5-Addenda 02 24SEPT2026.pdf
PDF 6 MB Posted
- Solicitation number
- 5129246--
- Issued by
- Salt Lake County, Utah
About this file
This is an Addendum document issued on September 24, 2026, for the Replace Flume/Auto Dump and JSL Canal Enclosure at Millcreek project in Utah. The project involves the construction of a replacement Jordan & Salt Lake Canal Mill Creek crossing located at approximately 1445 East Murphy's Lane. The scope of work includes furnishing and installing a Debris Rack Structure, new box culvert canal conveyance, Overflow Structure, Creek Crossing Structure, and Outlet Structure. The addendum modifies the original contract documents and bid requirements for this infrastructure improvement project. An open bid Microsoft Teams meeting has been scheduled for interested bidders, with meeting details and passcode provided for remote participation. The addendum document serves to clarify, modify, or supplement the original bid specifications and contract terms prior to bid submission.
The specific details regarding pricing terms, bid amounts, set-asides, response deadlines, and award timeline are not detailed in the addendum reference provided. Bidders should review the complete addendum document in conjunction with the original contract documents to understand all modifications to pricing requirements, bid submission procedures, and project conditions. Any changes to the original scope, schedule, or contractual obligations introduced by this addendum supersede conflicting provisions in the base contract documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised December 11, 2023 Addendum No. 2
00 91 13. 2 - 0
NOTICE
TO: All plan holders
DATE: September 22, 2026
FROM: Jason Draper, P.E.
Chief Engineer
Salt Lake City Public Utilities
1805 West 500 South, Salt Lake City, Utah 84104
(801) 483-6840 FAX (801) 483-6818
SUBJECT: Addendum No. 2 to the Contact Documents for REPLACE FLUME/AUTO DUMP
AND JSL CANAL ENCLOSURE AT MILLCREEK, Project No. 5129246--
Transmitted herewith is ADDENDUM No. 2 to the contract documents for the above mentioned project.
All bids submitted without the signed acknowledgment of this Addendum will be rejected.
https://secure.na1.documents.adobe.com/verifier?tx=CBJCHBCAABAAmsoV6VWyFWqc9A9nyZCynCRAklGcBJrm
00 91 13. 2 - 1
DOCUMENT 00 91 13. 2
ADDENDUM No. 2
ATTACHMENTS:
Revised Specifications:
1. 00 43 00 Bid Schedule
2. 31 37 00 Riprap
3. 31 23 23.43 Geofoam
Revised Drawings:
1. Millcreek City standard detail 110
2. C-3
3. PP-3
4. S-10
Added documents:
1. Stream Alteration Permit
2. Flood Control Permit
3. Geotechnical Report 1
4. Geotechnical Report 2
5. Mill Creek Flows
PART 1 GENERAL
1.1 DOCUMENT INCLUDES
A. Changes to the Bid Documents.
1.2 CONSTRUCTION CONTRACT
A. REPLACE FLUME/AUTO DUMP AND JSL CANAL ENCLOSURE AT
MILLCREEK
B. Project No. 5129246--
C. Date: September 22, 2026
PART 2 CHANGES
2.1 CHANGES TO PRIOR ADDENDA
A. NONE
2.2 CHANGES TO BIDDING REQUIREMENTS
A. NONE
2.3 CHANGES TO AGREEMENT AND OTHER CONTRACT FORMS
00 91 13. 2 - 2
A. NONE
2.4 CHANGES TO CONDITIONS OF THE CONTRACT
A. NONE
2.5 ENGINEER’S RESPONSE TO BIDDER QUESTIONS
Q: #6. Please confirm correct unit of measure (S.Y. vs. acre) and correct quantity for Item 9, given the Bid Schedule's 1,936 S.Y. vs. Spec's “paid by the acre” language and an independent takeoff of ~1,102 S.Y.
A: 1,102 S.Y. is the correct area. Please see attached revised Bid Schedule.
Q: #7. Confirm which Bid Schedule item(s) carry procurement/installation cost of the slide gates described in Section 35 20 16 of the project specifications.
A: Slide gates to be included with Bid Items 18 and 19 as shown on drawings.
Q: #8. We request any hydraulic/hydrologic survey data, historic peak-flow records, and geotechnical data for the 200 cfs diversion work area to properly prepare to mitigate for the flow through this area during the time of work.
A: The attached document (Mill Creek flows.docx) provides the known historic peak-flow records.
Q: #9. Please provide the tree inventory/caliper schedule supporting the 29 EA quantity, or confirm the basis for the count such as diameter sizing to determine which trees are to be removed.
A: Number of trees were determined by on site survey of trees in project disturbance area. As per part D.2 of section 00 21 13 contractors are to visit the site to become familiar with local conditions that may affect cost, progress, performance, or furnishing of the Work.
Q: #10. Define measurable completion/acceptance standards for the homeowner-specific items
(fencing, rock/composter salvage, vine relocation, access gate).
A: Work to be performed per notes 3, 4, and 5 of drawing sheet C-1 and restore to preconstruction conditions.
Q: #11. Confirm whether a Phase I/II ESA exists for the corridor and describe the differing-site-condition protocol should these environmental or contamination of soils be discovered.
A: There are no anticipated contaminated soils per attached Geotechnical report.
Q: #12. Confirm the governing antenna pole base dimension (12″ vs. 18″) and point of contact
(Le Tran vs. Robert Pier). Also, Sheet E6.1 2.17 SCADA System Note 3 is struck out;
however, there are notes to coordinate pole installation with Robert Pier. Please clarify if pole will be in contractor's scope of work.
A: Antenna pole base dimension shall be 18” per detail 2 on sheet E-5.2 and is in the contractor’s scope. Robert Pier is the point of contact per general note 3 on sheet E-
6.1.
00 91 13. 2 - 3
Q: #14. Do you have a description and gradation of the 12" granular filter material under rip rap?
I couldn't find anything in the referenced APWA spec.
A: See revised section 31 37 00.
Q: #20. If we are to abandon the existing pipes considered "relics", how are we to abandon them that will be accepted by the governing body? Please let us know what will be required to be considered complete in the abandoning on these pipes.
