This is a Deliverables Schedule (Attachment I) that outlines the milestones and deliverables required for a task order related to USACE water management systems work. The schedule specifies seven primary deliverables with corresponding delivery dates measured from either the Task Order award date or the Notice to Proceed (NTP).
The initial deliverables include a Draft Work Plan due 15 days after Task Order award, followed by pre-work coordination meeting materials (agenda due 2 days prior to the meeting and minutes due 2 days after). A Final Work Plan is due 30 days after Task Order award. Subsequent deliverables include USACE Water Management Systems familiarization completion (NTP + 60 days), web page verification and edits with embedded link verification (NTP + 120 days), modification of processes to run in CWBI systems (NTP + 300 days), and process improvements completion (NTP + 240 days). All deliverables are marked as "completed" status items, indicating the contractor must demonstrate full completion by the specified dates.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT I
Deliverables Schedule
Task No.
Item
Milestone or Deliverable
Delivery Date*
5.4.1.1 Draft Work Plan
15 days of Task Order award
5.4.1.2 Provide pre-work coordination meeting agenda
2 days prior to meeting
5.4.1.2 Provide pre-work coordination meeting minutes
2 days after meeting
5.4.1.3 Final Work Plan
30 days of Task Order award
5.4.2 USACE Water Management Systems
familiarization – completed. NTP + 60 days
5.4.3 Web page verification and edits completed
including verifying embedded links.
NTP + 120 days
5.4.4 Modify processes to run in CWBI – completed. NTP + 300 days
5.4.5 Process improvements – completed. NTP + 240 days
| 1.0 General. The Contractor, as an independent contractor and not as an agent of the Government shall, in accordance with the terms and conditions more particularly set forth below, furnish all labor, management, facilities, supplies, equipment and ... |
| 2.0 Definitions. Throughout this performance work statement these terms are defined as follows: |
| 5.4.1 Task 1. Work Plan and Pre-work Coordination Meeting. Based on information and deliverables (See Attachment I, Deliverables Schedule) described in this PWS, the contractor shall prepare a Work Plan. The Work Plan shall include all pertinent pro... |
| Project schedule including work and meeting schedules and milestones, anticipated start and end dates for each task, reporting process and schedule, equipment deployment and removal, draft report review, and tasks identified below and agreed to duri... |
| Data collection and analysis methods for the objectives of the evaluation. |
| A complete schedule including specific requests for NWP services and assistance required for completion of the contract. |
| Listing of Equipment type use and deployment locations and schedules. |
| Detailed information regarding design and operational specifications for all equipment to be utilized for this contract. |
| Contractor Quality Assurance/Quality Control Plans (QA/QC): |
| o The quality control system shall consist of plans, procedures, and organizations necessary to produce an end product which complies with the requirements of this contract, data processing procedures, and protocols. |
| o The system shall cover all operations, both on-site and off-site. Quality assurance and quality control (QA/QC), along with surveillance of quality during the project, will be critical to successful study implementation. |
| o Compliance with all sections of this contract and underlying Single Award Task Order Contract (SATOC), as appropriate, including items such as safety plan(s), Job Hazard Analysis (JHA), e-Verify, OPSEC requirements as described below. |
| 5.4.1.1 Draft Work Plan. The contractor shall prepare a draft Work Plan and deliver it electronically for acceptance to the COR within 15 days of contract award. |
| 5.4.1.2 Pre-work Coordination Meeting. Upon submitting a draft Work Plan, the contractor shall meet with NWP staff for a pre-work coordination meeting to review the document. All work must be closely coordinated with project staff and district staff. |
| 5.4.1.3 Final Work Plan. A final Work Plan addressing all comments shall be submitted no later than (NLT) 30 calendar days after contract award and prior to on-site activities. |
| 5.4.2 Task 2. USACE Water Management Systems Familiarization. This task involves familiarization with the USACE national Water Management data system and tools, the regional data system and tools, Water Management data, the use of the HydroDCS and HR... |
| The USACE national Water Management data system, CWMS, includes the CWMS database, CWMS-VUE and CWMS-CAVI, HEC models, HEC-DSS, CDA, A2W, CWBI, and the USACE Water Management GitHub. Information regarding HEC can be found at https://www.hec.usace.arm... |
| The USACE Water Management Northwest Region data system (RWCDS) architecture includes a data exchange server in the Amazon AWS Cloud resources, public web servers, use of Sun T7 Solaris servers and X86 Linux servers running RedHat, COOP configuration... |
| Familiarization with Water Management data includes understanding the types of data collected, how the data is collected, acquired, posted to the database, and disseminated. One of the tools used for interacting with the data include the OpenDCS soft... |
| The HydroDCS and HRIT appliances are used to acquire data using the OpenDCS software for operators at USACE dams. An accessible HydroDCS instance is located at https://cenwp.hydrodcs.com. |
| Water Management develops and manages web pages in support of the USACE Water Management mission. These web pages may be internal only, public facing, or places on both internal and public facing web servers. Processes are in place to keep resources ... |
| The USACE Northwest Region water managers interact with numerous other federal and state agencies along with public utilities and other stakeholders of the water resources in the region. The main federal agencies involved in water resource management... |
| 5.4.3 Task 3. Web Page Verification and Edits. Modify references and file links to external resources embedded in the web pages so that the links in the web pages function properly on the main web server and the CROHMS web server. Assure all embedd... |
| 8.2 Government Holidays. The Contractor is not required to work on the following federal holidays: |
| 8.4 Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts. In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department o... |
| 10.0 Attachments. |
| ATTACHMENT I |
File details come from the government source that posted it. Updated .