This is an Appendix to a Scope of Work for the Dream Canyon Project in Colorado, detailing mine closure specifications and work requirements. The document presents a comprehensive feature work table for Item 4.0, which involves the installation of mine closures at 21 distinct mine openings across the project site. The work encompasses three primary closure methodologies: machine backfill for shafts and stopes, rock bulkhead construction with bat access features for adits, and grated shaft closures with bat cupolas for larger openings. Mine features range in depth from 5 feet to 100 feet, with opening sizes varying from 2 feet by 3 feet to 50 feet by 35 feet. Each feature is assigned a unique identifier, UTM coordinates using NAD83 datum, and specific closure method designation with references to detailed specifications and standard drawings provided elsewhere in the contract documents.

Work descriptions emphasize environmental protection and wildlife considerations, with all machine backfill closures requiring pre-work bat exclusion protocols and stormwater sediment control measures, including installation of 25 linear feet of biodegradable waddles downstream of work areas under project manager supervision. Specialized closures such as rock bulkheads require foundation clearing and minimum 30-inch thickness grouted native rock construction, while grated shaft closures with bat cupolas incorporate modified bat gates with six-inch by 24-inch bat slots and structural steel beams rated to support opening spans. Several features require imported fill materials, including 60 cubic yards for Feature 363-GF012 and 5 cubic yards of polyurethane foam for Features 363-GF007a and 363-GF007b to support bridge structures. All work is subject to competent rock assessment with requirement for barring down weak or failing rock prior to closure installation.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix 1 – Item 4.0 Feature Work Table

Table - Dream Canyon – Item 4.0 Install Mine Closures

Feature ID Type Description of Mine

Opening Closure Method

General Bid Specifications and Drawings

UTM

(X,Y)

NAD83 Work Description / Notes

363-GF002 Shaft

Excavated:5ft by 6ft Eroded:8ft by 8ft Present:8ft by 8ft

Depth:15 ft Lining:Rock Drainage:No

Machine Backfill Section 2 465599

4428500

BAT EXCLUSION PRIOR TO CLOSING PER SPEC

PROVIDED UNDER ITEM 4.0.

Remove timber debris. Excavate to determine extents.

Bar off rocks from shaft collar and machine backfill with onsite material. Rockfill is not required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

363- GF002a Shaft

Excavated:5ft by 9ft Eroded:12ft by 9ft Present:5ft by 9ft Depth:23 feet ft

Lining:Rock Drainage:No

Machine Backfill Section 2 465580.

4428496

BAT EXCLUSION PRIOR TO CLOSING PER SPEC

PROVIDED UNDER ITEM 4.0.

Remove timber debris. Excavate to determine extents.

Bar off rocks from shaft collar and machine backfill with onsite material. Rockfill is not required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

363-GF003 Stope

Excavated:

Eroded:17ft by 34ft Present:17ft by 34ft

Depth:17 feet ft Lining:Rock Drainage:No

Machine Backfill Section 2 465564

4428474

BAT EXCLUSION PRIOR TO CLOSING PER SPEC

PROVIDED UNDER ITEM 4.0.

Excavate to determine extents. Machine backfill with onsite material. Rockfill is not required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

Description of Mine

Opening Closure Method

General Bid Specifications and Drawings

UTM

(X,Y)

NAD83 Work Description / Notes

363-GF004 Stope

Excavated:5ft by 7ft Eroded:3ft by 7ft Present:3ft by 7ft Depth:18 feet ft

Lining:Rock Drainage:No

Machine Backfill Section 2 465562

4428520

BAT EXCLUSION PRIOR TO CLOSING PER SPEC

PROVIDED UNDER ITEM 4.0.

Excavate to determine extents. Machine backfill with onsite material. Rockfill is not required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

363-GF005 Adit

Excavated:3ft by 7ft Eroded:3ft by 7ft Present:3ft by 7ft Depth:18 feet ft

Lining:Rock Drainage:No

Rock Bulkhead w/ Bat Ladder

Section 14 Section 13

Std. Drawing #s

6.2 & 10

465493 4428523

Construct a Rock Bulkhead closure with Bat Grate Alternative. Utilize a minimum three (3) foot length of thirty-six (36) inch, twelve (12) gauge CSP with an attached bat ladder.

Neither an access door nor drainpipe are required.