A: There are no existing pipes to be abandoned in the project.
Q: #21. On sheet C-3, a 12" steel pipe is shown but it is unknown as to whether this pipe is existing or to be installed by the contractor. Please confirm whether this is an existing pipe that is just to be tied into or if this is a new install. Please also confirm the wall thickness for this pipe as it is only shown as "STD WALL STEEL PIPE".
A: The pipe is to be new at a thickness of 0.375”. Please see revised C-3.
Q: #23. On sheet C6, the three sided precast culvert is shown to have precast footings.
Please clarify this to actually be expected to be precast or if it is meant to be cast in place footings that the precast, three sided culvert bears upon. If it is, in fact, supposed to be precast, is the three sided culvert to be cast with these footings attached or is there another way these footings are to be joined to the culvert?
A: The footings are to be precast and separated from the 3-sided culvert.
Q: #24. Please confirm geofoam type/grade (ASTM D6817), density, and board dimensions for the Creek Crossing Structure fill.
A: It is to be EPS12 and corresponding specification shall be attached.
Q: #27. Confirm which Bid Item includes the cost of required privacy construction fencing (to contain the adjacent homeowner's dogs), or whether a separate quantity/spec should be issued - none currently exists.
A: Added Bid Item 36 for Privacy Fencing. See attached revised Bid Schedule.
Q: #29. Please provide a station-range table showing where each gabion basket type
(2/3/4-basket) begins and ends along both banks. It is currently not able to be determined where one type begins and ends from the drawings alone.
A: Added clarification notes on sheet PP-3. See revised sheet.
Q: #31. In the gate specification section, hydraulic gates are called out specifically; however, on the drawings, gates are called out to be electrically actuated. Please clarify which design/specification is desired on the project.
A: Gates are to be electrically actuated as per the drawings.
Q: #32. Please confirm the desired mix design and class for the asphalt to be utilized on this project.
A: See attached Detail 110 of Millcreek City.
00 91 13. 2 - 4
Q: #33. Please confirm the existing thickness of the asphalt on Murphy Lane.
A: Existing asphalt is 5 1/2" per the geotechnical report.
Q: #34. Please confirm the existing thickness of asphalt to be placed back on the Murphy Lane
Crossing as well as the thickness of roadbase desired for this area as well.
A: See attached Detail 110 of Millcreek City.
Q: #37. Sheet S-10 shows a 12" RCP storm drain daylighting through the Southwest
Retaining Wall (gabion "divot" end treatment, non-shrink grout seal), with no length, station limits, or pipe class given, and no Bid Schedule item appears to include it -
Item 26 is described only as the wall structure. Confirm the pipe's length/station limits, class/material spec, and which Bid Item carries its furnish-and-install cost, or whether a separate pay item should be added.
A: S-10 shows incorrect size, revised to correct size of 15”. Pipe information is provided on sheet PP-2. Item to be paid as part of bid item 28.
Q: #38. No provision in the 210-page manual addresses an in-water work window, fish-passage/spawning-season restriction, or other environmental-permit-driven seasonal limitation on stream diversion/dewatering or in-channel work. Given the fixed Feb 28, 2027 completion date and an anticipated late-2026 NTP, confirm whether any Utah DWRi, DWQ, Army Corps (404/401), or DWR fish-related permit condition restricts timing of in-channel work on this reach of Mill Creek.
A: Please see attached Stream Alteration Permit and Flood Control Permit.
Q: #39. Doc 00 73 50/Spec 33 08 00 establish a full potable-water commissioning sequence (200 psi/2-hr hydrostatic test, chlorination, de-chlorination, two passing
City-lab bacteriological samples) applying to City-owned water/sewer/storm facilities.
Item 17's 18" DIP siphon connects to "existing irrigation/CMP" (non-potable). Confirm whether the full potable-water commissioning sequence applies to this non-potable line, or whether a lesser standard, such as a leak only test, governs.
A: The pipes shall follow the non-potable test schedule per specification 33 08 00 Table
3.
Q: #43. Are there Electric Motor Actuator Specs for the Hydraulic Slide Gates (spec section 35 20 16)?
A: Per part 2.1D of Section 35 20 16.03, “Gate actuators shall be sized, selected, and furnished by the gate manufacturer. They shall be adequately braced to prevent warping and bending under the intended usage. Gate actuators throughout the project shall be products from a single manufacturer. Shall operate on 240-volt single phase.”
2.5 CHANGES TO SPECIFICATIONS
A. Updated Section 00 43 00 – Bid Schedule with the following;
00 91 13. 2 - 5
1. Item 9 quantity revised to 1102 SY.
2. Added Item 36 – Privacy Fencing – 73 LF
3. Replace acre with square yard in Part 3.9.
4. Added Part 3.36 Privacy Fencing;
“A. Privacy Fencing will be measured by the lineal foot installed and accepted.
B. Bid price covers all the costs associated with furnishing and installing the new fence as shown on the drawings and as specified.“
B. Replaced Section 31 37 00 – RIPRAP with Section 31 37 00 – RIPRAP OR ROCK
LINING
C. Added Section 31 23 23.43 Geofoam
2.6 CHANGE TO DRAWINGS
A. Added wall thickness for steel pipe and clarified pipe is new on sheet C-3.
B. Added clarification notes where 2, 3, and 4-basket gabions start and end on PP-3.
C. Revised pipe call out to correct 15” diameter size on S-10.
D Added sheet Millcreek City standard detail 110
PART 3 ACKNOWLEDGEMENT
3.1 Acknowledgement of receipt of this addendum is made in paragraph 1.4 A. ADDENDA of
Section 00 41 00.
