GSA Solicitation No.47PE0218R0012

Document: DB201A-SB/DEC 2017 (The Solicitation)

+Constructions Contract for: Columbus Courthouse Interior Water Damage Repair

The Solicitation

Notice to Offerors of [Total Small Business Set-Aside

The General Services Administration (GSA) is setting aside the contract under the following clause found in the Agreement:

52.219-6, Notice of Total Small Business Set Aside.

Table of Contents

I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction H. Receipt of Offers

II. Proposals

A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors

III. General Provisions

A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding Documents Designated as Sensitive But Unclassified

IV. FAR/GSAR Solicitation Provisions A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR 101-29 B. FAR 52.211-3, Availability of Specifications Not Listed in the GSA Index of

Federal Specifications, Standards and Commercial Items Description C. FAR 52.216-1 Type Of Contract D. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of Work E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal

Employment Opportunity for Construction F. FAR 52.225-10 Notice of Buy American Requirement-Construction Materials G. Buy American Exceptions H. FAR 52.233-2 Service of Protest I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference J. GSAR 552.102 Incorporating Provisions and Clauses by Reference K. Additional Provisions L. Certified Cost or Pricing Data

V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition

B. FAR 52.219-14 Limitations on Subcontracting C. FAR 52.219-18 Notice of Competition Limited to 8(a) Eligible Participants D. FAR 52.223-21, FOAMS (Jun 2016) E. FAR 52.222-62 Paid Sick Leave Under Executive Order 13706 F. Security Requirements G. Additional Clauses

VI. Method Of Award A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Total Evaluated Price F. Non Price Factors G. Evaluation of Joint Ventures

I. General Information

I.A. The Solicitation and Contract

(1) This Solicitation is set-aside for Small Businesses / 8(a) Small Businesses / HUBZone Small Businesses / Service-Disabled Veteran-Owned Small Businesses / Economically Disadvantaged Women-Owned Small Business Concerns / Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program in accordance with FAR

19. This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.

(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.

(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer.

No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.

I.B. List of Solicitation Documents

The Solicitation Documents are comprised of:

(1) The Solicitation

(2) Offeror Representations and Certifications Form

(3) Standard Form (SF) 1442 – Solicitation Offer and Award

(4) The Agreement and Attachments to the Agreement

(5) The Statement of Work, Specifications, and Drawing Exhibits

I.C. Authorized Representatives

The following individuals are designated as the authorized GSA representatives under this Solicitation:

Authorized Representative Information:

Contracting Officer’s Information

Name: Wanda George-James

Address: GSA/PBS – Acquisition Management Division, 77 Forsyth Street, SW

Atlanta, GA 30303

Telephone: 404-772-8075

Authorized Representative Information:

Email: wanda.george-james@gsa.gov

Alternate POC Information

Name: Michelle Mayfield

Address: GSA/PBS – Acquisition Management Division

77 Forsyth Street, SW

Atlanta, GA 30303

Telephone: 404-561-3631

Email: michelle.mayfield@gsa.gov

I.D. Pre-Proposal Conference

Date: June 14, 2018

Time: 10:30 AM

Location: US Post Office & Courthouse 120 12th Street Columbus, GA 31901

I.E. Estimated Price Range The estimated price range for the Project is between $1,000,000 and $5,000,000.

TI.F. FAR 52.228-1 Bid Guarantee (SEP 96)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)

(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.

(3) Pre-registration is required for all attendees to the pre-proposal Site Visit. The Site Visit shall be limited to not more than four (4) representatives from each Offeror. Offerors shall submit a Visit Authorization Request (VAR) identifying all attendees from their respective team.

Participants must have a valid, Government issued picture identification, driver’s license preferred, to gain access for the pre-proposal Site Visit. Notification of the location of entry, where attendees are required to meet, and all other requirements for the Site Visit will be issued to the Offerors. Submit the VAR to the point of contact listed below.

For further information about the site visit or access requirements, please contact:

Name: Shonda Piper-Cameron, Project Manager

GSA, PBS Project Delivery Division (4PPG) 77 Forsyth Street, Suite G40 Atlanta, GA 30303

Telephone: office: (404) 331-0847 cell: (404) 431-0121

Email: shonda.piper-cameron@gsa.gov

I.H. Receipt of Offers

(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 2:00 PM EST on the following date and at the following address.

Date: July 02, 2018 Address: GSA/PBS – Acquisition Management Division / Georgia PMC Attn: Wanda George-James 77 Forsyth Street, SW (MLK Federal Building) Atlanta, GA 30303

(2) Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers.

(3) Offers sent by United States Mail shall be deemed timely if delivered to the address of the government installation designated for receipt of offers on or before the date established for receipt of offers.

