENT-FURNISHED MATERIALS
A. Government-furnished materials shall be limited to:
1. Submersible Well Pump
a. Franklin Electric Model 2243019204
b. 2 HP
c. 230 V
d. 10 Amp
e. 3450 RPM
f. 3 wire
g. Single phase
h. 1.5kW
2. Pump Control Box
a. Franklin Electric Standard Model 2823018110
b. 2 HP
c. 1.5kW
d. 230 V
e. 60 Hz
3. Lock Cylinder: Forest Service keyed cylinder for a Yale Lock.
B. All items will be removed from their current installation on a stand adjacent to the wellhead and reinstalled by the contractor in the new utility building. The Yale Cylinder will be provided to the contractor for installation in the utility building lockset upon request.
PART 3 - EXECUTION
3.1 GENERAL
A. Installation and testing of Government-furnished materials shall comply with the applicable contract specifications covering work requiring the use of such materials.
END OF SECTION 015500
SELECTIVE DEMOLITION SECTION 017320- 1
PINE CANYON WATER SYSTEM UPGRADES
SECTION 017320 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes demolition and removal of the following:
1. Removal and/or decommission in place in accordance with Santa Barbara County regulation, of all waterlines being replaced with new line.
2. Removal of waterline, meter, valving and appurtenances existing at the wellhead and water storage tanks.
3. Removal of electrical line, 30 amp power service disconnect, and submersible pump motor protection and the stand supporting these items adjacent to the wellhead.
4. Salvage of pump control panel from stand adjacent to well head and reinstallation within new utility building.
5. Any patches and repairs required.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.
1.4 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI A10.6 and NFPA 241.
1.5 PROJECT CONDITIONS
A. Government will occupy buildings onsite during this construction. Conduct selective demolition to limit impact to Government operations onsite. Provide not less than 72 hours' notice to CO of activities that will affect Government operations.
B. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.
SELECTIVE DEMOLITION SECTION 017320- 2
1. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Contracting Officer (CO).
C. Storage or sale of removed items or materials on-site will not be permitted.
1.6 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials damaged during selective demolition, by methods and with materials so as not to void existing warranties.
PART 2 - PRODUCTS
2.1 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.
2. Use materials whose installed performance equals or surpasses that of existing materials.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped.
B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.
3.2 PATCHING AND REPAIRS
A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.
B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.
D. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall
SELECTIVE DEMOLITION SECTION 017320- 3
coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
E. Ceilings: Patch, repair, or rehang existing ceilings as necessary to provide an even-plane surface of uniform appearance.
3.3 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Burning: Do not burn demolished materials.
C. Disposal: Transport demolished materials off Government property and legally dispose of them.
END OF SECTION 017320
WATER DISTRIBUTION SYSTEMS 221100- 1
PINE CANYON WATER SYSTEM UPGRADES
SECTION 221100 - WATER DISTRIBUTION SYSTEMS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section shall consist of furnishing and installing the following:
1. Potable water distribution pipe and fittings.
2. Valves, valve boxes and appurtenances.
B. This Section shall also include the flushing, testing and disinfection of waterlines.
C. Related Sections include the following:.
1. Section 312000 “Earthwork.”
1.2 DEFINITIONS
A. HDPE: High Density Polyethylene plastic.
B. PVC: Polyvinyl Chloride
C. GSP: Galvanized Steel Pipe
D. NSF: Formerly National Sanitation Foundation, now NSF International, a global public health and safety organization
1.3 SUBMITTALS
A. Product Data: For the following:
1. Pipe and fittings.
2. Valves, valve boxes, operating wrenches.
B. Plan for disposal of water used for testing and disinfection of waterlines.
C. Water System Operations and Maintenance Manual.
1.4 QUALITY ASSURANCE
A. All work is to be completed according to applicable Federal, State and Local codes. This work includes, but is not limited to, materials, installation, testing and disinfection.
B. Piping materials shall bear label, stamp, or other markings of specified testing agency.
C. NSF Compliance:
1. Comply with NSF 14 for plastic potable-water-service piping. Include marking "NSF-pw" on piping.
WATER DISTRIBUTION SYSTEMS 221100- 2
2. Comply with NSF 61 Annex G for materials for water-service piping and specialties for domestic water. All pipes, fittings, fixtures, solder and flux shall meet the 0.25% maximum lead content rules for all wetted components.
