Site visit log and questions

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 4/20/2015

Preaward Site Visit

Name of Project: Piegan/Raymond Abatement Building Number or Name: Piegan IFR/Raymond IFR City, State: Piegan MT/Raymond MT Date: 3/19/2018 and 3/21/2018 Contract or Solicitation No. GS-08P-

NAME (PRINT) AGENCY/FIRM EMAIL ADDRESS PHONE

NUMBER

Sam Hafen GSA Samuel.hafen@gsa.gov 303.513.7841 Carl Rosco MT2 732.533.9762 John Burton GSA 406.360.8764 Travis Reed GSA 406.450.1267

NOTES: Carl from MT2 met me at Piegan and Raymond for the sitewalks. Facilities management let us in the space but did not accompany us in the walk-through of the project space.

In Piegan, Carl had the following questions:

Q: What are the sizes of the HVAC ducts?

A: After finding the mechanical room, the ducts appeared to be 2ftx2ft Q: What design do the tiles have that require replacing?

A: They are porous (acoustic) and cannot be cleaned. The scope requires that they be replaced.

Q: Can porous materials be encapsulated (sealed) rather than cleaned or replaced.

A: No. Because they are being shot and torn apart, they need to be replaced rather than encapsulated.

Q: Does the peg board behind the IFR control computers need to be replaced?

A: Yes.

In Raymond:

Q: What materials is the bullet trap made of?

A: Recycled tire mulch.

Q: Does pegboard behind control computers need to be replaced?

A: No. The pegboard is metal and can be cleaned.