3.2 All bids submitted without the signed acknowledgment of this Addendum will be rejected.
END OF ADDENDUM
Revised May 4, 2026
Bid Schedule
00 43 00 - 1
DOCUMENT 00 43 00
BID SCHEDULE
PART 1 GENERAL
1.1 DOCUMENT INCLUDES
A. Price schedules.
B. Measurement and payment provisions.
1.2 CONSTRUCTION CONTRACT
A. Replace Flume/Auto Dump And Jsl Canal Enclosure At Millcreek
Approximately 1445 East Murphy’s Lane
Project No. 5129246
1.3 REFERENCES
A. APWA 01 29 00: Payment Procedures.
B. Document 00 52 00: Agreement.
1.4 SCHEDULE TO BE ADDED TO THE AGREEMENT
A. This document will be added to the Agreement by reference.
PART 2 PRICE SCHEDULES
2.1 GENERAL
A. Number of Schedules in Bid: One.
B. Number of alternate schedules: None.
C. For progress payment procedures, see APWA Section 01 29 00 requirements.
2.2 BASE BID
A. CAUTION: Bidder shall complete all blanks in the following price schedule.
Failure to do so may cause the bid to be declared non-responsive by ENGINEER.
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT UNIT COST
TOTAL
AMOUNT
01 71 13 Mobilization
1 L.S.
01 55 26 Traffic Control
1 L.S.
01 45 00 Quality Control Program
1 L.S.
SWPPP (Stormwater Pollution Prevention Plan)
1 L.S.
00 43 00 - 2
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT UNIT COST
TOTAL
AMOUNT
01 58 00 Project Identification Sign
1 L.S.
6 Public Information Coordination 1 L.S.
31 23 19 Stream Diversion/Dewatering
1 L.S.
31 11 00 Remove Existing Trees
29 Each
31 11 00 Clearing and Grubbing
1102 S.Y.
02 41 14 & 32 12 05 Remove and Replace Pavement (Murphys Lane)
76 S.Y.
02 41 13 Remove Existing Box Culvert and Headwalls (Murphys Lane)
1 L.S.
02 41 13 Remove Existing Concrete Creek Crossing Structure
1 L.S.
32 91 13 1422 E Millstream Ln Landscape Protection and Replacement
1 L.S.
33 05 02 5-foot X 3-foot Box Culvert RCP
245 L.F.
03 40 00 Catch Basin 315.1
1 Each
03 30 04 Debris Rack Structure
1 L.S.
03 40 00 & 33 05 05 Irrigation Siphon
1 L.S.
03 30 04 Overflow Structure
1 L.S.
03 30 04 Outlet Structure
1 L.S.
33 05 02 & 03 30 04 Creek Crossing Structure
1 L.S.
31 36 13 2-basket 3’ x 3’ Gabions
12 L.F.
31 36 13 3-basket 3’ x 3’ Gabions
50 L.F.
31 36 13 4-basket 3’ x 3’ Gabions
61 L.F.
31 37 00 4’ Thick Riprap D50 = 24”
430 Tons
00 43 00 - 3
ITEM DESCRIPTION
ESTIMATED
QUANTITY
UNIT UNIT COST
TOTAL
AMOUNT
31 37 00 12” Thick Granular Filter
193 S.Y.
03 30 04 Southwest Concrete Retaining Wall
1 L.S.
03 30 04 Turn Around Concrete Retaining Wall
1 L.S.
33 41 00 15-inch RCP Class III
46 L.F.
33 40 00 2-foot X 2-foot Precast Box 332
1 Each
31 22 00 Site Grading
1 L.S.
32 11 23 Access Road 6-inch Depth Depth Surface Coarse Aggregate
422 S.Y.
31 91 19 Revegetation
740 S.Y.
31 31 13 6' Chain Link Fencing
583 L.F.
34 Electrical System Complete 1 L.S.
35 General Allowance 1 L.S. $130,000
36 Privacy Fencing 73 L.F.
Total = $ ______________________
PART 3 MEASUREMENT AND PAYMENT
3.0 IN GENERAL
A. See measurement and payment in APWA Section 01 29 00.
B. Classification of Work:
1. In the price schedule, specification reference numbers are provided. The referenced specification describes work applicable to the classification of work indicated.
2. Payment for that classification of work covers cost of work in the referenced specification and any incidental work and material necessary to complete the referenced work.
C. Lump Sum Bid Items: Measured on a percent complete basis.
00 43 00 - 4
D. Utility Frames and Covers:
1. Any frame or cover damaged by CONTRACTOR will be replaced at no additional cost to OWNER.
2. If ENGINEER determines an existing frame or cover needs to be replaced, a new frame or cover will be either provided by OWNER or CONTRACTOR. A frame and cover supplied by CONTRACTOR will be paid for using prices agreed to in a Change
Order.
3. Quality Control Program: Bid price covers CONTRACTOR’s cost to secure and provide backfill compaction test results for ENGINEER’s acceptance. Test results by an independent testing agency will be the only test results accepted. The number of acceptance tests required is 1 density test per lift in each 200 feet of trench in a random location. An uncompacted backfill lift is 8” thick. Deficient number of required tests measured in percent will result in a pay reduction up to 25 percent of the
Bid item requiring compacted backfill material.
4. Over Excavation: No payment for over excavation and backfill unless approved in writing by ENGINEER.
3.1 MOBILIZATION
A. Measurement:
Percent of Original Contract
Amount Earned
Percent of Amount Bid for
Mobilization to be Paid
5 40
15 20
40 30
50 10
B. Bid price covers cost of mobilization, demobilization, installation of temporary facilities, permits, Millcreek City Excavation and Encroachment Permit, and bringing all necessary construction equipment to site. Insurance and bonding and repair of damages during access to the site, (e.g. Murphys lane).
C. Excluded from bid price cost of public information specialist.
3.2 TRAFFIC CONTROL
A. Measurement:
Percent of Original Contract
Amount Earned
Percent of Amount Bid for
Mobilization to be Paid
5 40
15 20
40 30
50 10
B. Bid price covers cost of police officer (if necessary), vehicular and pedestrian protection
00 43 00 - 5 from work zone activity, services of a certified traffic control technician, and a traffic control plan acceptable to Millcreek City’s engineer.
3.3 QUALITY CONTROL PROGRAM
A. Measurement:
1. The number of compaction acceptance tests required is 1 density test per lift in each
200 feet of trench in a random location. An uncompacted backfill lift is 8” thick.
2. Deficient number of required tests measured in percent will result in a pay reduction up to 25 percent of the classification of work (Bid) item requiring compacted backfill material.