363-GF006 Adit

Excavated:3ft by 7ft Eroded:3ft by 7ft Present:3ft by 7ft Depth:15 feet ft

Lining:Rock Drainage:No

Rock Bulkhead w/ Bat Ladder

Section 14 Section 13

Std. Drawing #s

6.2 & 10

465476 4428525

Construct a Rock Bulkhead closure with Bat Grate Alternative. Utilize a minimum three (3) foot length of thirty-six (36) inch, twelve (12) gauge CSP with an attached bat ladder.

Neither an access door nor drainpipe are required.

363-GF007 Stope

Excavated:17ft by 35ft

Eroded:17ft by 35ft Present:17ft by 35ft

Depth:15 feet ft Lining:Rock Drainage:No

Machine Backfill Section 2 465510

4428559

Collapse south side of trench to reduce highwall and use onsite material to backfill. No rockfill required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be

Description of Mine

Opening Closure Method

General Bid Specifications and Drawings

UTM

(X,Y)

NAD83 Work Description / Notes

363- GF007a Stope

Excavated:10ft by 4ft Eroded:10ft by 4ft Present:10ft by 4ft

Depth:10 feet ft Lining:Rock Drainage:No

Modified Machine Backfill

Section 2 465506 4428556

Install 5 CY of polyurethane foam inside opening to support bridge. Backfill both sides of opening with onsite material. Use large rocks on site.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

363- GF007b Stope

Excavated:3ft by 5ft Eroded:3ft by 5ft Present:3ft by 5ft Depth:10 feet ft

Lining:Rock Drainage:No

Modified Machine Backfill

Section 2 465497 4428550

Install 5 CY of polyurethane foam inside opening to support bridge. Backfill both sides of opening with onsite material. Use large rocks on site.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

363- GF007c Stope

Excavated:3ft by 5ft Eroded:3ft by 5ft Present:3ft by 5ft Depth:10 feet ft

Lining:Rock Drainage:No

Machine Backfill Section 2 465492

4428546

Backfill trench and stope with large onsite rocks and material.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

363-GF008 Stope

Excavated:50ft by 1ft Eroded:50ft by 5.5ft Present:50ft by 5.5ft

Depth:65 feet ft Lining:Rock Drainage:No

Shaft Grate w/ Bat Cupola

Section 8, Std.

Drawing # 4 and

Attachment 3

465469 4428544

Stope ranges in width from 3 to 10 ft.

Install a grated shaft closure with a bat cupola in accordance with Grated Shaft Closure Specifications.

The modified bat gate will be a raised four (4) sided ‘cupola’ consisting of one (1), six inch (6”) high by twenty-four inch (24”) wide bat slot on each side. One

(1) ten-foot (10’) W4 x 13 steel beam is required.

Incompetent, weak and failing rock will need to be barred down prior to any work. Access Door NOT required.

Description of Mine

Opening Closure Method

General Bid Specifications and Drawings

UTM

(X,Y)

NAD83 Work Description / Notes

363-GF009 Stope

Eroded:20ft by 40ft Present:13ft by 22ft

Depth:100 ft ft Lining:Rock Drainage:No

Shaft Grate w/ 2 Bat Cupolas

Section 8, Std.

Drawing # 4 and

Attachment 3

465538 4428565

Install a grated shaft closure with a bat cupola in accordance with Grated Shaft Closure Specifications.

Two (2) modified bat gates are required and will be a raised four (4) sided ‘cupola’ consisting of one (1), six inch (6”) high by twenty-four inch (24”) wide bat slot on each side. Two (2) fifteen foot (15’) W6 x 20 steel beams are required. Access Door NOT required.

363-GF010 Adit/ Decline

Excavated:5ft by 2ft Eroded:5ft by 2ft Present:5ft by 2ft

Depth:5 ft ft Lining:Concrete

Drainage:No

Grate with Bat Grate Alternative

Section 11 Section 13

Std. Drawing #s

6.1 & 6.2

465473 4428548

Construct a grated adit closure with a minimum two (2) foot by four (4) foot bat ladder in accordance with Grated Adit Closure Specifications. Neither an access door nor drainpipe are required.

363- GF010a

Adit/ Decline

Excavated:5ft by 2ft Eroded:5ft by 2ft Present:5ft by 2ft

Depth:8 ft Lining:Concrete

Drainage:No

Rock Bulkhead

Section 14 Std.

