5-21 N 7th Work Scope.pdf
PDF 174 KB Posted
- Attached to
- Request for Proposal for The Exterior Rehabilitation of Redevelopment Authority Owned Real Estate
- Solicitation number
- US.262101
- Issued by
- Northampton County, Pennsylvania
About this file
This is a Scope of Work document issued by the Redevelopment Authority of Easton, Pennsylvania (RDA) for the exterior rehabilitation of 21 North 7th Street in Easton, PA 18042. The project consists of comprehensive exterior work to be completed in a single phase, including demolition of the main building's exterior surfaces, roof material, siding, doors, and windows; removal of a two-story addition to the north; reconstruction of the front porch; masonry and stonework including foundation rebuilding and repointing; carpentry and framing to address structural deficiencies; installation of new roofing with fiber glass composition shingles rated for 25-year warranty; installation of vinyl replacement windows with low-E coating and new entry doors; gutter and downspout installation; and lead-based paint abatement in accordance with an environmental assessment report dated August 22, 2022. The mandatory pre-bid site meeting is scheduled for Monday, December 7th, 2026 at 9:00 a.m., and proposals must be submitted electronically via PennBid by Monday, January 4, 2026 at 3:00 p.m., prevailing time. The RDA reserves the right to hold proposals for review for up to ninety days from the opening date before awarding the contract.
The contractor must submit a fixed-price contract covering all labor, materials, equipment, permits, and applicable taxes required for project completion. A minimum of 10 percent retainage will be held until 100 percent contract completion and system acceptance, with payment processing taking a minimum of two weeks to six weeks following work inspection. The contractor must provide a one-year warranty on all materials and workmanship from the date of substantial completion and must maintain comprehensive insurance with the RDA named as additional insured throughout the project duration. All substitutions of specified products require prior RDA approval. The document does not identify a specific set-aside, though the RFP notice states that women-owned and minority-owned businesses are encouraged to apply and indicates the RDA is an equal opportunity, affirmative action agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3-21 N 7th St-Engineer report Memo.pdf | ||
| 4-21 N 7th St-Spec Drawings.pdf | ||
| 1-21 N 7th St-Request for Proposal Packet.pdf | ||
| 2-21 N 7th St-LBP Report.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
21 N 7th STREET EXTERIOR SPECIFICATIONS 1
SPECIFICATIONS FOR THE RENOVATION OF:
21 NORTH 7th STREET
EASTON, PA 18042
ISSUED BY;
THE REDEVELOPMENT AUTHORITY OF EASTON, PA (RDA)
123 SOUTH THIRD ST.
THIRD FLOOR
EASTON, PA 18042
610 250 2068 mbrett@easton-pa.gov
SECTION 1 GENERAL REQUIREMENT
Scope The project consists of the exterior rehabilitation of 21 N 7th St, Easton, PA as described by these Drawings and Specifications, to be completed in one phase. The scope of work shall include all areas described in the supplied drawings and specified in the written project scope. Contractor shall coordinate between site and building scope as required. The written specifications and the drawings should be used in conjunction with each other when bidding and carrying out this project.
The Contractor shall submit a fixed price contract to provide all labor, materials and equipment required for the completion of his work as described in the Drawings and/or Specifications.
Contractor shall pay all applicable taxes and fees and shall secure and pay for all permits necessary to complete the work.
Work shall be performed in a neat, clean, workman-like manner. The Contractor shall clean and protect the work in progress on a basis of continual maintenance. At no time shall hazardous or dangerous material (including nails, sharp debris, broken glass) be left in the public right of way.
To the extent possible through reasonable control and protection methods, the Contractor shall supervise the performance of his work in a manner which will ensure that none of the work (his own or that by others) will be subjected to harmful, damaging or otherwise deleterious exposures during the construction period. Contractor will be responsible for appropriate disposal of all construction debris both pre-existing on the site and debris produced throughout the construction process.
The contractor is not responsible for providing a Clear Certificate of Occupancy for the building but all components of the scope shall receive passing inspections by the City of Easton Code Department. If the contractor notices any code issues that are not covered in this scope of work that pertains to the areas of this scope, it is up to the contractor to include a proposal to address the issues when submitting a response to the RFP for this project.
Contractor shall be responsible for correcting any damage caused to adjoining properties from construction activities.
All activities involving the handling of lead based paint hazards identified in the report must be overseen by a certified abatement contractor.
Layout The Contractor shall be responsible for all labor and equipment necessary to accurately lay out his work in accordance with the Drawings and Specifications. All existing conditions shown shall be verified on-site. All work shall be installed plumb, level and true. All dimensions and shall be verified on site.
