5-Attachment D 2026 Standard Specifications Pipe Liner (1) (2).pdf

PDF 149 KB Posted

Attached to
UDOT Pipe reline and Segmental Thermoplastic Liners
Solicitation number
UDOT260127CN
Issued by
Utah

About this file

This is a Standard Specifications document for drainage pipe liner installation issued by the Utah Department of Transportation (UDOT) under Solicitation #UDOT260127CN, detailing technical requirements for pipe rehabilitation methods. The specification outlines four primary drainage pipe liner types: polyvinyl chloride (PVC) fold-and-form liners limited to 30 inches maximum diameter, cured-in-place pipe (CIPP) liners with minimum flexural modulus of 250,000 PSI and flexural strength of 4,500 PSI, segmental thermoplastic liners referencing AASHTO M 326 standards, and segmental metal pipe liners. The document establishes comprehensive submittal requirements including work area documentation, pipe preparation procedures, installation methods, product data, engineering calculations, grout mix designs, and trial batch test data. Installation procedures mandate host pipe cleaning using methods that prevent damage to the pipe or surrounding features, remote closed-circuit television (CCTV) inspection for pipes under 48 inches in diameter, and visual inspection for larger diameter pipes. For PVC fold-and-form and CIPP liners, contractors must follow ASTM installation standards with manufacturer-recommended curing and relaxation periods. For segmental thermoplastic and metal liners, contractors must construct bulkheads at pipe ends, allow 24 hours for pipe temperature equalization, fill the entire annular space with grout, and adhere to maximum grouting pressures specified by manufacturers.

The specification requires grout to be a cementitious low-density mixture with compressive strength between 100 and 400 PSI, fluidity to completely fill voids without segregation, fly ash not exceeding 30 percent of cementitious material, and shrinkage not exceeding 1 percent by volume. All pipe liners must meet or exceed AASHTO HL-93 or interstate alternate loading according to AASHTO LRFD Bridge Design Specifications, with the host pipe assumed to be fully deteriorated and unable to carry loads. The document references multiple ASTM and AASHTO standards governing material properties, installation procedures, and curing methods for each liner type. Work must be performed within UDOT right-of-way unless written property owner agreements are in place, and all material removed during cleaning must be collected and properly disposed of. The contract is structured as a potential multiple 5-year agreement with the lowest responsive and responsible bidder, requiring bidders to submit comprehensive documentation demonstrating compliance with all stated specifications and technical requirements outlined in the 2026 Standard Specifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Drainage Pipe Liner 02618 – Page 1 of 7

2026 Standard Specifications Latest Revision: December 7, 2023

SECTION 02618

DRAINAGE PIPE LINER

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Drainage lining methods such as polyvinyl chloride (PVC) fold-and-form, cured in place pipe (CIPP), and segmental thermoplastic and metal pipe.

1.2 RELATED SECTIONS

A. Section 02610: Drainage Pipe

1.3 REFERENCES

A. AASHTO M 326: Polyethylene (PE) Liner Pipe, 300- to 1600-mm Diameter, Based on Controlled Outside Diameter

B. AASHTO LRFD Bridge Design Specifications

C. ASTM D 790: Flexural Properties of Unreinforced and Reinforced Plastics and Electrical Insulating Materials

D. ASTM D 1784: Rigid Poly (Vinyl Chloride) (PVC) Compounds and

Chlorinated Poly (Vinyl Chloride) (CPVC) Compounds

E. ASTM D 5813: Cured-In-Place Thermosetting Resin Sewer Piping

Systems

F. ASTM F 1216: Rehabilitation of Existing Pipelines and Conduits by the

Inversion and Curing of a Resin-Impregnated Tube

G. ASTM F 1504: Folded Poly (Vinyl Chloride) (PVC) Pipe for Existing

Sewer and Conduit Rehabilitation

H. ASTM F 1743: Rehabilitation of Existing Pipelines and Conduits by

Pulled-in-Place Installation of Cured-in-Place Thermosetting Resin Pipe

(CIPP)

I. ASTM F 1867: Installation of Folded/Formed Poly (Vinyl Chloride) (PVC)

Pipe Type A for Existing Sewer and Conduit Rehabilitation https://drive.google.com/file/d/1vdUPLr3ZOwyA0rZurtU2ydsx5qEzPfSn/view?usp=drive_link

