About this file
This is a Bid Worksheet for an Acquisition Request for Bid issued by the North Carolina Department of Public Safety Emergency Management for Storm 4827, Project 122 (McDowell Group 2). The worksheet covers property acquisitions and site demolition services across thirteen properties located in Marion and Old Fort, North Carolina. The properties include residential structures, a 32-unit apartment complex, and various outbuildings such as carports, sheds, and workshops. Vendors are required to provide itemized pricing for acquisition-related activities (intake/DOB calculation, appraisal, title research, document preparation, legal fees, and closing fees) and site demolition activities (asbestos/lead inspection, structure demolition, UST/other clearance, grade/seed, and property-specific demolition items). Vendors must complete all property worksheets in their entirety, provide construction management costs and profit/overhead costs as applicable, specify units of measure and quantities for all line items, and provide an overall project timeframe in days from Notice to Proceed through project closeout.
The worksheet requires vendors to submit bids with all costs itemized and auto-calculated through the Bid Summary Sheet. Vendors are prohibited from modifying the worksheet format, adding or removing line items, or altering formulas; noncompliance constitutes grounds for proposal rejection. Vendors must verify all calculations and immediately contact the State regarding any errors or concerns. The bid summary auto-calculates work phase totals for Acquisition, Site Demolition, Profit & Overhead, and Construction Management Costs, with a Grand Total field for the overall project cost. Vendors must strive to meet the specified project timeframe and any deadlines established by North Carolina Emergency Management (NCEM) in support of Hazard Mitigation Grant Program (HMGP) goals, with the submitted timeframe serving as an evaluation criterion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 4827-0013 (Batch 2) - Rutherford - Acquisition Bid Worksheet.xlsx | XLSX spreadsheet | |
| 19-IFB-2464765364-RMT Foothills Group 3 Acquistion and Demolition.pdf | ||
| 4827-0017- McDowell County Group 1- Acquisition Bid Worksheet.xlsx | XLSX spreadsheet | |
| 4827-0091 City of Shelby Acquisition Bid Worksheet.xlsx | XLSX spreadsheet | |
| 4827-0013 (Batch 1) - Rutherford - Acquisition Bid Worksheet.xlsx | XLSX spreadsheet | |
| 4827-0200 McDowell County Acq Bid Worksheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SUMMARY SHEET
| North Carolina Department of Public Safety |
| Emergency Management |
| ACQUISITION REQUEST FOR BID WORKSHEET |
| RFB NUMBER: |
| VENDOR: |
| BID DATE: |
| BID SUMMARY | |
| WORK PHASE | TOTAL |
| ACQUISITION | $0.00 |
| SITE DEMOLITION | $0.00 |
| PROFIT & OVERHEAD | $0.00 |
| CONSTRUCTION MANAGEMENT COSTS | $0.00 |
| GRAND TOTAL: | $0.00 |
TOTAL PROJECT TIME (DAYS):
| NOTES: | **Please read the following information carefully** |
| 1) The Vendor shall fill out this Bid Worksheet in its entirety. | |
| 2) Modifications to this worksheet (i.e., adding/removing line items, modifying formulas, etc.) are not permitted. Noncompliance shall constitute grounds to reject Vendor's proposal. | |
| 3) Vendor is responsible for providing information in light blue cells. | |
| 4) This Bid Summary Sheet auto-calculates the Work Phase Totals (Acquisition, Site Demolition, Profit & Overhead, and Construction Management Costs) from subsequent Property Worksheets. Vendor shall verify that all amounts for each individual phase and the Grand Total have been calculated correctly. Any errors or concerns with this worksheet shall be brought to the immediate attention of the State; Vendor shall follow the contact method as specified in the RFB. | |
| 5) Vendor must provide Construction Management Costs and Profit & Overhead Costs for each property, as applicable. | |
| 6) An individual Property Worksheet must be filled out in its entirety for EACH property. Property Worksheets are included within this Bid Worksheet. | |
| 7) Vendor shall note the unit of measure for each line item listed on the Property Worksheet (i.e., linear feet, square feet, hour, flat rate, or any reasonable unit of measure). Vendor shall input a Unit Price and Quantity for every line item (a '1' must be entered in the Quantity column for flat or individual costs). | |
| 8) Additional rows for miscellaneous costs have been provided for each property. Three additional rows per work phase have been provided if the Vendor determines other eligible costs should be provided in their bid. If Vendor elects to use this category, a description of the cost must be provided along with the unit of measure, unit price, and quantity. | |
| 9) Vendor shall provide the anticipated overall project timeframe (i.e., total time to complete work for all properties listed). This estimate, in days, shall begin with the Notice to Proceed and end at closeout for all contracted work. Vendor shall strive to meet this timeframe, as well as any timeframes put forth by NCEM, barring any unexpected acts of nature requiring a change in the Scope of Work and/or Change Order(s). It is the responsibility of the Vendor to create a time schedule, including any phasing or work overlap, in order to complete all projects in the specified timeframe. The timeframe submitted by each Vendor shall be used by the State when evaluating bids as to meet HMGP goals and deadlines. |
REF-SHEET2-DONOTMOVE
*THIS SHEET HAS INTENTIONALLY BEEN LEFT BLANK. DO NOT DELETE.