21 N 7th STREET EXTERIOR SPECIFICATIONS 2
Examination of Site The Contractor shall inspect the site of the proposed work to arrive at a clear understanding of the conditions under which his/her work is to be done. No extra compensation concerning any matter about which the Contractor has or should have fully informed him/herself will be permitted.
Codes and Standards The Contractor shall control the quality of items and services to meet the requirements as detailed herein and applicable codes and standards. Design, materials, installation, testing, inspection, stamping, certification, and documentation shall conform to the applicable portions of the latest referenced editions of codes and standards. All materials shall be new and purchased specifically for this project. Any alterations to materials must be approved by the RDA.
Inspections The Contractor shall be responsible for obtaining the required permits and periodic municipal inspections and approvals of the work in progress, including Rough and Final Inspections for work covered under this scope. Copies of all Inspection Reports and/or Certificates shall be furnished to the RDA.
Temporary Utilities and Enclosure No “gun”-type space heaters allowed. Contractor shall provide temporary enclosure and/or protection of ongoing work as required ensuring complete weather protection during construction.
Provide temporary ABC fire extinguishers, (2) per floor level, until permanent fire protection systems are operational. Provide temporary fencing and security measures to maintain a secure jobsite during construction as required.
Contractor’s Insurance Contractor shall purchase and maintain such insurance as will protect him from claims which may arise out of, or result from, the Contractor’s operation under the Contract, whether such operations be by himself or by any subcontractor, or by anyone directly or indirectly employed by any of them. Coverages shall include workman’s compensation, bodily injury, personal liability, and destruction of tangible property. Proof of Insurance Certificates must be furnished to the Owner, for approval, prior to commencement of the work. The Redevelopment Authority of Easton shall be named as an additionally insured by the contractor for the duration of the project.
At the completion of the job, the Contractor shall provide guarantees covering all materials and workmanship performed by him and his subcontractors for a period of one year from the date of Substantial Completion, unless otherwise specified herein.
Waiver of Liens The Contractor and each Subcontractor engaged in any capacity for this project shall provide to the Owner a Waiver of Lien (against the Owner) concurrent with each progress payment throughout the job, including Final Payment.
Alternates and Substitutions The Contractor or any Subcontractor intending to supply a product other than that specified shall be required to submit samples, cut sheets, technical data, etc. sufficient to allow adequate review and comparison of the product by the RDA. The substituted product shall comply with all requirements set forth for the product originally specified. Substitutions of specified products will not be accepted on the job without prior approval by the RDA.
Payment Procedures
21 N 7th STREET EXTERIOR SPECIFICATIONS 3
A payment schedule shall be included in the Contract Agreement. The Contractor is to understand that payment will be released after an inspection of the invoiced work is performed.
Payment to contractor will take a minimum of 2 weeks and at times up to 6 weeks. A minimum of 10% of the contract will be held as retainage until the Contract is 100% complete, and all systems have been tested and accepted by the RDA. The project is considered complete when all aspects of the scope of work have been completed to the satisfaction of the RDA and all work requiring inspections have successfully passed.
Guarantees and Warranty The Contractor and each Subcontractor shall turn over to the RDA all guarantees of all products used in the work of the Contract. The Contractor warrants to the RDA that all materials and equipment furnished under the Contract will be new unless otherwise specified, and that all work shall be performed by labor skilled in the task being performed, and that the work will be of good quality, free from faults and defects, and in conformance with the Contract Documents.
Contractor shall be responsible for correcting any defects in materials as a direct result of installation or workmanship for a period of one year of project completion.
Document Submittals The contractor’s document submittal requirements are for engineer/owner and all authorities (as required) having jurisdiction in this project. Contractor shall pay for all fees and permits as required to complete all items within the project scope. The following documents and drawings shall be submitted for review and permission to proceed:
A. Construction Schedule.
B. Payment Schedule.
C. Shop drawings (if necessary) D. Manufacturer’s product data for all appliances and equipment for initial review by the
RDA
E. Material samples for all finishes to be installed for color/pattern selection by the RDA
Operations and Maintenance Manuals The Contractor shall submit complete manuals with the instructions for installation, operation, maintenance and storage. The manuals shall include operational adjustments, troubleshooting, instructions for assembly and disassembly, and a complete parts list showing part numbers. The manuals shall include copies of all reviewed drawings, test reports, data sheets, and catalogs for all equipment furnished. The Subcontractor shall assemble and submit the complete package.
SECTION 2 EXCAVATION AND SITEWORK
The Contractor shall exercise reasonable care during any excavation and site work operations to minimize disruption of the existing site, and shall repair all damaged areas to their former state upon completion of the complete project, including any damage caused to adjoining properties and City property such as sidewalks and roadways, etc.