3. Test results by an independent testing agency will be the only test results accepted.
B. Payment:
• 20 percent after submission of a quality control plan that explains CONTRACTOR’s quality control organization, inspection plan, testing plan, sampling plan, correction action plan, laboratory facility, quality control organization chart, control charts, personnel qualifications,
• 60 percent during progress of work.
• 20 percent when final summary report complying with APWA Section 01 45 00 is submitted.
• Payment includes compensation for all the testing required by the specifications including but not limited to concrete testing and compaction testing, C. Change Order: If ENGINEER requests supplemental control testing and such testing shows product meets specification, additional testing will be paid for by Change Order.
3.4 SWPPP (Storm Water Pollution Prevention Plan)
A. Measured as follows.
• 20 percent when plan is submitted to and accepted by ENGINEER.
• Remainder as work progresses on a percentage basis.
B. Bid price covers cost of preparing a storm water pollution plan (SWPPP) suitable to
Millcreek City. As a minimum, the plan will include components illustrated in APWA
Standard Plans.
3.5 PROJECT IDENTIFICATION SIGN
A. Includes incidentals such as building sign, placing sign, removing graffiti from sign, and removing sign after the work is substantially complete (see SECTION 01 58 00).
3.6 PUBLIC INFORMATION COORDINATION
A. Bid price is a lump sum payment for public information coordination.
B. The CONTRACTOR shall provide a public relations supervisor who shall have a 24-hour access phone number to respond to construction complaints; have authority to resolve concerns and complaints; provide updated schedule to the ENGINEER; ensure all notifications to adjacent property owners are made as described in the contract documents;
00 43 00 - 6 contact any property owners who have called with complaints or expressed concerns within 60 minutes; document all complaints in a public relations log, including name, address and contact information, data and time of initial notification, nature of complaint, actions taken to resolve complaint; be listed with name and phone number on all project flyers, notifications, and project signs; not be the project superintendent.
3.7 STREAM DIVERSION/DEWATERING
A. Measured as follows.
• 20 percent when plan is submitted to and accepted by ENGINEER.
• Remainder as work progresses on a percentage basis.
B. Bid price covers cost of preparing a stream diversion and dewatering plan, all materials and labor required to implement and maintain the stream diversion, and all materials and labor required to implement and maintain the dewatering plan.
C. A 200 cfs design flow is to be used for the Mill Creek diversion.
3.8 REMOVE EXISING TREES
A. Measured for each tree removed as designated on the plans.
B. Includes incidentals such as excavation, topsoil, removal and disposal of the tree and roots.
3.9 CLEARING AND GRUBBING
A. Clearing and grubbing will be measured by the square yard of area cleared and grubbed.
B. Clearing and grubbing will be paid for at the contract unit price per acre of area cleared and grubbed. Payment shall be considered complete compensation for all labor, equipment, and materials, including but not limited to: work described or enumerated in Section 31
11 00; Clearing Grubbing and Stripping; includes hauling and dumping fees; and all other operations and materials required to complete the item in accordance with the plans, and technical specifications.
3.10 REMOVE AND REPLACE PAVEMENT (Murphys Lane)
A. Measured by the square yard of replaced pavement.
B. Payment includes all work and material to remove existing pavement as required for installation of the new box culvert and head wall; includes incidentals such as excavation, saw cutting, removal and off-site disposal at an approved landfill; supplying, placing, compacting and grading the road base and asphalt (approved by the Engineer prior to placement); testing coordination; and all other operations and materials required to complete the item in accordance with the plans, and technical specifications.
3.11 REMOVE EXISTING BOX CULVERT AND HEADWALLS (Murphys Lane)
A. Includes all work and material to remove existing concrete head walls and culvert as shown on the project plans; includes incidentals such as excavation outside of typical trench section which may be required, backfill, compaction, saw cutting of pavement and existing structures; and removal and off-site disposal at an approved landfill.
00 43 00 - 7
3.12 REMOVE EXISTING CONCRETE CREEK CROSSING STRUCTURE
A. Includes all work and material to remove existing concrete creek crossing structure as shown on the project plans; includes incidentals such as excavation outside of typical trench section which may be required, backfill, compaction, saw cutting of existing structures; and removal and off-site disposal at an approved landfill.
3.13 1422 E MILLSTREAM LN LANDSCAPE PROTECTION AND REPLACEMENT (see notes 2 through 5 on drawing sheet C-1)
A. Includes all work and material to protect/replace existing landscaping including but not limited to the work described in Notes 2 through 5 on drawing sheet C-1.
3.14 5-FOOT X 3-FOOT BOX CULVERT RCP
A. Measured along centerline of installed precast culvert. No measurement or payment for over-excavation and backfill unless approved in writing by ENGINEER.
B. Includes work and material shown in APWA Plan 381, 382, Public Utilities Department
Standard Practice No. 1 and the contract drawings; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, gaskets, connections, closure collars, pipe zone and trench zone backfill and compaction, temporary roadway or sidewalk, surfacing materials, landscape restoration, cleaning and commissioning.
3.15 CATCH BASIN 315.1
A. Includes work and material shown in APWA Plan 332 and the project details; and incidentals such as excavation outside of typical trench section due to additional size of structure, additional excavation and backfill for foundation stabilization, backfill around the structure, adjusting frame and cover to grade, secure cover to frame to prevent rattle or pop-out and installing a concrete collar shown in APWA Plan 362.
3.16 DEBRIS RACK STRUCTURE
A. Bid price covers construction of debris rack structure, irrigation pipe, and boxes as shown on the drawings and specified herein; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, gaskets, connections, closure collars, pipe zone and trench zone backfill and compaction, temporary roadway or sidewalk, surfacing materials, landscape restoration, cleaning and commissioning.
3.17 IRRIGATION SIPHON
A. Bid price covers construction of the irrigation siphon under the overflow structure as shown on the drawings and specified herein; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, gaskets, new siphon boxes, ductile iron pipe, connections, closure collars, flowfill (CLSM), backfill and compaction, cleaning and commissioning.
3.18 OVERFLOW STRUCTURE
A. Bid price covers construction of overflow structure as shown on the drawings and specified herein; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, gaskets, connections, closure
00 43 00 - 8 collars, pipe zone and trench zone backfill and compaction, temporary roadway or sidewalk, surfacing materials, landscape restoration, cleaning and commissioning.