1.5 MINIMUM SYSTEM REQUIREMENTS
A. Unless otherwise noted, the minimum working pressure for piping and specialties shall be 160 psig.
1.6 DELIVERY, STORAGE AND HANDLING
A. Deliver piping with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe-end damage and to prevent entrance of dirt, debris, and moisture.
B. Protect stored piping from moisture and dirt. Elevate above grade.
C. Protect flanges, fittings, and specialties from moisture and dirt.
D. Store plastic piping protected from direct sunlight. Support to prevent sagging and bending.
1.7 PROJECT CONDITIONS
A. Existing Utilities: Do not interrupt utilities serving facilities occupied by the Government or others unless permitted under the following conditions:
1. Notify the Contracting Officer not less than three days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without the Contracting Officer’s written permission.
3. Construction shall not interfere in any way with the city water system.
1.8 COORDINATION
A. Coordinate connection to existing waterlines with Contracting Officer.
B. Verify piping materials, sizes, entry locations and pressure requirements are compatible with connection point.
C. Contractor shall coordinate work with the County and State as necessary.
D. Coordinate other utility impacts.
1.9 MEASUREMENT AND PAYMENT
A. Payment will be as listed for the following items:
1. 221100-A, 1.5” HDPE Waterline Installation
2. 221100-B, 1.5” HDPE Curb Valve and Box Installation
WATER DISTRIBUTION SYSTEMS 221100- 3
3. 221100-C, 3” HDPE Waterline Installation
4. 221100-D, 3” HDPE Curb Valve and Box Installation
5. 221100-E, 3” HDPE Waterline & 1.5” HDPE Waterline Installation in Shared
Trench
6. 221103-A, New Waterline Tie In to Existing Tanks
7. 221103-B, New Service Connection
8. 221103-C, Daylight Drain Assembly Installation
9. 221103-F, Hydrant Assembly Installation
10. 221103-G, Water Tanker Fill Station Assembly Installation
PART 2 - PRODUCTS
2.1 GENERAL
A. All waterlines, pipes, and fittings shall be new and unused, of the type, pressure rating or class, and size specified and as shown on the Drawings.
2.2 WATER DISTRIBUTION PIPES AND FITTINGS AND CONDUIT
A. PVC (For pipe sleeves and conduit only): ASTM D 1785, Schedule 40; solvent-cemented joints.
1. Solvent Cement: ASTM D 2564.
2. Socket Fittings: PVC, Schedule 40, ASTM D 2467.
B. Galvanized Steel (For hydrant, tanker fill station, daylight drain installation, wellhead upgrades, and within 10’ of utility building): ASTM A53, Schedule 40, threaded ends meeting ASME B1.20.1.
1. Fittings: Threaded, ASTM A 338.
2.3 PIPING SPECIALTIES
A. HDPE (For all new supply and distribution piping):
1. Pipe, AWWA C901:
a. Material Designation: PE 4710 resin
b. Material Classification: ASTM D1248
c. Minimum Cell Classification: ASTM D 3350, 445574C
d. Dimension Ratio and Minimum Pressure Rating: DR 11, 160 psig
e. NSF-61 Listed
2. Fittings:
a. Molded HDPE Fittings: ASTM D 3350, PE 4710 resin, butt-fusion type, made to match HDPE pipe dimensions and class.
b. Insert Fittings: Not allowed.
c. Transition Fittings to non-HDPE Pipe: Approved by HDPE pipe manufacturer. Compression-type fittings are not allowed.
WATER DISTRIBUTION SYSTEMS 221100- 4
d. HDPE transitions to steel line shall be welded/threaded.
3. Pipe larger than 2-inch diameter: provide in 40’ lengths rather than rolls.
2.4 WATER VALVES, BOXES, and APPURTENANCES
A. Valves: Valves shall be the same nominal size as the line in which they are installed or as indicated on the Drawings.
1. Valve Operating Rods: Steel, tee-handle, stem of length to operate deepest buried valve, and end socket to match curb valve. Furnish one valve operating wrench with every five (or fraction thereof) curb boxes installed, as indicated on the Drawings.