During construction the contractor shall install silt fencing as needed to control mud runoff into the sidewalk and street.
See SECTION 3 FOR BUILDING DEMOLITION. After partial building demolition and foundation removal, the area shall be back filled, compacted and graded so that water is diverted from the main building and is conducive for new construction.
Contractor shall hydroseed bare areas of the lawn.
SECTION 3 BUILDING DEMOLITION
21 N 7th STREET EXTERIOR SPECIFICATIONS 4
See SECTION 14 LEAD BASED PAINT
Exterior demolition of the main building shall include removing all existing surfaces (roof material, siding, any remaining exterior finishes), doors and windows. Siding shall be removed to the original clapboard. Any rotted roof decking or sheathing shall be removed.
The entire two-story addition to the north of the main building shall be removed including steps under bulkhead door to basement. This includes the entire structure and foundation/footings (stone foundation with crawl space. The area shall be backfilled and compacted to prepare for future construction.
The front porch posts, steps and deck including the floorboards, half walls, trim and insufficient or deteriorating structural components shall be removed and prepared for reconstruction. The porch roof structure shall remain and be temporarily supported during reconstruction on the deck.
Interior demolition will include support walls where indicated. Contractor shall provide temporary supports when removing any load bearing walls.
The entire chimney shall be removed.
The shed, fence, concrete walkways (excluding the sidewalks in the public right of way) and all other debris on the property shall be removed.
Any further demolition that is needed to achieve proper conditions for reconstruction and finishing shall be performed as needed.
The first-floor powder room shall remain.
SECTION 4 CONCRETE (NA)
SECTION 5 MASONRY AND STONEWORK
Construct a concrete block wall using 8”x8”x16” cinder block to seal off opening from the exterior where basement stairs were removed. Wall shall be reinforced with rebar and concrete and tied into the existing structure. The exterior of the wall shall be water proofed with rubber sealant application prior to backfilling.
The stone foundation on the south side of the building shall be rebuilt using existing stone. Any stone not used shall be removed from the site. An opening for a hopper window shall be created when rebuilding the wall. The opening shall match the size of the existing hopper windows. The remaining foundation shall be repointed as needed.
SECTION 6 METALS (NA)
SECTION 7 CARPENTRY, MILLWORK, AND GENERAL FINISHING
See SECTION 14 LEAD BASED PAINT
Throughout the structure, all existing framing that is inadequate due to rotting, deterioration, or poor construction methods shall be corrected per City code. Contractor shall provide and install all finishes specified per manufacturer’s written instructions.
All new exterior wall framing shall be 2”x6” 18” O.C., interior partition wall framing shall be 2”x4”, floor joist construction to be sized appropriately for the span, rafters construction to be 2”x12”
21 N 7th STREET EXTERIOR SPECIFICATIONS 5 sizing at 16” O.C., unless otherwise noted. Provide double studs at jambs of all openings (unless noted otherwise). All dimensional lumber shall be #2 SPF or better. All wood framing in contact with dampness shall be pressure treated. Provide furring, nailers, blocking, etc. as required to allow proper attachment of other work.
All conventional headers shall meet IRC size requirements, minimum. All engineered LVL headers shall be sized by LVL manufacturer with a deflection limit of 1/360, typical. Footers and columns shall be installed at the specified locations where load bearing walls are to be removed.
Footers shall be a minimum 12”Lx12”Wx36”D. Contractor shall supply engineering calculations by beam manufacturer for structural headers.
See construction diagrams for new wall openings and framing configuration.
All structural items identified in the engineers report shall be addressed. The beam and jack studs that shifted as a result of building damage shall be leveled/plumbed and fastened.
The exterior wall, including studs, plates and window header in the second floor front North-west room (bathroom), shall be reconstructed where temporarily supported.
Replace all sagging roof rafters. Level and secure dormer to new rafters. Existing rafters may be jacked and sistered where possible.
Sub-floor shall be ¾” T&G CDX plywood (or equal). Sub-floors shall be glued and screwed to supports, in accordance with floor joist manufacturer’s recommendations. Fill in all areas of missing subfloor throughout. Add framing nailers/supports as needed. Fill in holes in the floors and replace rotted subfloor as needed. New shall flooring meet the level of the existing. FLoorign shall be repaired as needed.
The attic stairs shall be repaired and secured. Replacement material shall be in like kind to existing, all risers and treads that are structurally deficient shal be addressed.
Frame in existing door opening on the North side of the budling at the second floor stair landing where interior entrance exists.thsi shall be closed, sheathed and receive siding on the exiterior.