3.19 OUTLET STRUCTURE
A. Bid price covers construction of outlet structure as shown on the drawings and specified herein; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, gaskets, connections, closure collars, pipe zone and trench zone backfill and compaction, temporary roadway or sidewalk, surfacing materials, landscape restoration, cleaning and commissioning.
3.20 CREEK CROSSING STRUCTURE
A. Bid price covers installation of precast footings, precast three-sided box, cast-in-place concrete walls and slabs (including culvert floor), and geofoam as shown on the drawings and specified herein; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, gaskets, connections, closure collars, weight limit signs, cleaning and commissioning.
3.21 2-BASKET 3’ X 3’ GABIONS
A. Gabion wall shall be measured by the lineal feet measured along the stream side front edge of the installed and accepted gabion wall.
B. Payment for these items shall be paid for at the contract unit price per lineal foot of gabion wall accepted in place and shall be full compensation for all labor, equipment, and materials, including but not limited to, excavation, shoring, protection of existing utilities, installation, granular filter, baskets, rock, removal and disposal of excess excavated material, backfilling, compaction, grading, and all other operations and materials required to complete this portion of the work as herein described and as shown on the drawing.
3.22 3-BASKET 3’ X 3’ GABIONS
A. Gabion wall shall be measured by the lineal feet measured along the stream side front edge of the installed and accepted gabion wall.
B. Payment for these items shall be paid for at the contract unit price per lineal foot of gabion wall accepted in place and shall be full compensation for all labor, equipment, and materials, including but not limited to, excavation, shoring, protection of existing utilities, installation, granular filter, baskets, rock, removal and disposal of excess excavated material, backfilling, compaction, grading, and all other operations and materials required to complete this portion of the work as herein described and as shown on the drawing.
3.23 4-BASKET 3’ X 3’ GABIONS
A. Gabion wall shall be measured by the lineal feet measured along the stream side front edge of the installed and accepted gabion wall.
B. Payment for these items shall be paid for at the contract unit price per lineal foot of gabion wall accepted in place and shall be full compensation for all labor, equipment, and materials, including but not limited to, excavation, shoring, protection of existing utilities, installation, granular filter, baskets, rock, removal and disposal of excess excavated material, backfilling, compaction, grading, and all other operations and materials required to complete this portion of the work as herein described and as shown on the drawing.
00 43 00 - 9
3.24 4’ THICK RIPRAP D50=24”
A. This bid item shall be measured by the ton based on weight tickets for the installed and accepted in place rip rap as shown on the plans and in accordance with the specifications.
B. This item shall be paid for at the contract unit price per ton of installed and accepted in place rip rap. Payment shall be considered complete compensation for all labor, equipment, and required materials including but not limited to: supplying, and placing as shown on the drawings the rip rap (D50 = 24”); and all other operations and materials required to complete the item in accordance with the plans, technical specifications, and
Salt Lake City standards.
3.25 12” THICK GRANULAR FILTER
A. Bid price covers the cost of supplying and installing granular filter material.
B. Bid item quantity is a plan quantity.
3.26 SOUTHWEST CONCRETE RETAINING WALL
A. Bid price covers construction of retaining walls as shown on the drawings and specified herein; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, backfill and compaction, surfacing materials, landscape restoration, cleaning and commissioning.
3.27 TURN AROUND CONCRETE RETAINING WALL
A. Bid price covers construction of retaining walls as shown on the drawings and specified herein; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, backfill and compaction, surfacing materials, landscape restoration, cleaning and commissioning.
3.28 15-INCH RCP CLASS III
A. Measured along pipe with no deduction for fittings, boxes, or manholes. No measurement or payment for over-excavation and backfill unless approved in writing by ENGINEER.
B. Includes work and material shown in APWA Plan 381, 382, Public Utilities Department
Standard Practice No. 1 and the contract drawings; and incidentals such as excavation, removing interfering structures and obstructions, groundwater control, shoring and bracing, gaskets, connections, closure collars, pipe zone and trench zone backfill and compaction, temporary roadway or sidewalk, surfacing materials, landscape restoration, cleaning and commissioning.
3.29 2-FOOT X 2-FOOT PRECAST BOX 332
A. Includes work and material shown in APWA Plan 332 and the project details; and incidentals such as excavation outside of typical trench section due to additional size of structure, additional excavation and backfill for foundation stabilization, backfill around the structure, adjusting frame and cover to grade, secure cover to frame to prevent rattle or pop-out and installing a concrete collar shown in APWA Plan 362 in asphalt paved surfaces.
00 43 00 - 10
3.30 SITE GRADING
A. Paid as a lump sum basis for excavation, subgrade preparation, and placement and compacting embankment material (not included elsewhere as backfill for structures or pipeline trenches) to the finished lines and grades as established on the Contract Drawings.
3.31 ACCESS ROAD 6-INCH DEPTH UNTREATED BASE COURSE
A. Bid price covers the cost of supplying and installing untreated base course material as access road surface.
B. Bid item quantity is a plan quantity.
3.32 REVEGETATION
A. Bid price covers the cost of spreading topsoil, seed bed preparation, and hydromulch application in accordance with the plans (see drawing sheet G-3) and specifications.
B. Bid item quantity is a plan quantity.
3.33 6’ CHAIN LINK FENCE
A. Chain link fence will be measured by the lineal foot installed and accepted.
B. Bid price covers all the costs associated with furnishing and installing the new fence as shown on the drawings and as specified. The bid price also includes gates.
3.34 ELECTRICAL SYSTEM COMPLETE
A. “Electrical System Compete” shall not be measured but shall be paid for on a lump sum unit price basis for the construction and installation of electrical work, including all components required on the drawings and in the specifications..
B. Payment for “Electrical System Complete” shall be made at the contract unit lump sum bid price. Payment shall be considered complete compensation for all labor, equipment, and required materials including but not limited to: furnishing and installing all electrical equipment including service connection conduit, all conduit from the Utility Pole to the
Metering Pedestal and to the Equipment Enclosure, power/control to the water slide gates, radar level sensors, SCADA system with PLC with antenna and mast, and all other operations and materials required to complete this portion of the work as herein described and as shown on the drawings.