B. Poly Valves (All Buried Valves)
1. NSF 61 Certified. Potable water systems only. Valves used in gas distribution are not permitted.
2. PE4710 resin.
3. Opening (Bore): Full port.
4. Ball lubricant shall be optimized for potable water applications.
5. Dimension Ratio and Pressure Rating: Same as pipe in which the valve is installed
6. Model: Polyvalve “Poly-Water II NSF” Valves, as manufactured by Polyvalve
LLC, an Andronaco Industries Company., or an approved equal.
a. Body: Polyethylene
b. Adapter: Polypropylene
c. Groundwater Seal: Neoprene
d. Seat and Stem Seal: EPDM
e. Ball: Acetal
f. Seat Retainer: Acetal
g. Stem: Stainless Steel
h. End Configuration: Butt fusion
i. Operator: 2” square nut
C. VALVE BOXES
1. Valve boxes shall be furnished for all buried valves sized to fit the entire assembly.
Valve boxes shall consist of galvanized steel, and lockable lid. Contractor may fabricate a box and lid system, consistent with project plans, in lieu of a commercial box.
a. Cover shall receive a 2” padlock.
b. Cover shall be easily removeable by hand.
2. Insulation of Valve Boxes: 1” Thick closed cell extruded polystyrene foam board insulation. Cut to fit tightly and attached securely to underside of lid, and placed around box exterior. Styrofoam Highload 40 Extruded Polystyrene Insulation as manufactured by Dow Chemical Company or approved equal.
WATER DISTRIBUTION SYSTEMS 221100- 5
a. Thermal Resistance, per inch, ASTM C518, C177, R-value min: 5.0
b. Compressive Strength, ASTM D1621, psi, min: 40
c. Water Absorption, ASTM C272, % by volume, 24 Hr max: 0.3
d. Water Vapor Permeance, ASTM E96, perms: 1.0
e. Max Use Temp, deg F: 165
f. Coeff. Linear Therm. Expansion, ASTM D696, in/in°F: 3.5X10-5
g. Flexural Strength, ASTM C203, psi, min: 60
h. Compressive Modulus. ASTM D 1621, psi, typical: 1,400
i. Complies with ASTM C578, Type: VI
D. TOOLS FOR OPENING VALVES AND BOXES
1. The Contractor shall supply two valve operating rods for operation of each type of product furnished.
2.5 END SEALS FOR SLEEVES
A. Design: With ASTM C443 compliant gaskets.
B. Model: Link-Seal, as manufactured by Pipeline Seal & Insulator, Inc. or an approved equal.
2.6 LOCATING WIRE
A. Nonconductive pipe shall have a 10 AWG copper tracer wire with blue PE-30 insulation.
2.7 OPERATION AND MAINTENANCE MANUAL
A. The Contractor shall furnish three sets of instructions for operating and maintaining the complete water system, including location of valves and other key system features, testing requirements for any backflow assemblies, parts list and parts order form, etc.
PART 3 - EXECUTION
3.1 EARTHWORK
A. Refer to Section 312000 “Earthwork” for excavating, trenching, bedding, and backfilling.
3.2 PIPING INSTALLATION
A. Construct the water system to the lines and grades shown or established in the field.
B. Stake locations of waterlines as shown on the Drawings. Waterline location shall be approved by the Contracting Officer before installation.
WATER DISTRIBUTION SYSTEMS 221100- 6
C. All pipe, fittings, and appurtenances shall be handled and installed in strict conformance to the manufacturer’s recommendations.
D. Drains, valves, and other regulating and controlling devices shall be installed in the line where called for on the drawings.
E. The interior of all pipe, fittings, and other accessories shall be kept as free as possible from dirt and foreign matter at all times. Each piece of line as it is laid shall be cleaned of all debris. When the pipeline has become dirty on the inside during shipment or storage, it shall be swabbed out by drawing a damp swab through the line before placing in trench. Care shall be exercised to keep all joining surfaces clean. Any pipe with contaminated or damaged joining surfaces, which cannot be satisfactorily cleaned or repaired, shall be discarded. Under no circumstances shall pipe be installed in water, and no pipe shall be installed when trench conditions or the weather is unsuitable for such work. At all times when work is not in progress, all open ends of the pipe and fittings shall be securely closed to the satisfaction of the Contracting Officer so that no trench water, rodents, earth, or other substance will enter the pipe or fittings.
F. Any section of pipe already installed and found to be defective shall be removed and replaced with new pipe at the Contractor’s expense.
