This is a Questions and Answers document for a BIE Tenant Fit Up RFI (Request for Information) related to an office suite remodel project at the Bismarck Federal Building. The document clarifies that work will only be performed in offices 365, 358, and 360, with specific requirements for lead paint removal, drywall repair, and painting.
Key details include: contractors must provide their own dumpsters but GSA will identify placement location; contractors are responsible for moving GSA furniture; only loose/peeling lead paint needs to be removed rather than full abatement; GSA will provide a lead report; drywall must be finished to Level 4 with orange peel texture; existing baseboards should be kept and repainted; and the hallway side of doors do not require painting but door frames must be painted up to the threshold. The project involves removing a tack board between offices 360 and 358 and painting both sides of that door and trim. No contractor parking is provided on site.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIE Tennant Fit UP RFI - 11/26/24
1. Will the hallway and elevator require any work? Or will work strictly only be performed in offices 356, 358, and 360?
a. Work will only be in offices 365, 358 & 360.
2. Will contractors be expected to replace/repair drywall after removing lead paint?
a. Repair drywall after scraping the loose lead paint.
3. Will contractors be responsible for moving GSA furniture?
a. Yes.
4. Just to confirm, will dumpsters be provided for the carpet project?
a. Dumpsters will be provided by the contractor
5. Will a lead report be given to contractors by the GSA?
a. The GSA can provide a lead report.
6. Should contractors hire a tester before beginning any abatement work?
a. Not required.
7. We would like to know how far lead may have penetrated and if wall substrates may require restoration too
a. Only scrape loose/peeling paint as needed.
8. Will the current baseboards need to be replaced by carpet team or just kept as is and repainted?
a. Keep the existing baseboard and repaint as per the SOW.
9. Will the GSA be open to receiving lead stabilization services instead of a full abatement?
a. Full abatement is not required. Only remove any peeling or loose paint
10. Is a full LCP Abatement required on all items requiring new paint, or is lead paint stabilization required in areas where the paint is peeling/cracking/chipping?
a. Full abatement is not required. Only remove any peeling or loose paint.
11. Has there been an LCP and Asbestos report on the rooms for this project that can be shared with us?
a. The GSA can provide a lead report.
12. Are there a parking spaces for contractors to park?
a. Unfortunately, there is not.
13. Is there a place to put a dumpster?
a. GSA will identify a location for the contractor supplied dumpster.
14. Does the door/frame/trim between the office 360 and office 358 get painted? Currently there is a tack board over the door in the middle office and SOW makes no mention of removing the tack board.
a. Remove the existing tack board and paint both sides of door and trim between rooms 360 & 358.
15. Do we have to paint both sides of the doors in particular on the hall side?
a. The hallway side of the door does not need to be painted. Paint the door frame up to the threshold.
16. What level of finish on drywall is required? Level 4, Level 5, Level 4 w/orange peel, Level 4 w/texture.
a. Level 4 w/orange peel