3.35 GENERAL ALLOWANCE
A. Measurement: To minimize delays and expedite the flow of work on the project, a maximum of $130,000 has been included in the Bid Schedule to compensate the
CONTRACTOR for unspecified extra or additional Work that was not foreseeable at time of the bid, but that is necessary to complete the Project as originally contemplated. An owner authorized General Allowance Work Order is required to obtain payment from the General Allowance.
B. Payment Covers: See Article 10.4 in the Modifications to the General Conditions for additional information on the management, approval and payment for General Allowance
Work Orders.
3.36 PRIVACY FENCING
A. Privacy Fencing will be measured by the lineal foot installed and accepted.
00 43 00 - 11
B. Bid price covers all the costs associated with furnishing and installing the new fence as shown on the drawings and as specified.
END OF DOCUMENT
09/2026 GEOFOAM
083.43.210 31 23 23.43 - 1
SECTION 31 23 23.43
GEOFOAM
PART 1 GENERAL
DESCRIPTION
This work shall consist of furnishing and placing expanded polystyrene, referred to in this specification as EPS Geofoam fill, in accordance with the details shown in the Contract Drawings, these Specifications, Division 31 Earthworks Sections, or as directed by
ENGINEER.
RELATED WORK
Related work specified in other Sections includes, but is not limited to:
Section 01 33 00 Submittal Procedures Section 01 45 00 Quality Control and Materials Testing Section 31 23 23 Excavation and Backfill for Structures Section 31 23 19 Dewatering
REFERENCES
The latest edition of the following publications form a part of these Specifications to the extent referred. The publications are referred to in the text by basic designation only.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM C 165 Standard Test Method for Measuring Compressive Properties of Thermal Insulation
ASTM C 203 Standard Test Methods for Breaking Load and Flexural Properties of Block-Type Thermal Insulation
ASTM C 303 Standard Test Method for Dimensions and Density of Preformed Block and Board-Type Thermal Insulation
ASTM C 390 Standard Practice for Sampling and Acceptance of Thermal Insulation Lots
ASTM D 1621 Standard Test Method for Compressive Properties of Rigid Cellular Plastics
ASTM D 1622 Standard Test Method for Apparent Density of Rigid Cellular Plastics
ASTM D 1623 Standard Test Method for Tensile and Tensile Adhesion Properties of Rigid Cellular Plastics
ASTM D 2863 Standard Test Method for Measuring the Minimum Oxygen Concentration to Support Candle-Like Combustion of Plastics (Oxygen Index)
ASTM D 6817 Standard Specification for Rigid Cellular Polystyrene Geofoam ASTM D 7557 Standard Practice for Sampling of Expanded Polystyrene Geofoam Specimens
083.43.210 31 23 23.43 - 2
The latest Edition of the American Public Works Association (APWA) and Associated General Contractors of America Standard Plans and Standard Specifications.
SUBMITTALS
Provide submittals in accordance with Section 01 33 00 Submittal Procedures.
Prior to the start of work, CONTRACTOR shall submit for review the following:
A plan sheet showing a profile and section view of the proposed embankment. The drawing shall clearly indicate the size, type, location and orientation of all Geofoam blocks.
The location and type of connectors Proposed ballasting or guying techniques Proposed placement methods
Prior to the delivery of the EPS Geofoam blocks, CONTRACTOR shall furnish ENGINEER with a copy of manufacturer’s test reports or a third party’s certified test report showing that the Geofoam blocks meet the physical properties and standards listed below in Table 1.
The Contractor shall submit to ENGINEER a Manufacturer’s Certificate of Compliance for the first 100 cubic yards and for every 1,500 cubic yards thereafter before the Geofoam is delivered to the site.
The Certificate of Compliance shall include current inspection reports showing that the Geofoam manufacturer is in compliance with a UL follow-up service program for both flame and physical properties. In addition, computer generated stress-strain data and the accompanying curves shall be produced from compressive testing and supplied to ENGINEER. The curves and/or data shall clearly indicate the stress at 1% strain and the modulus of elasticity.
HANDLING, DELIVERY, AND STORAGE
CONTRACTOR shall prevent damage to the Geofoam blocks during delivery, storage, and construction. Prior to delivery of Geofoam block fill to the project site, CONTRACTOR shall review and be thoroughly knowledgeable with the manufacturer's care and handling recommendations. Any Geofoam block that is exposed to sun light for more than six months shall be covered with an opaque material to prevent ultraviolet light degradation.
CONTRACTOR shall protect the Geofoam blocks from: (1) Organic solvents such as acetone, benzene, and paint thinner; (2) Petroleum based solvents such as gasoline and diesel fuel; (3) Open flames.
Placement of embankment soil cover material will require special procedures and careful selection of appropriate construction equipment to prevent damage to the Geofoam fill.
No heavy construction equipment or vehicles shall be allowed directly on the Geofoam.
Any damage to the Geofoam blocks resulting from CONTRACTOR’s vehicles, equipment or operations, shall be replaced by CONTRACTOR.
Damage to Geofoam shall be corrected as follows:
083.43.210 31 23 23.43 - 3
Slight damage less than 1 cubic foot may be left in place as is.
Moderate damage between 1 cubic foot and 35.3 cubic feet shall be filled with sand.
Geofoam blocks with excessive damage (i.e. exceeding the "moderate" category) shall be replaced with Geofoam blocks which meet the damage material design properties.
Geofoam blocks not meeting the damage criteria may be cut to eliminate the excessive damage and the remaining, undamaged, portion of the block may be used within the fill, provided the undamaged portion of the block meets all other design requirements.
QUALITY ASSURANCE
Quality assurance testing and sampling, to monitor the conformance of the Geofoam fill with the specification requirements, will be completed as directed by ENGINEER. Density, compression and geometry (dimensional tolerances) testing shall be conducted using 2-inch cubes cut from representative blocks. Blocks in conformance with contract requirements can be used to make required fills.
Testing shall be conducted on samples taken from the first 100 cubic yards of each Geofoam type manufactured for project delivery and at a rate of one test per 1,500 cubic yards thereafter. No more than 100 cubic yards of Geofoam shall be manufactured until ENGINEER has approved the material.
ENGINEER has the right to randomly sample the manufacturing plant. If any block does not conform to the physical requirements, it may be rejected by ENGINEER.
MEASUREMENT AND PAYMENT
The completed EPS Geofoam fill-work will be measured by the in-place volume in cubic yard. No credit will be given for wasted material.
PART 2 PRODUCTS
MATERIAL
Manufacturer with a minimum of 10 years documented experience in the manufacture of lightweight, geo-synthetic fill. Manufacturer must also have a UL classification in category BRYX. Manufacturer must also maintain a UL classification in category QORW that ensures physical properties in accordance with ASTM D 6817. Third-party certifications that only include ASTM C 578 physical properties will not be considered as an alternative equal and will be rejected.
Geofoam may be fabricated using material with recycled content provided the physical properties of Table 1 below are met. Unless the project dictates otherwise, the blocks shall have a height of at least 36 inches, a width of at least 48 inches, and length of at least 96 inches. All blocks shall be within tolerances of 0.5% of respective height, width and length dimensions. Additional field and/or shop trimming and cutting will be required as necessitated by the geometry of the fill being constructed.
Provide the type of geofoam blocks as indicated on the Contract Drawings meeting the following physical properties shown in Table 31 23 23.43-1 below:
TABLE 31 23 23.43-1: Physical Properties for EPS Geofoam
083.43.210 31 23 23.43 - 4
TYPE - ASTM D6817 EPS12 EPS15 EPS19 EPS22 EPS29 EPS39 EPS46
Density, min., kg/m 3, ( lb/ft3 )
11.2 (0.70)
14.4 (0.90)
18.4 (1.15)
21.6 (1.35)
28.8 (1.80)
38.4 (2.40)
45.7 (2.85)
Compressive Resistance @ 1% deformation, min., kPa (psi)
(2.2)
(3.6)
(5.8)
(7.3)
(10.9)
(15.0)
(18.6)
Flexural Strength min., kPa (psi)
(10.0)
(25.0)
(30.0)
(40.0)
(50.0)
(60.0)
(75.0)
Elastic Modulus, min., kPA (psi)
(220)
(360)
(580)
(730)
(1090)
10300 (1500)
12800 (1860)
Oxygen Index, min., volume %
24.0 24.0 24.0 24.0 24.0 24.0 24.0
Geofoam should be considered combustible and should not be exposed to open flame or any source of ignition. The Geofoam shall be manufactured using modified expanded polystyrene. Manufacturer must have a UL classification in category BRYX.
Each Geofoam block shall be marked with the manufacturer’s identification, and type.
Manufacturer shall be Insulfoam GF, ACH Foam Technologies, or approved equal.
PART 3 EXECUTION
SUBGRADE PREPARATION
Clear and grub the site in accordance with Section 31 11 00 – Clearing, Grubbing, and Stripping.
Dewater the site in accordance with Section 31 23 19 – Dewatering.
The grade on which the Geofoam fill will be placed shall be graded to the elevations shown in the contract drawings. The finish-grade shall be smooth and free from holes and protruding objects. An 8 inch leveling pad shall be constructed over the prepared grade.
The leveling pad material shall be sand, pea gravel or any locally available permeable material approved by ENGINEER.
PLACEMENT
EPS Geofoam fill shall be placed to the lines and grades shown in the plans and as directed by ENGINEER. The surface of a layer of Geofoam blocks to receive additional Geofoam blocks shall be constructed with a variation in surface tolerance of no more than
0.05 feet in any 10 ft interval. All blocks shall accurately fit relative to adjacent blocks. No gaps greater than 0.07 ft will be allowed on vertical joints.
083.43.210 31 23 23.43 - 5
The finished surface of the Geofoam immediately beneath pavement sections shall be constructed to within the tolerance of zero to minus 0.20 ft of the indicated grade.
The finished surface of the Geofoam on side slopes that receive soil cover shall be constructed to within a tolerance of plus 0.30 ft to minus 0.30 ft of the indicated grade.
Blocks placed in a row in a particular layer shall be offset 2.0 ft relative to blocks placed in adjacent rows of the same layer as shown on the plans. In order to avoid continuous joints, each subsequent layer of blocks shall be rotated on the horizontal plane 90 degrees from the direction of placement of the previous layer placed.
When needed to prevent blocks sliding during embankment construction, Insulgrip by Insulfoam, Geogripper by Foam Control, or approved equal, plates or a urethane adhesive such as Flexible Fast should be placed between horizontal layers of blocks. For the number required, refer to Paragraph 3.3 of this specification.
Blocks shall be cut using a hot wire.
Because of the light unit-weight of the geofoam fill, it is CONTRACTOR's responsibility to provide temporary weighting and/or guying as necessary until all the blocks are built into a homogeneous mass, and the pavement section as well as any soil cover are in place.
Embankment over the side slopes of the Geofoam fills shall be placed starting at the bottom of the slope in such a manner to prevent damage to the Geofoam. Finished Geofoam on side slopes shall have a minimum of 2 ft embankment cover.
The embankment material, in areas beyond the lateral distances necessary to protect Geofoam from damage, shall be compacted according to Section 31 23 23 – Excavation and Backfill for Structures. The intent of this requirement is to minimize the encompassed zone around the Geofoam fill.
During placement of the load distribution slab over the top surface of the Geofoam fill it is permissible to use rebar supports to support the reinforcing steel during concrete placement.
CONNECTORS
Connectors shall be galvanized steel multi-barbed connectors or a urethane adhesive.
Each connector shall have a lateral holding strength of at least 60 lbs when tested with an EPS15 Geofoam.
Install a minimum of 2 connectors for each 4 ft x 8 ft section of Geofoam material or as shown on contract drawings or directed by ENGINEER. Press firmly into the rigid foam until the connector is flush with the surface. Position the next foam block as specified and seat firmly before placing subsequent blocks.
- END OF SECTION –
Supplemental to
RIPRAP OR ROCK LINING
31 37 00 - 1
SECTION 31 37 00
RIPRAP OR ROCK LINING
This specification supplements APWA Standard Specification Section 31 37 00. In cases of conflict between this specification and APWA Section 31 37 00 this specification shall govern.
PART 1 GENERAL
1.1 GENERAL
A. This section covers furnishing and placing the granular filter and loose riprap materials in accordance with these specifications and in conformity with the lines, grades, and dimensions shown on the drawings or as directed by the ENGINEER.
1.2 REFERENCES
A. The latest edition of the following publications form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
B. American Society for Testing and Materials (ASTM)
ASTM C-127 Specific Gravity and Absorption of Coarse Aggregate.
ASTM C-535 Resistance to Degradation of Large-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine.
1.3 SUBMITTALS
A. The following shall be submitted:
1. Certification from a certified independent laboratory that the riprap meets the material properties of this specification.
2. A sample of the riprap to be used for construction.
1.4 STORAGE OF MATERIALS
A. Materials shall be arranged and used in a manner to avoid excessive segregation and to prevent contamination with other materials.
PART 2 PRODUCTS
2.1 GRANULAR FILTER
A. Granular filter sources shall be approved by the ENGINEER prior to use.
B. Concrete masonry or concrete pavement may not be used for granular filter.
C. Granular Filter shall be well graded with additional gradation requirements as follows:
GRANULAR FILTER GRADATIONS
% Smaller Than
Given Size By Weight
Size (Inches)
90-100 3 35-90 ¾ 0-30 No. 4 0-15 No. 16 0-3 No. 200
31 37 00 - 2
D. The CONTRACTOR shall be responsible for obtaining (by selective mining, crushing, screening, or some other method) drainage rock will meet the specified material requirements.
2.2 LOOSE RIPRAP
A. Riprap shall consist of quarry stone which is sound and durable against disintegration under conditions to be met in handling and placing, and is hard and tenacious and otherwise of suitable quality to ensure permanency in the specified kind of work.
B. Riprap sources shall be approved by the ENGINEER prior to use. Concrete masonry or concrete pavement may not be used for riprap. Riprap shall be well graded with additional gradation requirements for riprap as follows:
LOOSE RIPRAP GRADATIONS
Riprap Designation
%Smaller Than Given Size By Weight
Least Dimension (inches)
D50** (Inches)
Class I 70-100 50-70 35-50 2-10
Class II 70-100 50-70 35-50 2-10
Class III 70-100 50-70 35-50 2-10
Class IV 70-100 50-70 35-50 2-10
Class V 70-100 50-70 35-50 2-10
Class VI 70-100 50-70 35-50 2-10
31 37 00 - 3
Riprap Designation
%Smaller Than Given Size By Weight
Least Dimension (inches)
D50** (Inches)
Class VII 70-100 50-70 35-50 2-10
** D50 = Nominal particle size C. All stones shall be angular (no rounded rock will be permitted), each piece having its greatest dimensions not greater than three times its least dimensions. All stone shall conform to the following test requirements of the American Society for Testing and Materials Standards:
Requirements ASTM Standard Specific Gravity, minimum
2.60 C-127
Los Angeles Abrasion, maximum percent
40 C-535
D. The CONTRACTOR shall be responsible for obtaining (by selective mining, crushing, screening, or some other method) loose riprap that will meet the specified material requirements.
PART 3 – EXECUTION
3.1 GRANULAR FILTER
A. Prior to placement of granular filter, the subgrades to the granular filter shall be compacted and graded to the lines and grades shown on the drawings.
B. Granular filter shall generally be placed starting at the lowest elevations and working upward. The surface shall be leveled as necessary, to produce a reasonably uniform appearance and the required thickness.
3.2 LOOSE RIPRAP
A. Prior to placement of loose riprap, the granular filter shall be placed and graded to the lines and grades shown on the drawings.
B. Riprap shall generally be placed starting at the lowest elevations and working upward.
Riprap shall be placed to the minimum thickness designated on the drawings and shall be positioned in such a manner that will provide uniform distribution of the various sizes of stone and produce a well-keyed mass of rock with the least practical amount of void space. The surface shall be leveled as necessary, to produce a reasonably uniform appearance and the required thickness.
END OF SECTION
STANDARD PLAN
ROADWAY SECTION - 1 110
SHEET 1 OF 2
NOTES:
STANDARD CONFIGURATION
ROADWAY SECTION / BIKE LANE
STANDARD PLAN
ROADWAY SECTION - 2 110
SHEET 2 OF 2
PR
OF
ESS I ONA L ENG I NEER
STA T E OF UTA H
JEFFREY R.
BEVERLEY
No. 10990336-2202
PR
OFESS I ONA L ENG I NEER
S TA T E O F UTA H
JEFFREY R.
BEVERLEY
No. 10990336-2202
ORDER OF THE STATE ENGINEER
For Stream Alteration Application Number 26-57-10SA
Stream Alteration Application Number 26-57-10SA in thenameofSaltLakeCityDepartmentof Public Utilities was filed on July 10, 2026, in order to replace the Jordan and Salt Lake Canal crossing and install bank stabilization measures due to deterioration of the existing structure associated with Mill Creek, a natural stream located in Salt Lake County, Utah.
The application was made available for comment on the Division of Water Rights’ (Division) webpage, provided to pertinent governmental agencies, and to other entities as warranted, for a period of 20 calendar days, ending on July 30, 2026.
Comments received are summarized as follows:
1) NicoleFresardrepresentingtheU.S.ArmyCorpsofEngineershasreviewedtheapplication and determined that the proposed project meetsthetermsandconditionsofProgrammatic General Permit 10.
2) Aaron Murphy representing Salt Lake County Flood Control provided the following comment: The proposed work will require a flood control permit with Salt Lake County.
Please submitthefullplanset,structuraldetails,andcrosssectionsofMillCreekshowing the base flood elevation and low chord elevation of the proposed structure.
The State Engineer has reviewed the application, the information provided in support of the application, comments receivedandhasconductedadditionalinvestigationsasdirectedbystatute.
Action on an application to alter a natural stream by the State Engineer is governed by the provisions of Utah Code Ann. § 73-3-29 and Administrative Rule R655-13.
It is the opinion of the State Engineer that the stream alteration application can be approved without:
1) Impairing vested water rights.
2) Unreasonably or…