Opt-PROPERTY (1)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 57 Geneva Drive |
| PROJECT #: | 122 | CITY: | Marion |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | Workshop Annex | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (2)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | ||||||
| STORM #: | 4827 | STREET ADDRESS: | 89 Westwood Chateau Dr #101-233 | |||
| PROJECT #: | 122 | CITY: | Marion | |||
| *32 Units on Property | ||||||
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Central Sewer | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (3)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 132 Hummingbird Drive |
| PROJECT #: | 122 | CITY: | Old Fort |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | Carport/ pole barn | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (4)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 169 Commerce Street |
| PROJECT #: | 122 | CITY: | Old Fort |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Central Sewer | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (5)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 222 Geneva Drive |
| PROJECT #: | 122 | CITY: | Marion |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (6)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 245 Geneva Drive |
| PROJECT #: | 122 | CITY: | Marion |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (7)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 257 Hunnicutt Mountain Road |
| PROJECT #: | 122 | CITY: | Marion |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Central Sewer | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (8)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 286 Hebron Hill Road |
| PROJECT #: | 122 | CITY: | Old Fort |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (9)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 293 Geneva Drive |
| PROJECT #: | 122 | CITY: | Marion |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | Tiny Home Structure | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (10)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 381 Commerce Street |
| PROJECT #: | 122 | CITY: | Old Fort |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Central Sewer | $0.00 | ||||
| Misc. | Carport (3 car) | $0.00 | ||||
| Misc. | Wooden Outbuilding (x2) | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (11)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 415 Geneva Drive |
| PROJECT #: | 122 | CITY: | Marion |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | Shed (x2) | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (12)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 497 Graphite Road |
| PROJECT #: | 122 | CITY: | Old Fort |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00
Opt-PROPERTY (13)
| ACQUISITION REQUEST FOR BID PROPERTY WORKSHEET | |||
| STORM #: | 4827 | STREET ADDRESS: | 17001 US 221 North |
| PROJECT #: | 122 | CITY: | Marion |
| WORK PHASE | ITEMIZED WORK | UNIT OF MEASURE | UNIT PRICE | QUANTITY | ITEMIZED COST | |
| Acquisition | Intake / DOB Calculation | $0.00 | ||||
| Appraisal | $0.00 | |||||
| Title Research | $0.00 | |||||
| Document Prep | $0.00 | |||||
| Legal Fees | $0.00 | |||||
| Closing Fees | $0.00 | |||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Acquisition Total: | $0.00 | |||||
| Site Demolition | Asbestos / Lead Inspection | $0.00 | ||||
| Structure Demolition | $0.00 | |||||
| UST / Other Clearance | $0.00 | |||||
| Grade / Seed | $0.00 | |||||
| Misc. | Septic System | $0.00 | ||||
| Misc. | Pump house for well | $0.00 | ||||
| Misc. | N/A or Provide Details | $0.00 | ||||
| Site Demolition Total: | $0.00 | |||||
| Other | Profit & Overhead | |||||
| Construction Management Costs | ||||||
| Other Total: | $0.00 |
Property Total: $0.00