G. Water and Non-Potable/Sewer Line Crossings
1. Potable and NPWL lines shall never be installed in the same trench.
2. If a new line crosses below an existing line, the existing line shall be supported to prevent settling.
3. Where waterlines intersect NPWLs or are within 10 horizontal feet of NPWLs, the following applies:
a. At least one of the pipes (either the waterline or NPWL) shall be constructed or reconstructed with 200 psi pipe or encased in a continuous sleeve with same rating. At crossing, extend 200 psi pipe or sleeve for a distance of 10 feet perpendicular distance from each side of the waterline. The waterline and NPWL pipes or sleeves shall be centered at the crossing so that the joints will be an equal distance and as far as possible from the crossing.
1) Sleeves: Nominal sleeve diameter to be at least 3 inches larger than nominal diameter of pipe to be encased. Install end seals in annular space at each end of sleeves.
2) In lieu of constructing or reconstructing the NPWL with pipe conforming to waterline requirements, the NPWL may be encased in concrete at least 6 inches thick around the pipe measured at the bell, for 10 feet each side of the waterline.
b. Construct according to applicable federal, state and local regulations which the Contractor is responsible for obtaining and following.
c. Where applicable, state and local regulations supersede the above requirements.
WATER DISTRIBUTION SYSTEMS 221100- 7
H. Culvert Crossings: Where waterline crosses a road culvert, adjust grade of waterline to provide a minimum of 12 inches of separation between the waterline and culvert, maintaining slope of waterline to drain.
I. A minimum of one-foot separation shall be maintained between electric and waterlines in the same trench. Unless the electric conductors are in conduit the waterline shall be a minimum of one foot below the electric conductors.
J. Cutting and Handling of Pipe
1. Cutting of pipe for closure pieces or for other reasons shall be done in a neat manner by methods, which will not damage the pipe. The pipe and fittings shall be handled in such a manner as to insure delivery and final placement in good, undamaged condition. Particular care shall be exercised not to injure the pipe surfaces or coatings. Damaged pipe shall not be used in the work.
K. Laying Pipe
1. No pipe shall be placed in the trench until the Contracting Officer has approved the trench and bedding.
2. Do not drop pipe into trench. Ensure installation procedures meet the manufacturer’s requirements.
3. Pipes shall be placed true to the lines and grades shown on the Drawings and as specified.
4. Each section of the pipe shall rest upon the pipe bed for the full length of its barrel.
5. Backfill the pipe within 24 hours after installing the pipe in the trench, leaving the joints and one foot of pipe on each side of each joint exposed until testing is complete.
6. When work is not in progress, securely close open ends of pipe and fittings.
7. When high density polyethylene or solvent weld joint pipe is used, it shall be weaved in the trench to provide horizontal slack in the line for expansion and contraction.
8. High density polyethylene pipe shall be allowed to cool to within 20ºF of the shaded trench bottom temperature before backfilling.
9. When pipes are installed in a structure or utility box, they shall be adequately supported.
10. Use proper fittings in order to follow the required line and grades and to avoid excessive curvature. Deflections from a straight line or grade, as required by vertical curves, horizontal curves, or offsets, shall not exceed the manufacturer's recommended maximum joint deflection or curvature for their pipe.
11. When more than one pipeline is in the same trench, the pipes shall be separated by at least eight horizontal inches, or as shown on the Drawings.
12. Bends that result in joint tension or permanent pipe deformation are prohibited.
13. Pipelines may be relocated slightly, if necessary, to avoid existing obstacles.
However, slopes shall be maintained to avoid sags, and mid-line low points.
L. Branch Connections
1. Branch connections to the main shall be made with tees.
WATER DISTRIBUTION SYSTEMS 221100- 8
2. Horizontal tees for waterline laterals shall not be permitted. The branch side of tees shall be up when drainage is toward the tee, and down when drainage is away from the tee.
3. Waterline tees shall be the same diameter as the largest pipe connected to the tee.
M. Pipe Joints
1. Joints shall be made, using jointing materials and applied with the proper accessories, in accordance with the manufacturer's instructions. Completed joints shall be watertight, and capable of passing the required hydrostatic testing. If pipe and fittings are assembled with a lubricant, it must be nontoxic.
2. Dissimilar Joints: Connections between two dissimilar pipes or fittings shall be installed in manner recommended by the pipe manufacturer and approved by the Contracting Officer. Use adapters compatible with both piping materials, outer diameters and system working pressure.
