This document outlines a federal construction contract opportunity for water system upgrades at the Pine Canyon Water System within the Los Padres National Forest. The project involves base construction including well head upgrades, well casing liner installation, permit coordination, installation of a precast concrete utility building, and associated plumbing and electrical work. An optional scope of work includes installing HDPE and PVC waterlines, curb valves and boxes, new service connections, and a daylight drain. The estimated construction value is between $250,000 and $500,000. The solicitation is a total small business set aside issued by the Department of Agriculture Forest Service. The proposal due date is July 7, 2022, and all requests for information must be submitted to the contracting officer by that date. A pre-proposal site visit will not be held but the project site is open to the public for inspection.

View the file

Other files

File Type Posted
127EAW22R0055.pdf PDF
5. Forest Service Supplemental Specifications.pdf PDF
4. Pine Canyon Water System Plans - 10 June.pdf PDF
1. Statement of Work.pdf PDF
7. RFI Form.docx DOCX document
2. Fire Plan.pdf PDF
6. Davis-Bacon Act WD # CA20220014.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
11900
Mobilization/Demobilization
1
LS
$___________
$___________
221120-A
Well Head Upgrades
1
LS
$___________
$___________
221120-B
Well Casing Liner Installation
271.00
LF
$___________
$___________
221103-D
Well Modification and Water System Construction Permit Coordination
1.00
EA
$___________
$___________
13340-A
Precast Concrete Utility Building Installation, Site prep, utility rough in w/in 10'
1
LS
$___________
$___________
221103-E
Utility Building Plumbing
1
LS
$___________
$___________
260500-A
Utility Building Feeder
1
LS
$___________
$___________
260500-B
Utility Building Electrical
1
LS
$___________
$___________
BASE TOTAL:
$___________

B.1 SCHEDULE OF ITEMS – OPTION 1

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
221100-A
1.5" HDPE Waterline Installation
140.00
LF
$___________
$___________
221100-B
1.5" Curb Valve and Box Installation
4.00
EA
$___________
$___________
221100-C
3" HDPE Waterline Installation
80.00
LF
$___________
$___________
221100-D
3" Curb Valve and Box Installation
7.00
EA
$___________
$___________
221103-B
New Service Connection
2.00
EA
$___________
$___________
221103-C
Daylight Drain Installation
1.00
EA
$___________
$___________
321216-A
Asphalt Paving Resurfacing
750.00
SF
$___________
$___________
OPTION 1 TOTAL:
$___________
BASE + OPTION 1 TOTAL:
$___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Company Name:
POC & Title:
Email:
Phone Number:
UEI Number:
Tax ID: