Amendment 0001 - Standard Form 30 - Phase 1 Questions and Answers.pdf
PDF 781 KB Posted
- Attached to
- Building 40 and 1A Consolidation Project
- Solicitation number
- 47PJ0020R0043
About this file
This amendment provides answers to questions received in response to a Phase 1 request for qualifications solicitation. The solicitation seeks design-build services for renovations to Buildings 40 and 1A of approximately 55,294 gross square feet for the Bureau of Land Management Colorado State Office consolidation project. The General Services Administration will award a firm-fixed-price contract.
The amendment answers seventeen questions, lowers the required bonding capacity from $20 million to $15 million per project, and requires teaming arrangement offerors to submit their agreement. Offerors must submit past performance questionnaires directly to references rather than including them in proposals. The submission deadline remains May 14, 2020 for the three short-listed offerors to be selected for Phase 2. A $25,000 stipend will be provided to unsuccessful Phase 2 offerors. The estimated value is between $10-20 million and work must meet LEED Gold requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
Amendment 0001 – D-B Building 40 & 1A BLM COSO Consolidation Project – 47PJ0020R0043 Page 2
Amendment 0001, April 29, 2020
Continuation of Block 14 of Standard Form 30
Solicitation 47PJ0020R0043 – D-B Services for the Building 40 & 1A BLM, COSO Consolidation Project
Amendment 0001 is issued to provide answers to questions received in writing in response to the Phase I request for qualifications and to include associated changes to the Solicitation document.
1. Answers to questions are provided as follows:
Question 1: The “Phase 1 – Solicitation” document states on page 6 of 15, II.D Other Requirements “(2) Proof of Bonding to
$20,000,000.” Then on page 12 of 15 of the same document VI.A Evaluation of Phase 1 Proposals, “Proof of bonding capacity of $20 million per project.” Finally page 13 of 15 of the same document VI.G Non-Price Factors states “Proof of Bonding Capacity of $20 Million.” Can the Government please confirm that the proof of bonding capacity must be $20M per project or $20M for a single project, NOT $20M bonding capacity in aggregate?
Answer 1: The proof of bonding capacity is per project (not aggregate). In addition, please note that the proof of bonding capacity has been changed from $20 million per project to $15 million per project as shown in section 2 below.
Question 2: Can the Government confirm that the proof of bonding capacity must be provided by the prime contractor?
Answer 2: Yes, the proof of bonding capacity (as well as the bond), must be provided by the prime contractor in accordance with FAR 52.228-15, “the Contractor shall furnish all executed bonds”.
Question 3: In 1 – Phase 1 – Solicitation, under II.C Technical Proposal, (2) Proof of Bonding to $20,000,000, is a bonding capacity letter sufficient for this requirement?
Answer 3: Yes. A letter, which meets the minimum bonding requirement, from the Offeror’s surety company is sufficient.
Question 4: Would the Government consider allowing for previously completed PPQs and/or CPARS from Federal clients to be accepted and submitted with our proposal? Getting new PPQs for our projects presents 2 challenges. First, many of our Federal clients one they have completed a final PPQ and or CPAR are reluctant to complete the other PPQs as they have already provided the information. Second, with projects dating back 10 years many of the people associated with the project have moved on or in some cases retired. Finding current contacts who still have knowledge of a project from 10 years ago is proving difficult, however we have final PPQs and CPARs on file that were completed in timely fashion upon those project's completion and would provide a more accurate picture of our performance on the project.
Answer 4: No. For each Offeror reference, for each Similar Project, the Offeror shall complete Section 1 and distribute the Past
Performance Questionnaire (Attachment 1 for GCs, Attachment 2 for A/Es) to each Reference for completion. The
References shall email the completed Past Performance Questionnaire to Rhonda Widick, Contracting Officer at rhonda.widick@gsa.gov and Andrew Hunsicker, Contract Specialist at andrew.hunsicker@gsa.gov not later than
10:00 AM Mountain Time, May 14, 2020. The subject line should contain the solicitation number and the name of the offeror. Completion questionnaires within the Offeror proposal will not be accepted. While the Government may elect to consider data from any source, the burden of providing detailed, current, accurate, and complete past performance information by the deadline for initial submissions rests with the Offeror and its evaluator/reference.
GSA may also contact and question the past performance references directly.
Information specific to the Similar Project is requested within the Past Performance Questionnaire. This information must be confirmed by the Reference. CPARs evaluations do not allow the Government to properly confirm the project is a Similar Project.
Question 5: In 1 - Phase 1 - Solicitation, under II.E Requirements of Joint Venture Offerors and II.F Requirements of Mentor
Protégé Offerors, request fully executed copies of their respective agreements. However, under Teaming
Arrangements it does not request a copy of the executed teaming arrangement. We would like to request that the teaming arrangement be included in the proposal as is requested for Mentor Protégé and Joint Venture arrangements.
Furthermore, this teaming arrangement can outline "Offerors submitting experience information of a teaming arrangement affiliate shall describe what involvement the teaming affiliate will have specific to the requirements of
Amendment 0001 – D-B Building 40 & 1A BLM COSO Consolidation Project – 47PJ0020R0043 Page 3 this project and demonstrate an affiliate's commitment to the project" as listed under Factor 1: Experience of the
General Contractor or A/E.
Answer 5: The solicitation (1 - Phase 1 - Solicitation) has been amended to include the following language at II.G, Requirements of Contractor Teaming Arrangement Offerors, "all initial offers submitted by contractor teaming arrangement offerors must include a copy of the teaming arrangement which fully discloses the legal identify of each member of the teaming arrangement, the relationship between the members, the form of ownership of each member, and any limitations on liability for each member."
Question 6: Can the prime offeror use a Similar Project where they were a major subcontractor and/or the offeror's Project
Executive held a lead role on the project while with another firm?
Answer 6: Evaluation Factor 1: Experience of the General Contractor and A/E considers the extent of the past experience of the
Offeror's proposed General Contractor and A/E members of the Offeror's design-build team. For purpose of this evaluation factor, the term General Contractor is defined as an individual, firm, partnership, corporation, association, or other legal entity permitted by law whose main responsibility is for the construction, improvement or renovation project under contract. The term A/E is defined as an individual, firm, partnership, corporation, association, or other legal entity permitted by law to practice the profession of architecture and engineering that will have the responsibility for developing complete, detailed design and construction documents. If the Offeror is neither the proposed General Contractor nor the A/E for this procurement, then this factor considers the past experience of the
Offeror's proposed General Contractor and A/E. if the Offeror is a joint venture, mentor protégé, or consists of a teaming arrangement, the individual experience of each individual party may be considered. Without detailed information on the Project Executive (assuming construction PE), this question is answered generally, the term
General Contractor is defined as an individual, firm, partnership, corporation, association or other legal entity permitted by law whose main responsibility is for construction, improvement or renovation project under contract.
IF the Project Executive had the main responsibility for construction improvement or renovation under the contract and the offeror adequately demonstrates that the Project Executive had the main responsibility for construction, improvement or renovation, the Similar Project may be considered assuming it meets all parts of the Similar Project definition.
Question 7: What is the stipend amount to be issued to unsuccessful teams?
Answer 7: Approximately $25,000 is available for each Phase II unsuccessful offeror
Question 8: Are there any LEED requirements?
Answer 8: Yes, the Contractor shall design the project to achieve, at a minimum, a Leadership in Energy and Environmental
Design (LEED) Version 4 Gold rating. Please refer to the technical documents provided via the solicitation for the required full scope of services.
Question 9: Will the project be LEED certified?
Answer 9: Yes, the Contractor shall design the project to achieve, at a minimum, a Leadership in Energy and Environmental
Design (LEED) Version 4 Gold rating. Please refer to the technical documents provided via the solicitation for the
Question 10: Will as-built drawings be provide in .dwg format of the existing buildings
Answer 10: All available documents have been provided with the solicitation.
Question 11: Was there a feasibility study prepared?
Answer 11: All available documents have been provided with the solicitation.