The porch floor joists that are rotted or structurally insufficient shall be replaced with pressure treated nominal lumber dimensionally adequate for the span. Porch layout and configuration shall match existing.
SECTION 8 THERMAL AND MOISTURE PROTECTION (NA)
SECTION 9 EXTERIOR FINISHING, ROOFING AND GUTTERS/DOWN SPOUT
See SECTION 14 LEAD BASED PAINT ABATEMENT.
Install ½” plywood sheathing over exiting lap siding. Install weather resistant protective membrane vapor barrier over sheathing. Contractor may use sheathing with integrated vapor barrier.
Exterior siding shall be cement fiber board 4” reveal, smooth lap clapboard siding with corner boards as indicated with a standard manufacturer’s finish. Caulk shall be manufacturer’s color match to siding manufacturer.
21 N 7th STREET EXTERIOR SPECIFICATIONS 6
Decorative trim shall be a solid, weather resistant, paintable, composite material to meet the design as specified in the elevation drawings. Trim shall be properly flashed and sealed above windows and areas where water may penetrate. See drawings for trim and molding configurations. All seams and nails holes shall be filled.
Porch decking, stair risers and treads shall be mahogany (or equal) T&G oil finished.
Porch ceiling shall be ½” x 5 1/8” PVC paintable beaded ceiling board, color TBD. Install finishing bed mould or cove around perimeter of the ceiling.
Porch columns shall be structural Victorian style 6”x6” dimensional. Railing spindles shall be 4” turned Victorian style with correlating top and bottom rail. Railing and post shall be paintable composite or cedar. Contractor shall apply three coats of exterior grade paint including 1 coat of primer and 2 coats of finish, Color TBD. Handrails shall be installed on both sides of the front steps. The handrail on the building side of the steps shall be wood and may be fastened to the building itself and painted to match the porch railings.
Contractor shall install metal house numbers in bronze or black finish, minimum 4” high, approved by owner.
Contractor shall install a black metal wall mounted mailbox at the front door with lock.
Roofing
“Total tear off” means the complete removal of 100% of the shingles and underlayment so as to fully expose 100% of the existing roof deck. Replace all rotted wood with plywood. Plywood panels shall be structural 1, C-D interior APA plywood with exterior glue of a thickness no less than 1/2 “. Panels shall span over a minimum of three rafters or truss chords. The substitution of
OSB or other wafer type sheathing is prohibited, except where an OSB type roof sheathing exists.
Note: when installing the new roof, contractor should take into consideration the new depth of the exterior wall after the insulation and siding is installed and should accommodate for this increased wall depth.
Water proofing underlayment: Apply the self adhering waterproofing membrane directly to the bare (exposed) wood deck. Apply the membrane parallel to the eaves, starting from the bottom edge of the deck over lapping the metal drip edge installed along the eaves.
New roofing shall be fiber glass composition meeting the EnergyStar® Program criteria, UL Class
A fire resistance, ASTM D3462, ASTM 3018 Type 1 conforming to CSA standard A123. All requisite underlayment and trim will be used and installed per manufacturer’s written instructions for a 25-year warrantee. Install roof shingles in accordance with manufacturer’s instructions.
Roofing product shall be GAF Slateline or equal, Color TBD. Install ridge vent with cao shingles to match the rest of the roof.
Gutters/Downspouts:
Install gutters and downspouts along the rear of the building. The yankee gutter on the on the front of the building shall be restored to proper functioning order with new downspout installed.
21 N 7th STREET EXTERIOR SPECIFICATIONS 7
General:
Gutters shall be installed so that water flow from the roof will be caught by the gutters. Each downspout shall drain a maximum of 600 sqft of roof area and downspouts shall be spaced to drain a maximum of 30 linear feet of gutter. Downspouts shall be located so that water will be diverted a minimum of 30” away from the structure and will drain away from the foundation without draining onto adjoining properties.
Gutters shall be seamless 6” k style. Aluminum gutter material shall be a minimum of .027 inches in thickness. Downspouts and downspout extensions shall be 3”x2”; corrugated rectangular material to match gutters. Splashblocks shall be precast concrete.
Gutters shall have a uniform slope at the rate of 1/16” per foot to downspout. Gutters shall be installed under drip edge where it exists. Hangers shall be securely fastened and shall be spaced a maximum of 36” on center. Strap hangers shall be concealed using a mastic designed for this purpose.
Downspouts shall be securely fastened at top and bottom, if over 10’ in length a third intermediate fastener shall be installed equal distance between the top and bottom fasteners. Elbows shall be fastened with sheet metal screws. Installation of gutters, downspouts and accessories shall be in accordance with trade standards.
