This document package includes a federal contract solicitation and related questions and responses file. The solicitation seeks proposals for new boiler system projects at the Haines and Skagway Land Ports of Entry in Alaska. Offerors must provide design and construction services for replacement of existing boiler systems with new oil-fired boilers rated at 5 million BTUs or less per hour. Proposals are due December 14, 2021. The pre-proposal conference was held virtually on November 15, 2021 and site visits took place on November 17-18, 2021. The General Services Administration Public Buildings Service Region 10 is the contracting agency. Access to controlled unclassified information attachments requires completion of provided forms. The questions and responses file clarifies requirements around fuel piping scope, conduit and baseboard reuse, and long-term operation and maintenance responsibilities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 47PL0122R0001_AM0001.pdf | ||
| Exhibit 1 GSA Affiliated Custom Accounts.pdf | ||
| 47PL0122R0001 Generated PDF with TOC.pdf | ||
| Exhibit 0 Read Me First - CUI Document.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
R10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
10PQCB2
Kimberly Johnson, Supervisory Contracting Officer
See Description on Modification Continuation Page.
[See Description of Modification Continuation Page]
10PQCB2
Acquisition Management Division Construction Branch Team B 400 - 15th Street SW Auburn, WA 98001-6599 USA
Acquisition Management Division Construction Branch Team B 400 - 15th Street SW Auburn, WA 98001-6599 USA
EQ10PCPB2-22-0001
47PL0122R0001
1 2
12/7/2021
11/9/2021
PAGE OF PAGES
Solicitation number 47PL0122R0001 entitled "New Boiler Projects for Skagway, AK and Haines, AK" is hereby amended as follows"
1. The Question and Response period has ended.
2. To provide Questions and Responses as of 12/07/2021.
3. All other terms and conditions remain unchanged by this amendment.
Attachment(s): Questions and Responses as of 12/07/2021.
47PL0122R0001/0002
Description of Modification Continuation Page
Amend No. Item #
Date
Submitted
Question
Type
(Technical or
Admin) Question
Response
Date Response
Responded
By
0001 01 12/2/2021 Admin
I understand that we are to submit two separate proposals, but they are combined on one SF1442 and the pricing schedules are also combined.
Are you wanting us to submit two different bid bonds, one for each of the proposals or are you wanting one for the entire SF1442? 12/6/2021 Yes; two different bid bond are required per project proposal. GSA CO/Mark
0001 02 12/3/2021 Technical
Are pictures available of interior finishes or copy of interior finish legend for each building ? 12/6/2021 No pictures are available to my knowledge GSA PM/Paul
0001 03 12/6/2021 Technical
Can you please address the following?
1 - Is the Fuel oil tank being replaced?
2- Are we assuming that ventilation rates from original design are to remain? 12/6/2021
1. Per SOW, Section 2.1.1.3: Fuel Oil System - Piping: Contractor shall design and install new fuel oil transfer pump, associated fuel oil piping, leak protection, and required appurtenances to serve the new boiler equipment. New fuel oil system shall be designed in accordance with latest codes and standards, including NFPA 30.
Fuel oil tank is NOT to be replaced as part of this project.
2. Ventilation rates are to be determined during the design phase and are to take into account current existing conditions of each facility. The ventilation rates from the original design are NOT to be used.
GSA PM/Paul
0001 04 12/6/2021 Admin
1. Can you please clarify which factor you would like the PPQ’s in?
2. Can CPARS be submitted for factor 2 instead of PPQ’s?
3. For Factor 2: Experience of Comparable Projects we would like to see if instead of the last 3 years can it be 7 years?
4. Can previous GSA PPQ’s be used in the solicitation proposal? 12/6/2021
1. PPQ’s are a FACTOR 2 requirement.
2. No, we are looking for no more than a 2-page narrative.
3. This factor requires relevant projects “completed within the last 3 years”.
4. The contractor must ensure that the PPQ’s provided meets the requirements of FACTOR 2 of this solicitation. GSA CO/Mark
0001 05 12/6/2021 Admin Are proposals due 12/13/2021 or 12/14/2021? 12/6/2021
Correction: RFP section I.H. Reciept of Offers at paragraph C(1):
Proposals Due Date should read: December 14, 2021. *Proposal are due
December 14, 2021 at 10:00 AM AKST. GSA CO/Mark
0002 06 12/6/2021 Admin
Attachment 4-Exhibit 2-Project Experience, Attachment 5-Exhibit 3-Key
Personnel Resume Form; Attachement 6-Exhibit4-Past Performance.
Where can we find these forms? 12/7/2021
All exhibits are available on the the GSA Controlled Google Drive. To gain access offerors are required to complete Exhibit 0 and Exhibit 1 and email the forms with their GSA Afflilitated Custom Account (GAGA) to the CO and CS listed in the RFP for access. GSA CO/Mark
0002 07 12/6/2021 Admin
Can you please confirm if CPAR is acceptable. In Lieu of Past
Performance. 12/7/2021
CPARS is acceptable for FACTOR 4-Past Performance of Offeror.