02618 – Page 2 of 7

2026 Standard Specifications Latest Revision: December 7, 2023

J. ASTM F 1871: Folded/Formed Poly (Vinyl Chloride) Pipe Type A for Existing Sewer and Conduit Rehabilitation

K. ASTM F 1947: Installation of Folded Poly (Vinyl Chloride) (PVC) Pipe into

Existing Sewers and Conduits

L. ASTM F 2019: Rehabilitation of Existing Pipelines and Conduits by the

Pulled in Place Installation of Glass Reinforced Plastic (GRP) Cured-in- Place Thermosetting Resin Pipe (CIPP) Using the UV-Light Curing Method

1.4 DEFINITIONS Not Used

1.5 SUBMITTALS

A. Include the following information into a single submittal for each drainage pipe to be lined, for review. Use the naming convention used in the plans for each location. Provide the seal of a Professional Engineer (PE) or Professional Structural Engineer (SE) for engineering calculations. Divide information into the sections listed below.

1. Work Area

a. Locations and dimensions of any temporary access roads

b. Locations and dimensions of pipe liner assembly and insertion area “footprints” or area of disturbance.

c. Distance of insertion footprint from the traveled way

d. Amount of time the footprint will be exposed

e. Shoring method when excavation is proposed

f. Written access agreements from property owners when work area is outside Department Right of Way

2. Preparation

a. Host pipe cleaning

b. Management of flows in the host pipe

c. Initial pipe inspection

3. Installation

a. Method of pipe liner installation and finishing

b. Bulkhead and grouting details for segmental thermoplastic and metal liner

c. Curing method identifying required curing times, temperatures, and pressures

d. Any potential for producing contaminant concentrations in excess of surface water quality standards or ambient groundwater quality standards, as applicable

e. Control and disposal of any contaminants from materials or installation methods during and after installation

f. Final pipe inspection

02618 – Page 3 of 7

2026 Standard Specifications Latest Revision: December 7, 2023

4. Product Data

a. Engineering calculations and recommended size and wall thickness of pipe liner for products not specified in Section 02610.

1) The host pipe is considered to be fully deteriorated and unable to carry loads.

2) Meet or exceed AASHTO HL-93 or interstate alternate loading according to AASHTO LRFD Bridge Design Specifications and interim specifications for pipe liner load capacity.

b. Maximum allowable external grouting pressure on pipe liner and joints for segmental thermoplastic and metal liners.

5. Certificate of compliance.

6. Mix Designs

a. Grout Mix design

b. Trial batch test data

PART 2 PRODUCTS

2.1 PVC FOLD-AND-FORM LINER

A. PVC resin manufactured from virgin materials containing no fillers.

1. Meet or exceed the physical property requirements in ASTM F 1504 or ASTM F 1871 for the cell classification as defined in ASTM D 1784.

B. Do not use greater than 30 inch diameter.

2.2 CIPP LINER

A. Fabric tube consisting of one or more layers of absorbent non-woven felt fabric, felt/fiberglass, or fiberglass meeting the requirements of ASTM D 5813 and ASTM F 1216, ASTM F 1743, or ASTM F 2019.

1. Use a CIPP liner that meets or exceeds the following physical properties outlined in Table 1.

Table 1

Minimum Physical Properties

Property Test Method

ASTM Value Initial Flexural Modulus ASTM D 790 250,000 PSI @73º F

Flexural Strength ASTM D 790 4,500 PSI @73º F

02618 – Page 4 of 7

2026 Standard Specifications Latest Revision: December 7, 2023

2. Use a sufficient quantity of resin for impregnation to fill the volume of air voids in the pipe liner with additional allowance for polymerization and for any migration of resin into the cracks and joints in the host pipe.

a. Color the resin with a pigment compatible with the resin system as specified by the resin manufacturer.

2.3 SEGMENTAL THERMOPLASTIC LINER

A. Solid wall polyethylene pipe. Refer to AASHTO M 326.

B. Profile wall thermoplastic pipe. Refer to Section 02610.

2.4 SEGMENTAL METAL LINER

A. Metal Pipe. Refer to Section 02610.

2.5 GROUT

A. Cementitious low density grout mixture having the following characteristics.

1. Suitable with the site conditions, construction methods, and pipe liner structural capacity.

2. Compressive strength between 100 and 400 psi

a. Determine strength from trial batches at 28 days

3. Fluidity to completely fill voids and the annular space between the host pipe and the pipe liner without segregating

4. Fly ash not to exceed 30 percent of cementitious material

5. Shrinkage not to exceed 1 percent by volume

PART 3 EXECUTION

3.1 GENERAL

A. Furnish the type of drainage pipe liner shown with the following exception:

1. Select from any of the drainage pipe liner products listed in this

Section, Part 2 meeting the allowable pipe size reduction when no specific product is shown.

