5-Attachment A - Bid Form.pdf
PDF 131 KB Posted
- Solicitation number
- 26-51
- Issued by
- Brazoria County, Texas
About this file
This is a bid form for Brazoria County, Texas, for the Quintana Beach Park Septic System, Electrical and Loop Road Improvements project (CSP #26-51). The project encompasses three primary scopes of work: site work items including RV concrete pad extensions, asphalt paving, concrete sidewalks, and site restoration; septic system items involving demolition of the existing septic tank system, decommissioning of existing septic beds, and installation of a proposed septic system; and electrical items including removal and replacement of 30-ampere RV pedestals, transformers, panels, wire, and conduit. The bid form contains 58 line items organized into general work, site work, septic system, electrical, and extra work categories, with quantities ranging from single units to thousands of linear feet or square yards. Additional options include four line item adds addressing alternative septic system configurations, RV concrete pad modifications, and asphalt overlay scenarios. The form requires bidders to provide unit costs and total item costs for all line items, with subtotals calculated for each work category and cumulative totals for the base bid and each add option.
The bid form does not specify pricing terms, response deadlines, bid due dates, site visit requirements, or bidder conference information within the document itself. Bidders are required to complete all cost fields for the lump sum items, unit price items, and extra work provisions, with particular attention to minimum bid requirements noted for pot holes ($500 each), machine excavation ($20 per cubic yard), hand excavation ($25 per cubic yard), and electrical modifications ($5,000 lump sum). The form structure allows for flexible project scope through the inclusion of line item adds, enabling the owner to select alternative construction approaches based on final bid evaluations and project requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CSP #26-51 BID FORM
BRAZORIA COUNTY QUINTANA BEACH PARK
SEPTIC SYSTEM, ELECTRICAL AND LOOP ROAD IMPROVEMENTS
ITEM
NO.
DESCRIPTION
MEAS.
UNIT
QUANTITY UNIT COST ITEM COST
Mobilization, Demobilization, Insurance and Furnish
Performance and Payment Bonds
LS 1 -$ -$
Furnish, Implementation, and Management of the
SW3P; including Concrete Truck Washout, In
Accordance with the Plans and Specifications
LS 1 -$ -$
Site Restoration, including but not limited to Hydro-
Mulch, Sidewalk and Pavement removal and replacement, Complete-in-Place, In Accordance with the Plans and Specifications
LS 1 -$ -$
04 RV Concrete Pad Extensions (6" Thick) SY 569 -$ -$
05 Remove and Dispose of Existing RV Concrete Pad (1) SY 50 -$ -$
06 RV Concrete Pad (1), 6-Inch SY 100 -$ -$
07 Stabilized Subgrade for RV Concrete Pads. 8-Inch SY 669 -$ -$
Remove and Dispose of Existing Gravel Pavement, With or Without Base
SY 311 -$ -$
Type D Hot Mix Asphaltic Base Course, 3-Inch
(Parking and Loop)
TON 374 -$ -$
10 Lime Stabilized Subgrade, 8-Inch SY 2,219 -$ -$
11 Lime for Lime Stabilized Subgrade TON 374 -$ -$
12 Type A, Grade I Crushed Limestone Base, 8-Inch SY 2,219 -$ -$
Remove and Dispose of Concrete Sidewalk (All
Thickness)
SY 19 -$ -$
14 5-Inch Concrete Sidewalk SF 169 -$ -$
15 Concrete Wheelstop EA 29 -$ -$
Trench Safety System (All Depths); in accordance with the contract plans and specifications. Complete in Place.
LS 1 -$ -$
17 Demolish Existing Septic Tank System LS 1 -$ -$
18 Decomision and Abandon Existing Septic Beds LS 1 -$ -$
19 Proposed Septic System LS 1 -$ -$
GENERAL WORK ITEMS
GENERAL WORK ITEMS SUBTOTAL
SITE WORK ITEMS
SITE WORK ITEMS SUBTOTAL
SEPTIC SYSTEM ITEMS
SEPTIC SYSTEM ITEMS SUBTOTAL
BID SHEET
SEPTIC SYSTEM, ELECTRICAL AND LOOP ROAD IMPROVEMENTS
ITEM
NO.
DESCRIPTION
MEAS.
