About this file

This document is an amendment to a solicitation for a Single Award Indefinite Delivery Indefinite Quantity (IDIQ) contract for Repair and Alteration (R&A) / General Construction Services in Richmond, VA, and surrounding areas. The solicitation is being issued by the General Services Administration (GSA) Mid-Atlantic Region.

The amendment provides clarification on the technical proposal requirements, including the number of projects that can be submitted and the timeframe for those projects. It also clarifies that while experience in the specific geographic area is considered favorable, it is not a requirement to be eligible for award. The amendment incorporates a pre-proposal conference attendance list and a request for information (RFI) log with questions and answers. The proposal due date remains unchanged at June 10, 2024, 4:00 PM Eastern Time. This procurement is set aside for 8(a) small businesses, with a NAICS code of 236220 and a size standard of $45 million.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

5/6/2024

Paul Ferguson, Contracting Officer

EQ3PSR-24-00430001

GSA ACQUISITION SVCS SOUTH - MD & WV SECTION

100 S INDEPENDENCE MALL W

PHILADELPHIA, PA 19106-2320 USA

47PD0224R0057

3PQSW

GSA ACQUISITION SVCS SOUTH - MD & WV SECTION

100 S INDEPENDENCE MALL W

PHILADELPHIA, PA 19106-2320 USA

3PQSW

5/31/2024

Single Award Indefinite Delivery Indefinite Quantity (IDIQ) Contract for Repair and Alteration (R&A) / General Construction Services in Richmond, VA, and surrounding areas. See attached.

SOLICITATION NO.: 47PD0224R0057

PROJECT TITLE: Single Award Indefinite Delivery Indefinite

Quantity (IDIQ) Contract for Repair and Alteration (R&A) / General Construction Services in Richmond, VA, and surrounding areas.

SOLICITATION ISSUE DATE: 05/06/2024

SOLICITATION DUE DATE: 06/10/2024 at 4:00 PM (Eastern Time)

1. The attached pre-proposal conference meeting attendance list is hereby incorporated into the solicitation.

2. The previous “Richmond IDIQ pricing sheet” is hereby replaced by “Richmond IDIQ pricing sheet_rev1.” The pricing sheet must be signed, dated, and submitted with the offeror’s price proposal.

3. The Request for Information (RFI) log with questions and answers has been attached and incorporated into the solicitation.

4. The proposal due date and time remain unchanged, June 10, 2024, at 4:00 PM (Eastern Time).

5. Offerors must acknowledge this amendment on the SF30 (include name, signature, date) and block 19 of the SF1442.

6. All other terms remain unchanged.

7. Attachments:

a. Pre-Proposal Conference Meeting Attendance List– Single Award Indefinite Delivery Indefinite Quantity (IDIQ) Contract for Repair and Alteration (R&A) / General Construction Services in Richmond, VA, and surrounding areas.

b. Richmond IDIQ pricing sheet_rev1

c. Richmond IDIQ RFI Log

Richmond IDIQ

Pre-Proposal Meeting (05/15/24) - Attendance

Name Company Valerie James Derri Bennett

Mark Turner Construction

Juane Robinson

IMEC Group LLC.

Eric Cheek Neal Hasweh

Pace Contracting

Jamie Vanek Kelsey Cates, John Trant Nick Sutton

Etolin Strait

Lisa Alexander Nicholas Alexander Thomas Addison Mike Luckett Tom Petty

Primordial Ventures Primordial Ventures 4TAS Supply Cesa Solutions 4TAS Supply

Mohammad Fridy PR Communications Stephen Drake ARCHITECTUREFIRM Matt Martin, Mike Devlin, Ben Lehnerer, Paul Brady, Taylor Jansen, Anthony Owens

Waseyabek Elevated Solutions JV.

Timothy Gayles Ms. Kelli Shannon

Yukon Management, LLC

Tiffany Tsedendamba

Terra Site Constructors, LLC

Cedric Wiggins Sr Plurax, LLC Lenell Rogers Diverse Solutions Group

Tom Andresen GSA Paul Ferguson GSA Paul Gapinski GSA Ahmadou Kante GSA Scott Hughes GSA

RFI #

Solicitation / Contract

Section Request for Clarification/Interpertiation Response

1 II. D. Technical Proposal - Technical Factor 1

The "Experience Workbook" paragraph indicates that projects performed within the last 5 years from the proposal due date should be included. What is the performance / completion timeframe for the three (3) primary projects required for this factor?

The three (3) primary projects should have been completed within the past three (3) years from the proposal due date. The following change is incorporated into Section II.D. Technical Proposal - Technical Factor 1 (emphasis added to highlight changed language):

Pertaining to this factor, each offeror shall submit the following:

Factor 1 Primary Projects Detailed Narrative - The technical proposal must include a detalied narrative of three (3) projects submitted in response to the Technical Factor. These projects should have been completed within the past three (3) years from the proposal due date.

2 II. D. Technical Proposal - Technical Factor 1

This factor states in part, "…The offerors shall also submit the "Experience Workbook" and provide no more than 15 contracts and / or projects performed in the last 5 years from proposal due date.". It further states, "An offeror is not required to submit 10 projects, this is the maximum". How many contracts and / or projects is the maximum number an offeror may submit?

The maximum number of contracts and / or projects an offeror may submit in the "Experience Workbook" is 15.

3 II. D. Technical Proposal - Technical Factor 2

The RFP states, "i. At a minimum the Offeror’s Approach must demonstrate how they will approach:

1. Providing general construction services within the geographic area

a. This must be supported by Projects provided in Factor 1

b. Offerors who demonstrate capability to perform throughout the entire area is considered favorable, but not required to be considered for award"

Is experience in the specific locals cited in the RFP required?

Experience in the specific locals is considered favorable, but not required. The following change is incorporated into Section II.D.

Techincal Proposal - Technical Factor 2 (emphasis added to highlight changed language):

1. Providing general construction services within the geographic area

a. This should be supported by Projects provided in Factor 1

Request for Information Log

SOL # 47PD0224R0057

Proposal Due Date: June 10, 2024 4:00PM EST Single Award Indefinite Delivery Indefinite Quantity (IDIQ) Contract for Repair and Alteration (R&A) / General Construction Services in Richmond, VA, and surrounding areas.

47PD0224R0057_Amendment 0001_Richmond IDIQ
Amend 0001_Richmond IDIQ_continuation page
Amend 0001_Richmond IDIQ_preproposal attendance
Amend 0001_Richmond IDIQ_RFI Log

File details come from the government source that posted it. Updated .