II. Proposals

II.A. Proposal Contents

Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:

1. Price Proposal

2. Technical Proposal

3. Representations and Certifications

4. Standard Form 24, Bid Bond

5. GSA Form 527 – Contractor’s Qualification and Financial Information

II.B. Proposal Format

II.C. Price Proposal

(1) Contents

The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.

(2) Qualifications, Exclusions and Conditions

If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

(3) Additional Proposal Requirements

II.D. Technical Proposal

The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.

Special Note - Design Phase Services and Construction Phase Work can be represented by a single project and Offerors are encouraged to submit projects wherein both types of services were provided on the same project. In cases where the Offerors member teams (designer and constructor) have not worked together on similar projects the Offeror may submit projects that demonstrate the work of either the designer or constructor or both.

The factors below in descending order of importance will be used to evaluate all Proposals:

Factor 1: Experience on Comparable or Similar Projects Factor 2: Past Performance of Offeror Factor 3: Technical /Management Approach Factor 4: Qualifications & Experience of Key Team Members ]

Factor 1: Experience on Comparable or Similar Projects. This factor will evaluate the specialized experience and technical competence of the Offeror’s Design-Build Team, including the designer and constructor. For this factor, Offerors must identify by name its member firms, both designer (Architect-Engineer) and constructor. Accordingly, this factor will evaluate the extent of the Offeror’s experience with similar project types.

Information to be submitted by Offeror - Offerors shall address the following in its submission for this evaluation factor:

Offeror shall provide three (3) similar projects, of which at least two (2) was substantially or contractually completed within the last five (5) years of this solicitation issue date. Provide the name and location of each project along with a brief description of the scope. Provide the project delivery method of each project (design-build or bridging design-build) and the name of the designer (Architect/Engineer) and of the constructor for each project along with a brief description of their roles and responsibilities.

1. Describe how each project is similar to the project requirements in this solicitation.

Specifically, related to waterproofing, asbestos, mold, and lead paint abatement. Submit the description of any unusual physical site constraints that had to be overcome for each project and how they were managed. Highlight work completed in an occupied facility.

2. Provide the contract award amount at time of initial award and final contract amount (including all modifications) for each project.

Factor 2: Past Performance of Offeror. This factor will evaluate the extent to which the past performance of the Offeror’s Team, including the designer and constructor, have a successful and satisfactory performance record on similar waterproofing and environmental abatement projects providing design and construction services over the last five (5) years.

This factor will also evaluate the extent to which the Offeror’s Team has a successful and satisfactory track record on similar projects including coordination with various government agencies including Federal (GSA and U.S. Courts) and State Historic Preservation Office.

Information to be submitted by Offeror - Offeror shall address the following in its submission for this evaluation factor:

Offeror shall provide three (3) same or similar projects completed, within the last five (5) years of the solicitation issue date. The Offeror may use the same projects submitted in Factor 1 if they are substantially or contractually completed. The Offeror is defined as the design-builder that will contract with the Government. Provide the name and location of each project along with a brief description of the scope, including the date the original building was constructed.

Provide the name of the member firms for each project – this includes all trades used for the project. At a minimum, the designer (Architect/Engineer) and constructor must be provided. In addition, provide the following information for each project submitted for evaluation:

1. Demonstrate how each project is similar and comparable in scope and complexity to the project requirement for this solicitation.

2. Provide the contract award amount at the time of initial award and the final contract amount (including all modifications) for each project. Provide how the costs were managed during the execution of each project.

3. Provide the performance period at the time of initial award and the actual performance period for the contract of each project. Provide the completion date. Provide how the schedule was managed during the execution of each project, and if the performance period increased, provide the reasons why it did so.

4. Describe any key features or constraints that required additional effort, creativity, or innovations to successfully complete each project (e.g., a limited budget, accelerated schedule, difficult site, unusual functional requirements, phased construction in an occupied space, special permits, coordination with multiple stakeholders including Judges, etc.).

5. Provide a minimum of one (1) reliable* reference (previous Client) to complete a Past Performance Questionnaire (PPQ) (included in the solicitation as Attachment 8) for each project included in proposal for Factor 1 - Experience on Comparable or Similar Projects.

- The term reliable relates to the ability of GSA to readily contact these references.

- If the reference is not deemed to be reliable, the project will be disqualified from the submission. If the number of projects submitted drops below the required number of projects, the contractor will receive and unsatisfactory rating for this factor.

- Completed PPQs should be submitted with the proposal. Ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the Offeror is unable to obtain a completed PPQ from a client for project before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the project.

- If the client requests, the client may submit a questionnaire directly to the Government's point of contact, via email at wanda.george-james@gsa.gov prior to proposal closing date. Offerors may resubmit questionnaires previously submitted with other proposals or may obtain an updated/new PPQ from a client for any submission.

Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.

6. Also include performance recognition documents received within the last five (5) years, such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition. In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), previously submitted PPQ information, and any other known sources not provided by the Offeror. While the Government may elect to consider data from a variety of sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. GSA will not maintain database of PPQs submitted by Offerors.

Factor 3: Technical/Management Approach. This factor will evaluate the Offeror’s Technical Approach to performing site investigation, design and construction document preparation, project management, construction, contract administration, and how the Offeror plans to achieve the project requirements.

Information to be submitted by Offeror - Offerors shall address the following in its submission for this evaluation factor:

Offerors shall describe their general approach to managing and delivering design-build projects of similar complexity. In describing this general approach, Offerors should address such areas as risk analysis/management/mitigation, cost estimating and how costs are controlled, schedule development and monitoring, and, site access. Offerors are encouraged to provide examples of where they have successfully utilized such approaches. Offerors shall:

1. Describe/verify the capacity of the project team members to be available on this project as proposed during the term of the contract.

2. Provide a written narrative that describes its means, methods, and processes used to manage clients, trade subcontractors, consultants, and other entities during Design Phase Services and Construction Phase Work. Of particular importance will be the Offeror’s experience with managing and coordinating design services within a Design-Build contract.

Offerors may submit flow charts and illustrations of the processes or systems.

3. Provide a Management Plan that identifies how the Offeror plans to implement management techniques to ensure the success and quality of the design and construction of this project. Provide a proposed project schedule in Gantt chart format for execution of the design-build project from award of the contract to completion. The proposed schedule should provide sufficient detail to illustrate the proposed flow of design and construction activities for the project with the overall duration clearly shown.

a. Discuss the project schedule that highlights key assumptions on which the schedule is based, and discusses the Offeror's strategy for sequencing the work. The narrative should also discuss any significant contingency issues that could potentially delay overall progress on the project, and what actions the Offeror would propose to mitigate the impact on project completion.

b. Discuss how the project will be executed in a fully occupied building without causing disruption to the daily operation of the building and its tenants. Discuss what actions will be taken to ensure proper coordination with all stakeholders regarding building access, general safety, and security.

c. Outline how the responsibilities of the team will be managed. Discuss coordination of trade subcontractors and suppliers to minimize installation conflicts and to ensure that specified products, and installation means and methods comply with contract requirements.

d. Discuss monitoring construction schedule and costs, including change orders, to ensure that the project is completed on time and within budget.

4. Provide a draft Project Quality Control Plan. The plan shall detail the proposed methods or processes of providing quality control for all work products. This plan will be kept current with the work requirements. The plan shall include, but is not limited to, the following areas:

a. Organization of the Quality Team: Roles and Responsibilities

b. Quality Control Process; including processes, procedures, protocols and reviews the Quality Team will use to assure quality of the project

5. Provide a draft Safety Management Plan. The plan shall provide for the following:

a. Planning, management, and design to avoid hazards

b. Subcontractor safety management

c. Detection of potential hazards

d. Timely correction of hazards

e. Dedication to the protection of the public and the work

f. Active participation of all persons involved with the Contrac

g. Dedicated safety staff

h. Site safety orientation, training, and safety meetings, including a plan for indicating attendance at safety orientation.

Factor 4: Qualifications and Experience of Key Personnel. This factor considers the qualifications and experience of key personnel on the Offeror’s Team. The RFP requests resumes or other relevant documentation for certain positions. The Offeror may submit additional resumes as it believes necessary to fully describe the talents and depth of their team.

The qualification of each individual is based upon the skill, experience and education level of the individual.

The scope of this project requires construction-related experience in key positions to ensure reasonable expectation of project success.

At a minimum, key personnel are the Designer of Record, Design Manager, Construction Project Manager, Superintendent and Quality Control Superintendent.

Note: The DB Contractor will not be allowed to substitute key personnel during the course of the project without prior approval by the Contracting Officer or his/her representative. All substitutions MUST have equal or better qualifications and experience.

Information to be submitted by Offeror - Offerors shall address the following in its submission for this evaluation factor:

1. Provide a project organization chart identifying how the design-builder will organize and staff the project from project award and inception of design through construction completion.

a. The chart should identify the title of key positions in the organization and the names of the persons proposed to fill those positions. At a minimum, the chart should address design management, project management, project superintendence, quality assurance/control (both design and construction), and project controls. The reporting relationships between these functions and the company's senior management should also be defined. By including this information in this proposal, the Offeror is making a commitment to assign specific individuals to specific roles in this project, and that commitment is a consideration in the evaluation of the proposal.

b. Provide a narrative on the project organization. It should define the roles, responsibilities and authority to be delegated to the incumbent of each position and discuss how work flows through the organization

2. Provide a one-page resume for each person shown in the organization chart, highlighting previous work experience similar to this project.

a. For each proposed key person, identify their proposed duties in the project.