Drawing # 10

465472 4428594

The foundation shall be cleared of all unconsolidated material prior to construction of the bulkhead.

Construct a bulkhead seal of grouted durable native rock, a minimum of thirty inches (30”) in thickness.

Drainpipe IS required. Access door is NOT required.

363-GF012 Shaft

Excavated:4ft by 8ft Eroded:17ft by 35ft Present:15ft by 25ft

Depth:14 feet ft Lining:Rock

Drainage:Yes

Machine Backfill Section 2 465645

4428649

Collapse sides of opening to reduce highwall. Leave wood/brush debris. Sixty cubic yards (60cy) of imported common fill required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be

Description of Mine

Opening Closure Method

General Bid Specifications and Drawings

UTM

(X,Y)

NAD83 Work Description / Notes

363-GF013 Adit

Excavated:8ft by 7ft Eroded:9ft by 9ft Present:9ft by 9ft Depth:17 feet ft

Lining:Rock Drainage:No

Grated Corrugated Steel Pipe w/ Bat Access

Section 10 Section 13

Std. Drawings # 5 & 6.2

465690 4428641

After clearing all loose debris, install a thirty-six (36) inch diameter ten (10) foot length of twelve (12) gauge corrugated steel pipe (CSP) with bat ladder in accordance with Corrugated Steel Pipe Adit Specifications and Bat Grate Alternative. Access door is NOT required. Drainpipe is NOT required. Rock grouting around the CSP IS required. The CONTRACTOR shall cover the CSP with onsite soil bedding prior to backfill and to reduce the likelihood of damage to the CSP by falling rock from the brow. In addition, the exterior of the CSP shall be backfilled using onsite material

363-GF015 Shaft

Excavated:8ft by 5ft Eroded:10ft by 10ft Present:10ft by 10ft

Depth:10 ft Lining:Rock

Drainage:Yes

Machine Backfill Section 2 465714

4428570

Excavate to determine extents. Machine backfill with onsite material. Rockfill is not required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

363- GF015a

Adit/ Decline

Excavated:4ft by 5ft Eroded:2ft by 3ft Present:2ft by 3ft

Depth:10 ft Lining:Rock

Drainage:Yes

Rock Bulkhead

Section 14 Std.

Drawing # 10

465731 4428572

The foundation shall be cleared of all unconsolidated material prior to construction of the bulkhead.

Construct a bulkhead seal of grouted durable native rock, a minimum of thirty inches (30”) in thickness.

Drainpipe IS required. Access door is NOT required.

363-GF016 Adit

Excavated:3ft by 1.5ft Eroded: 3ft by 1.5ft Present: 3ft by 1.5ft

Depth:14 ft Lining:Rock Drainage:No

Rock Bulkhead w/ Bat Ladder

Section 14 Section 13

Std. Drawing #s

6.2 & 10

465737 4428520

The foundation shall be cleared of all unconsolidated material prior to construction of the bulkhead.

Construct a Rock Bulkhead closure with Bat Grate Alternative. Utilize a minimum three (3) foot length of thirty-six (36) inch, twelve (12) gauge CSP with an attached bat ladder.

Neither an access door nor drainpipe are required.

Description of Mine

Opening Closure Method

General Bid Specifications and Drawings

UTM

(X,Y)

NAD83 Work Description / Notes

GF017 Stope

Excavated:5ft by 3ft Eroded:5ft by 3ft Present:5ft by 3ft Depth:20-30ft ft

Lining:Rock Drainage:No

Machine Backfill Section 2 465671

4428646

BAT EXCLUSION PRIOR TO CLOSING PER SPEC

PROVIDED UNDER ITEM 4.0.

Excavate to determine extent of opening. Backfill with onsite material. Rockfill is not required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be installed on the downstream side of the working area under the direction of the PROJECT MANAGER.

W-1 Stope

Excavated:5ft by 3ft Eroded:13ft by 13ft Present:5ft by 3ft

Depth:N/A ft Lining:Rock Drainage:No

Machine Backfill Section 2 469855

4429753

Excavate to determine extent of opening. Backfill with onsite material. Rockfill is not required.

Storm water sediment control measures shall be implemented prior to work on the closure. Twenty-five

(25) linear feet of biodegradable waddles shall be