Question 12: Will upgrades to the shell be included, or interior only?
Answer 12: Yes, the scope includes upgrades to both the core/shell and interior. Please refer to the technical documents provided via the solicitation for the required full scope of services.
Question 13: Is the exterior of the building being touched?
Amendment 0001 – D-B Building 40 & 1A BLM COSO Consolidation Project – 47PJ0020R0043 Page 4
Answer 13: Yes, limited exterior work is required. Please refer to the technical documents provided via the solicitation for the
Question 14: Will the building 40 work include sitework, facade work, and structural engineering work?
Answer 14: Please refer to the technical documents provided via the solicitation for the required full scope of services.
Question 15: Will the new technology systems of building fall under the General Contractor's scope of work or will these systems be solicited at a later date? Examples; public address, video conferencing, Wi-Fi, CCTV, structured cabling.
Answer 15: Offeror's should assume, unless specifically required by the statement of work, that all technology systems will be provided through a separate order outside of the Design-Build contract.
Question 16: Has programming been completed or will this be included in the design?
Answer 16: Programming is required during design.
Question 17: Are there known hazardous materials in the building?
Answer 17: There is a potential for hazardous materials in the buildings. The successful offeror will be required to complete an asbestos Pre-Alteration Assessment as well as a Lead Pre-Alteration Assessment prior to demolition/construction.
2. Change of Bonding Capacity (per project):
The proof of bonding capacity is changed from $20 million per project, to $15 million per project. The document entitled 1 – The Solicitation – Phase I is changed as follows:
Section II.D. Other Requirements
FROM:
TO:
Amendment 0001 – D-B Building 40 & 1A BLM COSO Consolidation Project – 47PJ0020R0043 Page 5
Section VI.A. Evaluation of Phase 1 Proposals
Section VI.G. Non-Price Factors, Go/No-Go Factors
Amendment 0001 – D-B Building 40 & 1A BLM COSO Consolidation Project – 47PJ0020R0043 Page 6
3. Change to Requirements of Contractor Teaming Arrangement Offerors:
The requirement for contractor teaming arrangement offerors is changed to include the submission of a copy of the teaming arrangement. The document entitled 1 – The Solicitation – Phase I is changed as follows:
Section II.G. Requirements of Contractor Teaming Arrangement Offerors:
All other terms and conditions remain unhanged
The 10:00 AM Mountain Time, May 14, 2020 submission due date remains unchanged.
| topmostSubform[0]: |
| Page1[0]: |
| AmendmentNo[0]: 0001 |
| Code[0]: 8P2PQ |
| Code[1]: |
| AccountingData[0]: |
| A13[0]: |
| C13[0]: |
| D13[0]: |
| NameandTitleSigner[0]: |
| NameandTitleOfficer[0]: |
| Description[0]: See attached Continuation of Block 14 of Standard Form 30. |
| FacilityCode[0]: |
| Code[2]: 8P2PQ |
| IssuedBy[0]: GSA Acquisition Management Staff |
W 6th AVE & KIPLING ST Denver, CO 80225-0546
| NameandAddress[0]: |
| AdministeredBy[0]: GSA Acquisition Management Staff |
W 6th AVE & KIPLING ST Denver, CO 80225-0546
| ContractIDCode[0]: |
| ReqNumber[0]: |
| AmendmentNo[1]: 47PJ0020R0043 |
| ModificationNo[0]: |
| ProjectNo[0]: N/A |
| Page[0]: 1 |
| Pages[0]: 6 |
| EffectiveDate[0]: 04/29/2020 |
| Dated9B[0]: 04/15/2020 |
| Dated10B[0]: |
| CheckBox9[0]: Off |
| CheckBox10[0]: Off |
| CheckBox11[0]: 1 |
| CheckBox13A[0]: Off |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| CheckBox13D[0]: Off |
| IsNot[0]: Off |
| Is[0]: Off |
| Extended[0]: Off |
| NotExtended[0]: 1 |
| DateSigned[0]: |
| DateSigned[1]: |
| Copies[0]: 1 |
| CopiesReturned[0]: |