BASELINE SCHEDULE EXHIBIT

ITEM MILESTONE DATE

1 A/E NTP 01/17/17

2 Design Stage

2.01 A/E Kick-off Meeting / Partnering Session 01/18/17

2.02 Start Concept Design – New Annex & Jonas 01/18/17

2.03 Complete Concept Design – New Annex & Jonas 08/01/17

2.04 Concept Design Approved 08/29/17

2.05 Start DDs / CDs – New Annex 08/30/17

2.06 Complete Design – New Annex 08/29/18

2.07 Start DDs / CDs – Jonas Renovation 08/30/18

2.08 Complete Design – Jonas Renovation 08/29/19

3 Construction Stage

3.01 Start CMc Procurement Using Approved Concepts 9/29/17

3.02 Contract Award - CMc 1/30/18

3.03 Construction begin (early packages) – New Annex 4/01/18

3.04 Substantial Completion – New Annex 08/04/20

3.05 Complete Move from Jonas to New Annex 09/14/20

3.06 Construction begin - Jonas 09/15/20

3.07 Substantial Completion - Jonas 10/21/22