SECTION 10 DOORS AND WINDOWS
See SECTION 14 LEAD BASED PAINT ABATEMENT.
New windows shall be vinyl construction replacement with low-E coating (u-value of 0.30 or better). Provide all standard hardware and screens for operable units. Unless otherwise specified windows shall fit existing rough openings, double hung, two-over two configurations, tilt in with half screens. Units shall be new construction with integrated trim, sill and j channel.
The second floor bathroom window shall have obscured manufacturers’ privacy glass in bottom sash.
Vinyl awning hopper windows shall be installed in all basement window openings.
Front entry door shall be pre-hung fiberglass or aluminum entry doors with ¾ lite, frosted/obscured glass with bottom raised panel. Hardware shall include handle with lockset and deadbolt. The existing transom opening may remain with new insulated glass installed, trimmed and fully sealed for weatherization or door may be purchased with integrated transom to fit the size of the original window.
Side door shall be pre-hung fiberglass or steel entry door with ½ lite without divided grill.
Contractor is not responsible for insulating gaps in windows and doors. The exterior must be weather tight.
Doors shall be painted on the exterior side only, color TBD by the RDA. Provide all hardware and deadbolt locks for all entry doors, finish TBD. Hardware shall include lockset handle with deadbolt, bronze or black finish.
21 N 7th STREET EXTERIOR SPECIFICATIONS 8
SECTION 11 EQUIPMENT (NA)
SECTION 12 PLUMBING AND HVAC SYSTEMS
Contractor shall provide product information on proposed equipment, locations, piping layout including returns, and all accessories for review prior to installation.
All domestic supply water piping shall be PEX tubing where ever possible. All water supply lines will be insulated with closed cell polyethylene foam. All sewer piping shall be PVC with sound insulation at verticals. Contractor shall provide design & code drawings, including riser diagram, if required. Further coordination of piping locations with shall be done in accordance with the supplies construction drawings. Provide as shop drawing to RDA for review prior to submittal to city.
All plumbing fixtures must meet the EPA’s WaterSense program standards.
Install a frost free sillcock at the rear of the house with interior shut off.
Replace main sewer vent with PVC starting at main line in basement.
First floor powder room shall remain and be brought up to functional order. Existing fixtures shall be used.
SECTION 13 ELECTRICAL WORKS
All electrical work shall meet the latest City code requirements.
All work shall be in accordance with applicable codes and local utility requirements. Electrical Contractor shall provide all further design and engineering as necessary, by qualified personnel, to properly size and locate all components of the work.
Wiring shall be copper throughout, of appropriate gauge. All exterior outlets shall be weatherproof type. Outlets in bathrooms, kitchens and exterior outlets shall be ground-fault type with-in 6 feet of a water source or required by code. All bedrooms will have arc fault receptacles installed.
Where outlets are not specifically identified in the drawings, all locations, types, and quantities shall be per the City Code.
Install four ceiling lights in the basement with protective plastic cages. One light shall be with in 36” of the electric service panel switched at the top of the basement stairs with the other basement lights.
Install one functional outlet in each area of the house as indicated on plans. Install one ceiling mount white outlet box lamp holder with bulb and cage in each area and switched as indicated.
Install 2 exterior grade recessed ceiling fixtures evenly space in the front porch ceiling switched to inside the front door. Install a wall mount exterior barn sconce over side exterior door switched to inside the door, bronze or black finish.
All final fixture selections will be made by the RDA.
Combination Fire/Carbon monoxide detectors (hard-wired units) shall be installed at one per every approximate 1,000 square feet and in the basement and second floor hall units shall be hardwired with battery backup, per code. Locations are provided in the electrical plan.
21 N 7th STREET EXTERIOR SPECIFICATIONS 9
SECTION 14 LEAD BASED PAINT ABATEMENT/ENVIRONMENTAL
Painting requirements: Refer to LEW Environmental Services report dated August 22, 2022, project #220826 for lead-based paint assessment. Dust wipe clearance is not required for this portion of the project. A lead abatement contractor must be used on the project for all lead hazards identified in the risk assessment.
• All interior/exterior prep and painting shall be performed by a state of Pennsylvania licensed lead abatement contractor. If the general contractor does not have the proper credentials, he must subcontract this portion of the job to an approved abatement contractor. The following documentation must be submitted prior to work activities:
o Contractor’s lead abatement license o All paperwork to be submitted to the Redevelopment Authority of Easton, PA, attention: Michael Brett Deputy Director, RDA.
A lead dust wipe clearance will not be required at this point but all exterior lead hazards shall be addressed.