Activity ID Activity Name Float Dur Start Finish

DBB ScopDBB Scope Revised 11/28/2017 0 593 15-Dec-17 15-Apr-20

AdminisAdministrative 0 593 15-Dec-17 15-Apr-20

50 Issue RFP 0 0 15-Dec-17*

60 Receive GC technical/management and price proposals 0 0 23-Feb-18

A1000 Award Contract 0 0 20-Apr-18*

1000 NTP 0 0 30-Apr-18

2000 Mobilization 68 15 1-May-18 21-May-18

2010 Substantial Completion 0 0 18-Feb-20

2012 Punchlist - Contract Deliverables 0 20 18-Feb-20 16-Mar-20

3000 Construction Complete 22 0 16-Mar-20

2020 Contract Close-out 0 22 17-Mar-20 15-Apr-20

1st Floor1st Floor USC (Grand Jury) 69 337 12-Jul-18 6-Nov-19

A1050 Submittal & Approval 69 60 12-Jul-18 4-Oct-18

A1020 Safeoff & Demolition 69 22 5-Oct-18 5-Nov-18

A1030 Build-out 69 255 6-Nov-18 6-Nov-19

Future GFuture GSA Tenant 330 111 22-May-18 26-Oct-18

A1260 Safeoff & Demolition 330 21 22-May-18 20-Jun-18

A1270 Build-out of Shell 330 90 21-Jun-18 26-Oct-18

3rd Floo3rd Floor EPA 29 291 12-Nov-18 7-Jan-20

A1210 HP Contract Finish DB Contract 0 0 12-Nov-18*

A1060 Selective Demolition 0 22 3-Sep-19* 2-Oct-19

A1070 Build-out 29 65 3-Oct-19 7-Jan-20

4th Floo4th Floor EOIR & Adjacent Hallway Upgrade 68 241 29-Nov-18 7-Nov-19

A1080 Safeoff & Demolition 68 21 29-Nov-18 28-Dec-18

A1090 Build-out 68 220 31-Dec-18 7-Nov-19

4th Floo4th Floor EPA & Adjacent Hallway Upgrade 109 200 29-Nov-18 11-Sep-19

A1110 Demolition & Demising Wall 109 20 29-Nov-18 27-Dec-18

A1120 Build-out 109 180 28-Dec-18 11-Sep-19

4th Floo4th Floor GSA Conference Room and Adjacent Core Upgrade 68 132 22-May-18 28-Nov-18

A1140 Safeoff & Demolition 68 22 22-May-18 21-Jun-18

A1150 Build-out 68 110 22-Jun-18 28-Nov-18

GeneratoGenerator, Feeder for Fire Pump, & Transfer Switches 0 413 1-May-18 16-Dec-19

A1170 Submittal & Approval 0 108 1-May-18 2-Oct-18

A1180 Procurement 0 100 3-Oct-18 25-Feb-19

A1190 Installation & Startup 0 205 26-Feb-19 16-Dec-19

Fire PumFire Pump 0 248 26-Feb-19 17-Feb-20

A1220 Submittal & Approval 117 88 26-Feb-19 28-Jun-19

A1240 Installation 0 43 17-Dec-19 17-Feb-20

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2018 2019 2020

Schwartz FY16 DBB

Actual Work Remaining Work

Critical Remaining Work Milestone