Identify the person as a part-time or full-time employee and the firm that person is employed (i.e. Designer or Constructor).

b. Offeror must state how long the key personnel have worked for the firm.

Indicate the specific geographic location of employment where each proposed employee is located at the time of response to this announcement.

c. Also include the amount of time anticipated to be spent on-site and the amount of time to be spent working in the home office on this project. State which personnel will be involved in the design phase and which will be involved in the construction phase.

3. Provide a staffing summary for the design-builder that identifies the proposed design and construction staffing for this project.

a. The summary should include the number of people employed, the number that would be available for this project, and the estimated number required for this project. If design and construction are being provided by separate companies, provide a staffing summary for each company.

4. Identify the number of personnel on your project team who have HSPD-12 clearances. It is not required that a specific building badge be possessed, but the full clearance is the topic of concern.

5. Indicate how the Project Manager guides the work, how change orders, claims and disputes will be handled, and how shop drawings, submittals, etc. are coordinated.

6. For each proposed key person, describe their knowledge and experience with local markets, subcontractors, the general labor market, and local government in the location where the project is being built.

II.E. Other Information to Submit with Proposal

(1) Representations and Certifications

Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management. Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301-SAT).

(2) Qualifications of Offerors]

Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract. Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.

II.F. Requirements of Joint Venture Offerors]

(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.

(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.

(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.

(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.

III. General Provisions

III.A. Availability of Funds

Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.

III.B. Requests for Clarification or Interpretation

The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 14 calendar days. Prospective Offerors should make such requests not less than 14 calendar days prior to the date set for receipt of offers.

III.C. Notice to Small Business Firms

A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.

III.D. Information Concerning the Disclosure of Solicitation Results

This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.

III.E. Affirmative Procurement Program

GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement. Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.

III.F. Notice Concerning Preparation of Proposals

Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.

III.G. Bond Requirements

If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.

III.H. Contractor Performance Information

(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process.

CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment

Completed CPARS evaluations are sent to the Past Performance Information Retrieval System (PPIRS) which may then be used by Federal acquisition community for use in making source selection decisions. PPIRS assists acquisition officials by serving as the single source for contractor past performance data.

(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS.

The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.

(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.

(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.

Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.

GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.

Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.

III.I. Safeguarding Documents Designated as Sensitive But Unclassified

Certain information contained in the Solicitation Documents may have been designated as Sensitive but Unclassified (SBU) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.

IV. FAR/GSAR Solicitation Provisions

IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (AUG 98)

(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to—

GSA Federal Supply Service Specifications Section, Suite 8100 470 East L’Enfant Plaza, SW Washington, DC 20407

Telephone (202) 619-8925 Facsimile (202) 619-8978

(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.

IV.B. FAR 52.216-1 Type of Contract (APR 84)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

IV.C. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work

(MAY 14)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

IV.D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for Minority Participation for Each Trade

Goals for Female Participation for Each Trade

% 6.9%

These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order

11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is: [Columbus, GA (Muscogee County)

IV.E. FAR 52.225-10 Notice of Buy American Requirement—Construction Materials.

(MAY 2014)

(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American—Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

IV.F. Buy American Exceptions

For Buy American exceptions, if any, see the applicable Buy American clause in Section

IV of the Agreement.

IV.G. FAR 52.233-2 Service of Protest (SEP 06)

(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

IV.H. FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 98)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address:

Federal Acquisition Regulation

NUMBER TITLE DATE

52.214-34 Submission of Offers in the English

Language

APR 91

52.215-16 Facilities Capital Cost of Money JUN 03 52.236-28 Preparation of Proposals - Construction OCT 97

IV.I. GSAR Clause 552.102 Incorporating Provisions and Clauses

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.

]IV.J. Requiring Certified Cost or Pricing Data [15.403-4]

[N/A

V. Instructions and Clauses

V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (Jan 2017)

(a) Definitions. As used in this provision.

“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.

“In writing,” “writing,” or “written” means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

“Proposal modification” is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.

“Time,” if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.

(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c) Submission, modification, revision, and withdrawal of proposals.

(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.

(2) The first page of the proposal must show.

(i) The solicitation number;

(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);

(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;

(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and

(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.

(3) Submission, modification, revision, and withdrawal of proposals.

(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.

(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and.

(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or

(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or

(3) It is the only proposal received.

(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(v) Proposals may be withdrawn by written notice received at any time before award.

Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.

(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.

(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225- 17, Evaluation of Foreign Currency Offers, is included in the solicitation.

(6)…