Solicitation 47PE0119R0001 – Pricing/Wage/Overhead Breakout Sheet

1 | P a g e

Unallowable and Generally Unallowable Costs

31.205-3 Bad Debt

31.205-7 Contingencies

31.205-8 Contributions

31.205-14 Entertainment Costs

31.205-15 Fines, Penalties, and Mischarging Costs

31.205-20 Interest and Other Financial Costs

31.205-22 Lobbying and Political Activity Costs

31.205-23 Losses on Other Contracts

31.205-27 Organization Costs

31.205-31 Plant Reconversion Cost

31.205-49 Goodwill

31.205-51 Cost of Alcoholic Beverages

The above costs are not intended to represent all unallowable costs within the confines of FAR Part 31, as most allowable costs contain some restrictions by which they may be determined unallowable. Therefore, you are required to review each cost pool proposed in the makeup of your overhead as it relates to the FAR Part 31 Package provided along with the submissions of your overhead pools for analysis, you are required to sign and return a certificate of current cost and pricing data certifying the accuracy of the costs at the time of submission.

2 | P a g e

SAMPLE Period Ending Disallowances Allowed Overhead Direct Labor 1,500,000 1,500,000

Indirect Expenses

Salaries Indirect 1,000,000 1,000,000 Rent 300,000 300,000 Insurance 200,000 200,000 Marketing 500,000 500,000 0 Leased Equipment

250,000 250,000

Taxes 45,000 45,000 Transportation 10,000 10,000 Bad Debt 50,000 50,000 0

Total Indirect Expenses

2,355,000 550,000 1,805,000

Overhead 157% 120.33%

Disallowances IAW FAR Part 31

PROPOSED CONSULTANTS MUST REVIEW FAR PART 31 AND EXCLUDE UNALLOWABLE ACCOUNTS

ATTACHMENT A

This is not intended to represent all disciplines subject to perform under the contract. The A&E firm shall provide, at a minimum, experts with credentials as indicated, in disciplines listed in the PBS P100 and may be otherwise required in Task Orders, as they apply to projects.

The A&E firm shall utilize the personnel named in its proposal offer (SF330) to perform the services required under this contract. In the event that any of the personnel named in the accepted A&E proposal (which will be incorporated into this contract by reference) become unavailable, the A&E shall promptly submit a detailed explaination of the circumstances necessitating the proposed substitution, a resume for a proposed substitution, and any other information necessary for the GSA to approve or disapprove. The Contracting Officer reserves

3 | P a g e the right to reject the substitution of personnel when professional qualifications and experience of the proposed substations are inadequate or otherwise unsatisfactory, as determined by the Contracting Officer. An increase in salary rates is not allowed when substitute personnel are authorized. See Also FAR 52.244-4 regarding subcontractors and outside associates and consultants.

PRIME

Discipline Name Base Year Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Principle Architect Project Architect Architect Architect Administrative/CFO Administrative

4 | P a g e

CONSULTANT (1) - (STRUCTURAL)

Discipline Name Base Year Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Sr. Principle Sr. Principle Sr. Project Engineer

Project Engineer Project Engineer Engineer CADD Operator

5 | P a g e

CONSULTANT (2) - (CIVIL)

Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Project Manager Chief Engineer

Designer

Engineer Tech.

Engineer Tech.

Clerical

6 | P a g e

CONSULTANT (3) - (MECHANICAL/ENGINEERING/PLUMBING/FIRE PROTECTION)

Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Principle Electrical

Mechanical

Plumbing

Electrical Designer CADD Technician Office Manager

Assistant

7 | P a g e

CONSULTANT (4) - (ACOUSTIC)

Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Sr. Consultant 1 Sr. Consultant 2 Sr. Consultant 1 Sr. Consultant 2 Technical Assistant 1

Assistant 2

CONSULTANT (5) - (LANDSCAPE)

Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Principle

8 | P a g e

CONSULTANT (6) - (INTERIOR DESIGN)

Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Registered Interior

Design Assistant Sr. Consultant 1 Sr. Consultant 2

Assistant 1

Assistant 2

CONSULTANT (7) - (COST ESTIMATE)

Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Construction Consultant/Estimator

CONSULTANT (8) - (ENVIRONMENT)

Hourly Rate

Option Year I

Option Year

II

Option Year

III

Option Year

IV

Construction Consultant/Estimator

9 | P a g e

OVERHEAD RATES:

FIRM

Principle

Consultant 1

Consultant 2

Consultant 3

Consultant 4

Consultant 5

Consultant 6

Consultant 7

Consultant 8