Offerors are reminded that, while the Government may elect to consider data obtained from other sources, the burden of providing thorough and complete performance information rests with the Offeror GSA CO/Mark
0002 08 12/6/2021 Admin
Also, Amd 1 says PPQ’s are in Factor 2. I am a little confused as to what goes in Factor 4 if PPQ’s go in Factor 2. 12/7/3032
Correction of Amendment 0001: Past Performance Questionnaire (PPQ) are Factor 4-Past Performance of Offeror not Factor 2 GSA CO/Mark
0002 09 12/6/2021 Admin Can any positions be dual roles such as a Superintendent and SSHO 12/7/2021
The RFP Factor 1-Proposed plan and Management Approach does not ask for specific positions. The decision on what position to include resides with the offeror. GSA CO/Mark
0002 10 12/6/2021 Technical
What is GSA’s intent if we encounter any asbestos or hazardous materials? 12/7/2021
To date, no asbestos or hazardous materials have been identified at either location. If for some unexpected reason it is both identified and encountered during construction, an RFI would be written by the
Contractor and GSA would evaluate at that time. GSA PM/Paul
0002 11 12/6/2021 Admin What is the page limitation for resumes? 12/7/2021 The page limit for resumes is three (3) pages. GSA CO/Mark
0002 12 12/6/2021 Admin What is the page limitation on project examples? 12/7/2021 The page limit for Factor 2 in the RFP is two (2) pages per project. GSA CO/Mark
0002 13 12/6/2021 Admin Do you want project examples from the design firm and offeror? 12/7/2021
The RFP Factor 2 ask for the "Experience on Comparable Projects" for the Offeror. GSA CO/Mark
0002 14 12/6/2021 Admin Would GSA consider excluding the manufacturer data in the page limits? 12/7/2021
The manufacture data is not a part of the five (5) page narrative page limit. GSA CO/Mark
0002 15 12/6/2021 Admin
If GSA would like resumes, would GSA consider excluding them from the page count? 12/7/2021 The page limit for resumes is three (3) pages GSA CO/Mark
0002 16 12/6/2021 Admin Would GSA consider excluding an Org Chart from the page count? 12/7/2021 Yes, GSA will exclude an Org Chart from the page count. GSA CO/Mark
0002 17 12/6/2021 Admin
Section B Factor 2: Experience on Comparable Projects – 8 page limit
(max of 4 projects each with a 2 page limit) 12/7/2021 Page limit is two (2) per project GSA CO/Mark
Questions and Responses as of 12/07/2021
0002 18 12/6/2021 Admin
Section C Factor 3: Schedule – Max 3 page schedule narrative. No page limited identified for schedule 12/7/2021 The page limit for the narrative is three (3) pages. GSA CO/Mark
0002 19 12/6/2021 Admin Section D Factor 4: Past Performance – No page limit identified 12/7/2021
There are no page limits for Factor 4. Section II.D Technical Proposal states the offeror's technical proposal is limited to 40 pages total. GSA CO/Mark
0002 20 12/6/2021 Technical
1) 2.1.1.3. Fuel Oil System - Piping: Contractor shall design and install new fuel oil transfer pump, associated fuel oil piping, leak protection, and required appurtenances to serve the new boiler equipment. New fuel oil system shall be designed in accordance with latest codes and standards, including NFPA 30.
Where is the demark of where the fuel piping stops in each project?
Please confirm that the fuel piping replacement is inside of each boiler room.
2) Can the baseboard covers be re used if they are in good condition?
3) 2.1.1.10.2. New oil-fired boilers with a heat input capacity equal to or less than 5Mbtu/hr are required to have a tune up every five years. [See 40
CFR
63.11223(a) and (e)]
1. The first five-year tune-up must be no later than 61months after the initial startup.
2. Each five-year tune-up must be conducted no more than 61 months after the previous tune-up.
Are these tune ups required to be performed by the contractor or the
O&M operator?
4) 2.1.1.2 Re use of existing conduit and conductors.
If the existing conduit is capable of handling the wire and meets all codes can the electrical conduits on this project be reused?
Can the control wiring conduits be reused?
12/7/2021
1. Demark for the fuel piping is at the fuel tank. Fuel oil tank is NOT to be replaced as part of this project. Fuel piping replacement is inside the mechanical spaces of each building.
2. Baseboard covers can be reused if in good condition. However, each cover is to be evaluated during construction and determined, in conjunction with GSA, that they can be reused, refinished, and/or need to be replaced.
3. Reference Section 2.1.1.10 header paragraph: Contractor is required to provide a closeout submittal for a long term O&M plan which includes subparagraphs 2.1.1.10.1 through 2.1.1.10.4. These tuneups wll be performed by the O&M operator upon completion and turnover of the project.
4. Existing conduits (electrical and controls) are to be evaluated and determined if they are in acceptable condition. If the existing conduits are determined, in conjunction with GSA, that they are in acceptable condition and are capable of handling the wire while also meeting all current codes, they can be reused. All wiring within the conduits associated with this project need to be replaced with new.
GSA PM/Paul
Questions and Responses as of 12/07/2021