UNIT
QUANTITY UNIT COST ITEM COST
20 Remove 30a RV Pedestal EA 56 -$ -$
21 Remove 30a RV Pedestal Wire (Assume #8) CLF 472 -$ -$
22 Remove 30a RV Pedestal Conduit (Assume 1-1/2") LF 11,800 -$ -$
23 Remove 30a RV Pedestal Panel EA 3 -$ -$
24 Remove Existing Pole and Transformer EA 3 -$ -$
25 Remove Existing Pole and Transformer Wire CLF 36 -$ -$
Remove Existing Pole and Transformer Conduit
(Assume 2")
LF 1,200 -$ -$
Remove Existing Septic System Electrical components and wiring
EA 1 -$ -$
Replace Existing Septic System Electrical components and wiring
EA 1 -$ -$
29 New Service Weatherhead EA 1 -$ -$
30 50a pedestal EA 56 -$ -$
31 75 kva Transformer EA 6 -$ -$
32 45 kva Transformer EA 1 -$ -$
33 Panel EA 8 -$ -$
34 3x3 Pullbox EA 9 -$ -$
35 400a, 3p fused disconnect EA 2 -$ -$
36 320a meter and can EA 1 -$ -$
37 3/0 ground triad, 10/ rod EA 1 -$ -$
38 480v, 400a, 2p disconnect EA 2 -$ -$
39 480v, 200a, 2p disconnect EA 5 -$ -$
40 480v, 125a, 2p disconnect EA 1 -$ -$
41 #3/0 wire LF 300 -$ -$
42 #6 wire CLF 472 -$ -$
43 1 1/2" conduit LF 11,800 -$ -$
Pot Hole for Utility Investigation as Directed by the
Engineer as Directed by the Owner's Representative, Complete-in-Place, In Accordance with Plans and
Specifications (Minimum Bid $500/EA)
EA 6 -$ -$
Furnish and Install Extra Cement Stabilized
Sand, Complete in Place:
CY 200 -$ -$
46 Extra 5-Inch Concrete Sidewalk Replacement SF 80 -$ -$
Extra Machine Excavation as Directed by the
Owner's Representative, Complete-in-Place, In
Accordance with the Plans and Specifications
(Minimum Bid $20/CY)
CY 50 -$ -$
Extra Hand Excavation as Directed by the Owner's
Representative, Complete-in-Place, In Accordance with the Plans and Specifications (Minimum Bid
$25/CY)
CY 50 -$ -$
Extra Electrical Modifications including but not limited to additional conduit, wires and controls as
Directed by the Owner's Representative, Complete-in-Place, In Accordance with the Plans and
Specifications (Minimum Bid $5,000/LS)
LS 1 -$ -$
ELECTRICAL ITEMS
ELECTRICAL ITEMS SUBTOTAL
EXTRA WORK ITEMS
EXTRA WORK ITEMS SUBTOTAL
BASE BID TOTAL
BID SHEET
SEPTIC SYSTEM, ELECTRICAL AND LOOP ROAD IMPROVEMENTS
ITEM
NO.
DESCRIPTION
MEAS.
UNIT
QUANTITY UNIT COST ITEM COST
50 Remove Existing Septic Beds and Restore Site LS 1 -$ -$
51 Deduct Septic System Item No. 18 LS 1 -$ -$
52 RV Concrete Pads, 6-Inch SY 1,682 -$ -$
53 Remove and Dispose of Existing RV Concrete Pads SY 1,064 -$ -$
54 Stabilized Subgrade for RV Concrete Pads, 8-Inch SY 1,682 -$ -$
55 Deduct Site Work Items No. 04-07 LS 1 -$ -$
Type D Hot Mix Asphaltic Base Course, 3-Inch (Tie-in)
TON 199 -$ -$
Remove Existing Asphalt Pavement Surface by
Milling
SY 9,016 -$ -$
Type D Hot Mix Asphaltic Base Course, 3-Inch
(Milled Overlay)
TON 1,521 -$ -$
LINE ITEM ADD 3 SUBTOTAL
BASE BID & LINE ITEM ADD 3 TOTAL
LINE ITEM ADD 4
LINE ITEM ADD 4 SUBTOTAL
BASE BID & LINE ITEM ADD 4 TOTAL
END OF SECTION
LINE ITEM ADD 1 SUBTOTAL
BASE BID & LINE ITEM ADD 1 TOTAL
LINE ITEM ADD 2
LINE ITEM ADD 2 SUBTOTAL
BASE BID & LINE ITEM ADD 2 TOTAL
LINE ITEM ADD 3
LINE ITEM ADD 1
File details come from the government source that posted it. Updated .