Bid Sheet Template -.xls
XLS spreadsheet 103 KB Posted
- Attached to
- Region 8 Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC)
- Solicitation number
- 47PJ0020R0064
About this file
This document contains a bid sheet template for a General Services Administration construction project price proposal. The template includes line items for various construction divisions with unit costs and quantities to calculate total prices. It requests pricing for general conditions, site work, concrete, masonry, metals, wood and plastics, thermal and moisture protection, doors and windows, finishes, specialties, equipment, furnishings, special construction, conveying systems, plumbing, HVAC, and electrical work. Bidders should specify their total construction cost according to the template format. General requirements, overhead, profit, and bond percentages will be applied to determine the total proposed construction cost per square foot. Notes indicate that additional comment sections and line items can be added as needed.
The related federal contract opportunity is a solicitation for an Indefinite Delivery Indefinite Quantity Multiple Award Construction Contract for GSA Region 8 in Colorado, Montana, Utah, North Dakota, South Dakota, and Wyoming. As a total small business set-aside, the solicitation seeks pricing from contractors to complete future construction projects on an task order basis for the six stated region 8 states.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| GENERAL SERVICES ADMINISTRATION | |||||||
| PROJECT | |||||||
| PRICE PROPOSAL / BID FORMAT | |||||||
| 1442 Bid Schedule | |||||||
| Contractor Name: | Date: | ||||||
| Division | |||||||
| Item # | Description | Unit | Cost | Quantity | Total | Comments | |
| 1000 | GENERAL CONDITIONS | ||||||
| 1 | Project Manager | Hrs | $ - 0 | ||||
| 2 | Superintendant | Hrs | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 2000 | SITE WORK / DEMOLITION | ||||||
| 3 | Excavation (ext.utility work incl.backfill) | Cu.Yd. | $ - 0 | ||||
| 4 | Interior Demolition | Sqr. Ft. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 3000 | CONCRETE | ||||||
| 5 | Concrete | Cu.Yd. | $ - 0 | ||||
| 6 | Formwork | Sqr. Ft. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 4000 | MASONRY | ||||||
| 7 | CMU | Sqr. Ft. | $ - 0 | ||||
| 8 | Brick | Sqr. Ft. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 5000 | METALS | ||||||
| 9 | Exterior walls - furring & gyp.brd., 1 side | Sqr. Ft. | $ - 0 | ||||
| 10 | Int.walls - gyp.brd. 2 sides to fram'g above | Sqr. Ft. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 6000 | WOOD & PLASTICS | ||||||
| 11 | Base & Wall Cabinets | L.F. | $ - 0 | ||||
| 12 | Countertops | L.F. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 7000 | THERMAL & MOISTURE PROTECTION | ||||||
| 13 | Insulation (sound batts) | Sqr. Ft. | $ - 0 | ||||
| 14 | Ceiling Insulation | Sqr. Ft. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 8000 | DOORS & WINDOWS | ||||||
| 15 | Single, H.M. door | each | $ - 0 | ||||
| 16 | Hardware (office keyed, lever, hinges) | each | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 9000 | FINISHES | ||||||
| 17 | Suspended Acoustical Grid including Tile | Sqr. Ft. | $ - 0 | ||||
| 18 | Paint including prep | Sqr. Ft. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 10000 | SPECIALTIES | ||||||
| 19 | Toilet Partitions (per stall) | each | $ - 0 | ||||
| 20 | Urinal partitions | each | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 11000 | EQUIPMENT | ||||||
| 21 | Display Boards | L.S. | $ - 0 | ||||
| 22 | Audio-Visual Rough-in | each | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 12000 | FURNISHINGS | ||||||
| 23 | Desks | L.S. | $ - 0 | ||||
| 24 | Televisions | each | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 13000 | SPECIAL CONSTRUCTION | ||||||
| 25 | Storage Tanks | L.S. | $ - 0 | ||||
| 26 | Asbestos Abatement | Sqr. Ft. | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 14000 | CONVEYING SYSTEMS | ||||||
| 27 | Passenger Elevators | each | $ - 0 | ||||
| 28 | Freight Elevators | each | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 15000 | PLUMBING (includes rough-in) | ||||||
| 29 | H.W Heater | each | $ - 0 | ||||
| 30 | Water Closets | each | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 15000 | HVAC (includes controls) | ||||||
| 31 | Duct Work | L.F. | $ - 0 | ||||
| 32 | Diffusers | each | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| 16000 | ELECTRICAL | ||||||
| 33 | Lighting | Sqr. Ft. | $ - 0 | ||||
| 34 | Fire Alarm / Smoke Detection | Ea Zone | $ - 0 | ||||
| Sub-Total | $ - 0 | ||||||
| Sub-Total Construction Cost | $ - 0 | ||||||
| 1000 | GENERAL REQUIREMENTS | ||||||
| General Conditions | % | $ - 0 | $ - 0 | ||||
| 56 | Over Head | % | $ - 0 | $ - 0 | |||
| 57 | Profit | % | $ - 0 | $ - 0 | |||
| 58 | Bond | % | $ - 0 | $ - 0 | |||
| TOTAL CONSTRUCTION COST | $ - 0 | ||||||
| TOTAL CONSTRUCTION COSTS | Sqr.Ft. | $ - 0 | $ - 0 | ||||
| Date | Authorized Negotiator Signature | ||||||
| NOTES | |||||||
| 1 | Each Comment should have a note number and be explained in the notes section | ||||||
| 2 | Spreadsheet may be expanded as necessary for CSI Divisions and/or additional line items | ||||||
| 4 | This Price Proposal Format will be the only format accepted by GSA. This format will | ||||||
| also serve as the subsequent Contract Schedule of Values used for Progress Payments |