02618 – Page 5 of 7

2026 Standard Specifications Latest Revision: December 7, 2023

3.2 PREPARATION

A. General

1. Perform all work within the limits of the Department right of way unless written agreements are in place with adjacent property owners.

2. Provide adequate control of water in the host pipe when necessary.

a. Repair damage caused as a result of flow control or lack thereof.

3. Provide the necessary controls to prevent pollutants from being transported downstream.

B. Host Pipe Cleaning

1. Remove material to include sediment, rocks, and miscellaneous debris to inspection and install the pipe liner.

2. Use a cleaning method and tools that will not cause damage to the pipe or surrounding roadway features.

a. Notify the Engineer when cleaning could result in damage.

b. Do not cause erosion of surrounding areas from cleaning operations.

c. Minimize sediment from being transported downstream.

3. Collect and properly dispose of all material removed.

C. Host Pipe Inspection

1. Perform remote inspection for pipes with a nominal diameter less than 48 inches using a closed-circuit television (CCTV) crawler.

2. Perform a visual inspection for pipes with diameter greater than 48 inches.

3. Inspect the condition of the host pipe and the suitability of the pipe liner installation. Document and notify the Engineer of the following:

a. Collapsed or impassable sections of the pipe

b. Horizontal or vertical alignment deviations

c. Structural concerns

d. Loss of material surrounding the pipe exterior

e. Infiltration of water

f. Repairs required to perform the installation

D. Drainage Pipe Liner

1. Verify host pipe internal size and length before ordering pipe liner.

2. PVC fold-and-form and CIPP liner dimensions

a. Size the pipe liner to have an outside diameter that will tightly fit the inside of the host pipe.

02618 – Page 6 of 7

2026 Standard Specifications Latest Revision: December 7, 2023

b. Provide sufficient pipe liner length to continuously line the host pipe with no intermediate joints.

3. Segmental Thermoplastic and Metal liner dimensions

a. Size the pipe liner to have an outside dimension that will freely pass through the host pipe and accommodate grout placement.

b. Use only one type of pipe liner and joint system in any single host pipe.

3.3 INSTALLATION

A. General

1. Remove sediment and debris that might have accumulated after the initial cleaning immediately before installing the pipe liner.

2. Handle and install the pipe liner in a manner that will not cause damage to the pipe liner.

3. Provide a smooth finish and a tight seal between the pipe liner and the drainage structure walls at pipe penetrations.

4. Restore lateral and inlet connections.

5. Inspect the rehabilitated pipe upon completion and before acceptance by the Engineer.

a. Evaluate pipe liners that contain dry spots, wrinkles, delamination, holes, cracks, joint gaps, soft spots, blisters, or other defects.

B. PVC fold-and-form and CIPP Liner

1. Meet minimum installation requirements according to ASTM F

1867 or ASTM F 1947 for PVC fold-and form

2. Meet minimum installation requirements according to ASTM F

1216 or ASTM F 1743 for CIPP.

3. Follow the manufacturer’s recommended curing and relaxation period required to hold the pipe liner against the host pipe.

a. Provide sufficient gauges, monitoring devices, and tests to determine the effectiveness of the curing.

C. Segmental Thermoplastic and Metal Liner

1. Construct a bulkhead at each end of the host pipe to fully support the fluid thrust loads exerted by the placement of grout.

a. Vent bulkheads to allow release of trapped air as the grout flows into the annular space.

2. Provide a minimum of 24 hours for the pipe liner temperature to equalize within the host pipe before placing grout.

02618 – Page 7 of 7

2026 Standard Specifications Latest Revision: December 7, 2023

3. Fill the entire full length of annular space between the host pipe and the pipe liner with grout.

a. Provide sufficient gauges, monitoring devices, and tests to determine the effectiveness of the grout placement.

4. Do not exceed the pipe liner maximum specified grouting pressure.

a. Use a pumping unit with a pressure meter and valves capable of limiting grout pumping pressures to the maximum pressure recommended by the manufacturer at the end of the discharge pipe.

5. Place grout in lifts to avoid excessive buoyant forces or grouting pressures.

a. Allow each lift to cure sufficiently before proceeding with next lift.

6. Remove any internal braces or bands once the grout is sufficiently cured and before acceptance.

END OF SECTION