3. HDPE Heat-Fusion Joints
a. According to ASTM D 2657 and piping manufacturer's written instructions.
b. The joining method shall be butt fusion method and shall be performed in accordance with the pipe manufacturer's recommendations. Butt fusion equipment used in the joining procedures shall be capable of meeting all conditions recommended by the pipe manufacturer, including but not limited to, temperature requirements, alignment, and fusion pressures.
c. Personnel trained in butt fusion techniques by the manufacturer of the pipe, shall supervise or perform butt fusion operations.
d. Butt fusion shall be performed between pipe ends or pipe ends and fitting and valve outlets, of like outside diameter and wall thickness, SDR or DR.
Butt fusion joining between same diameters but unlike wall thickness shall not be permitted. Transitions between unlike wall thickness shall be made with a transition nipple (a short length of the heavier wall pipe with one end machined to the lighter wall) or by mechanical means.
e. Branch connections to the main shall be made with polyethylene fittings, and butt fused.
f. Bent Strap Test: On each day that butt fusions are to be made, perform a “Bent Strap Test.” The first fusion of the day shall be a trial fusion. The trial fusion shall be allowed to cool completely, and then fusion test straps shall be cut out. The test strap shall be 12" (min) or 30 times the wall thickness in length with the fusion in the center, and 1" (min) or 1.5 times the wall thickness in width. Bend the test strap until the ends of the strap touch. If the fusion fails at the joint, a new trial fusion shall be made, cooled completely and tested. Butt fusion of pipe to be installed shall not commence until a trial fusion has passed the bent strap test.
4. Plastic Piping Solvent-Cemented Joints: Clean and dry joining surfaces. Join pipe and fittings according to the following:
WATER DISTRIBUTION SYSTEMS 221100- 9
a. PVC Pressure Piping: Join schedule number ASTM D 1785, PVC pipe and PVC socket fittings according to ASTM D 2672. Join other-than-schedule-number PVC pipe and socket fittings according to ASTM D 2855.
5. Threaded Metal Joints:
a. Thread pipes with tapered pipe threads according to ASME B1.20.1, apply tape or joint compound, and apply wrench to fitting and valve ends into which pipes are being threaded.
b. Exposed threaded pipe joints on galvanized steel pipe shall be painted with mastic following the manufacturer’s application procedures.
c. Field cut ends shall be squared off by grinding or filing; ends shall be reamed with all chips and flakes removed.
d. Field cut threads or machined joints shall be made with sharp tools to sharp finished ends.
3.3 IDENTIFICATION
A. According to Section 312000 “Earthwork.”
B. Wrap all buried, non-metallic, nonperforated piping with locating wire.
C. Use detectable warning tape over piping and at outside edges of underground structures.
3.4 VALVE INSTALLATION
A. Valves shall be installed in accordance with manufacturer’s requirements and recommendations and good trade practices.
B. Valves shall be installed at the required locations with the joints centered, and valve stems plumb and straight. Valves shall be installed so as to be easily accessible for operation and service. Valves shall be set and joined to pipe and supported, as recommended by the manufacturer or as needed to prevent stress on the valve, fitting, or pipe.
C. Test all valves and appurtenances for proper operating adjustments and settings, and for freedom from vibration, binding, scraping, and other defects.
3.5 PIPE SLEEVE INSTALLATION
A. End Seals
1. The annular space between the sleeve or casing and the installed pipe shall be plugged with an end seal to provide a positive seal against a hydrostatic head and prevent soil from entering the space.
3.6 DAYLIGHT DRAINS
A. Transition from water system piping to galvanized steel pipe 10-feet from atmospheric outlet of daylight drain.
WATER DISTRIBUTION SYSTEMS 221100- 10
B. Install insect screens on the atmospheric outlet of daylight drains. Attach insect screens to pipe as shown in the drawings.
C. Minimum grade of slope of drain shall be 1%.
D. Place riprap securely around outlet with a minimum 12” air gap.
3.7 HYDROSTATIC TESTING
A. General
1. The Contractor shall conduct pressure and leakage tests on all newly constructed portions of the water system, including water mains, service lines, fittings, valves, and hydrants. New waterlines that are extensions or modifications of an existing water system shall be tested at the test pressure specified here unless the Contracting Officer specifies another pressure. Pneumatic testing will not be allowed.
2. The contractor shall ensure that any appurtenance attached to the pipeline at the time of testing is rated to withstand the pressures that will exist during testing.
3. Conduct piping tests before joints are covered and after thrust blocks, if required, have hardened sufficiently. Joints shall remain uncovered until testing is completed satisfactorily.
4. The Contractor shall furnish the pump, pipe, gauge, measuring device, connections, and all other necessary equipment, and shall furnish the necessary personnel to conduct the tests. All equipment, gauges, and attachments shall be subject to approval by the Contracting Officer.
5. The Contracting Officer shall be present during the testing period.
6. Waterlines shall be tested in sections not to exceed 2,000 ft in length or a maximum pressure differential of 30 psi in the test section.
7. No paints, asphalts, tars, enamels, or other types of pipe compounds shall be used to eliminate leaks.
B. Pressure and Leakage Test
1. The test pressure shall:
a. Equal at least 125% of the normal working pressure at the highest elevation of the test but not exceed 160 psi at any point being tested.
b. Not exceed the thrust restraint design pressures.
c. Not vary by more than +/- 5 psi from the established test pressure.
d. Not exceed twice the rated pressure of valves when the test section includes closed valves.
e. Be not less than 100 psi for all piping within buildings.
2. Pressure Test Procedure
a. Equipment: The test pressure shall be applied by means of a pump connected to the pipe in a manner satisfactory to the Contracting Officer.
WATER DISTRIBUTION SYSTEMS 221100- 11
b. Preparation: Fill pipeline 24 hours before testing. Use only potable water.
Each valved section of pipeline shall be slowly filled with water and all air shall be expelled from the pipeline. Apply test pressure to stabilize system.
c. Pressurization:
1) Increase pressure in 50-psig increments and inspect each joint between increments.
2) Hold at test pressure for 1 hour.
3) Decrease to 0 psig.
4) Slowly increase again to test pressure and hold for 1 more hour. If the test pressure cannot be sustained within +/- 5 psi during this time, then the system will be determined to have leakage.
5) Leakage shall be verified by the Contractor and the Contracting Officer.
6) Locate and repair leaking joints with new materials and repeat test until leakage is within allowed limits. All visible leaks are to be repaired regardless of the amount of leakage.
d. Examination: All exposed pipe, fittings, valves, and joints shall be carefully examined. Any cracked or defective pipe, fitting, or valve discovered shall be repaired or replaced by the Contractor at his own expense with new material and the test repeated until satisfactory to the Contracting Officer.
3. Results
a. The Contractor shall furnish a written report to the Contracting Officer describing the results of each test. The report must identify the specific portions of the pipeline tested, the pressure, the duration of the tests, and the amount of leakage.
3.8 CLEANING AND DISINFECTION
A. Clean and disinfect water-distribution piping as follows:
1. Purge new water-distribution piping systems and parts of existing systems that have been altered, extended, or repaired before use.
2. Use purging and disinfecting procedure prescribed by authorities having jurisdiction or, if method is not prescribed by authorities having jurisdiction, use procedure described in AWWA C651 or as described below:
a. Flushing Pipelines
1) After the pressure and leakage testing has been completed, all water pipes shall be thoroughly flushed.
2) Flushing shall remove all debris from the pipeline, including HDPE pipe shavings, gravel and any other material that may have accidentally entered the pipeline during construction.
3) Remove all self-closing faucets from hydrants before flushing lines.
Failure to do so will likely clog the internal parts of the faucet.
WATER DISTRIBUTION SYSTEMS 221100- 12
4) Minimum velocities must be obtained in all mainlines, laterals and drainlines.
5) Ensure flushing outlets have adequate drainage and no damage or erosion will occur from the flushing process. Install hoses and/or pipe extensions if necessary.
TABLE 1
Required Flow in Gallons per Minute (GPM) to provide 2.5 feet per second
Flushing Velocity
Type of Pipe
Nominal Pipe Size (inches)
HDPE
(SDR 11)
PVC
(160 psi)
Galv. Steel (Schedule 40)
1 7 9 7 1 ¼ 11 15 12 1 ½ 14 19 16 2 22 30 27
2 ½ - 44 38 3 49 64 58
b. Requirement of Chlorination
1) Pipelines: After flushing, all new waterlines and repaired portions of, or extensions to, existing waterlines shall be disinfected by chlorination. Chlorination shall provide a minimum of 25 mg/l residual after 24 hours contact in the system. This may be expected with an application of 50 mg/l, although some conditions may require more.
The entire system including the storage tank or spring box shall be filled with the disinfecting solution. All taps, hydrants, and other outlets shall be opened and left open until chlorine is noticeable by odor or testing in the water coming from each. Immediately close taps, hydrants, and other outlets.
This is the start of the file's text. The full file is on GovTribe.