GSA Solicitation No. 47PD0123R0023 Charleston East Repair and Alteration (R&A) Single Award IDIQ
Document: C201-SB GC/MARCH 2023 (The Solicitation)
Construction Contract for: Charleston East Repair and Alteration (R&A) Single Award Indefinite Delivery / Indefinite Quantity (IDIQ)
The Solicitation
Table of Contents
I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction H. Receipt of Offers
II. Proposals
A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors
III. General Provisions
A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding and Dissemination of Controlled Unclassified Information
(CUI) Building Information
IV. FAR/GSAR Solicitation Provisions A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of
Federal Specifications, Standards and Commercial Item Descriptions, FPMR 101-29
B. FAR 52.211-3, Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Items Description
C. FAR 52.216-1 Type Of Contract D. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of
Work E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure
Equal Employment Opportunity for Construction F. Buy American Requirements G. Buy American Exceptions H. FAR 52.233-2 Service of Protest
I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference J. GSAR 552.102 Incorporating Provisions and Clauses by Reference K. GSAR 552.252-5 Authorized Deviations in Provisions (Nov
2021)(DEVIATION FAR 52.252-5)
L. Additional Provisions
(i) GSAR 552.236-74, Evaluation of Options (Mar 2019)
(ii) FAR 52.216-27 – SINGLE OR MULTIPLE AWARDS (OCT 1995)
(iii) GSAR Clause 552.236-77, Government’s Right to Exercise Options
(Mar 2019)
(iv) FAR 52.217-5 – EVALUATION OF OPTIONS (Jul 1990)
(v) Special Provisions for IDIQ Contracts: FAR 52.216-27 – SINGLE
OR MULTIPLE AWARDS (OCT 1995)
V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition B. FAR 52.219-18 Notice of Competition Limited to 8(a) Eligible Participants C. Security Requirements D. Additional Clauses
VI. Method Of Award
A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Non Price Factors F. Evaluation of Joint Ventures
Notice of Equal Employment Opportunity (EEO) Compliance Plan GSA has partnered with the Department of Labor to ensure compliance with equal employment opportunity requirements that apply to this project. An EEO Compliance Plan is required after the award.
The General Services Administration (GSA) is setting aside the contract under the following clause found in the Agreement:
100% 8(a) Small Business Set Aside
I. General Information I.A. The Solicitation and Contract This Indefinite Delivery Indefinite Quantity (IDIQ) Single-Award Term Contract is to provide general construction services throughout eastern West Virginia for the Charleston Field Office. The Government intends to award one (1) single contract under this solicitation in accordance with FAR 19.5. This procurement will be a total small business set-aside for 8(a) small-business. The applicable NAICS code is 236220 (Commercial and Institutional Building Construction. The annual small business size standard is $45 million.
The individual orders to be placed under the contracts will range in value from $2,000 to Simplified Acquisition Threshold of $250,000 as defined in FAR 2.101. However, individual orders may be placed outside of this range at the discretion of the Contracting Officer. The contract duration will be one (1) base year with four (4) one-year options with the possibility of an extension of performance up to an additional six (6) months, in accordance with FAR 52.217-8. The anticipated aggregate Maximum Ordering Limit (MOL) for this contract vehicle is $5,000,000.00. There is no annual MOL.
An IDIQ is a type of contract that provides for an indefinite quantity of supplies or services during a fixed period. The selected Single Award IDIQ General Contractor (GC) shall supervise, administer, perform, and contract all construction activities required to complete construction projects within eastern West Virginia. Construction activities for the anticipated solicitation include but are not limited to commercial office construction and/or renovations / repairs, MEP (Mechanical / Electrical), repairs / modifications / replacement, fire sprinkler systems repairs / modification/replacement, sitework, exterior construction repair and alterations (including facades and roofs), demolition (including abatement of hazardous materials), elevator modernizations and any other construction activities the government may require.
The GC may be required to utilize the following delivery methods to deliver projects for the GSA;
1. Design/Bid/Build (DBB) Traditional
2. Design/Build (D/B) The geographic area of work to be completed under this contract includes the following counties of West Virginia:
Raleigh, Mercer, Fayette, Nicholas, Randolph, Harrison, West Virginia, and Berkeley Counties and Ohio County in West Virginia. However, individual orders may be placed outside of this geographic area at the discretion of the Contracting Officer.
The contract will include by reference the most current version of the Facilities Construction Costs Book with RSMeans Data (referenced hereafter as “RSMeans Book”).
The Government intends to utilize the RS Means Line Items in connection with the awardee RS means Locality. Coefficient (referenced hereafter as “Locality Bid Factor”) to award future task orders. The Bid Factor shall apply to the entirety of the RSMeans Line Items.
Attached by reference is “Charleston West Line Items” which will be included and part of the contract at award. This list is provided for reference only. Following contract award, GSA intends to have the awardee price these line items using their accepted RSMeans bid coefficient.
This Solicitation is set-aside for 8(a) Small Businesses, in accordance with FAR 19. This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein.
The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
The government intends to award one (1) contract to the selected firm whose offer is considered to be the best value to the Government considering price and other non-price factors.
This Solicitation sets forth requirements for proposals for a Contract described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award a Contract to the selected Offeror, subject to the conditions set forth herein.
Task Order Pricing - For individual task orders, the government intends to utilize RSMeans Line Item pricing for all task orders. However, the Government may utilize either RSMeans Line Item pricing or Lump Sum Proposals at the discretion of the Contracting Officer. Instructions shall be provided to the awardee in all Requests for Proposal (at the task order level).
The two award methods [RSMeans Line Items and Lump Sum Competitive Proposals] shall not be used simultaneously on any future task order. The solicitation at the task order level will clearly define which method will be utilized.
The Bid Factor(s) is the maximum coefficient (i.e. multiplying factor) that the selected awardee may apply on future task orders. However, an offeror may elect to provide a discount at the task order level for a competitive advantage. When using the Bid Factor no other markups may be applied. The Bid Factor shall be utilized through the base period and all option periods (i.e. the potential total five-year Indefinite Delivery Indefinite Quantity (IDIQ) Contract).
The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF-1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF-1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.
I.B. List of Solicitation Documents The Solicitation Documents are comprised of:
(1) The Solicitation
(2) Offeror Representations and Certifications Form
(3) Standard Form (SF) 1442 – Solicitation Offer and Award
(4) The Agreement and Attachments to the Agreement
(5) Price Excel / Offer Form
(6) Attachment 1, Project Experience Information Worksheet (7)Attachment 2, Experience Workbook Spreadsheet (excel)
(8) Attachment 3, Past Performance Questionnaire
(9) Attachment 4, Charleston East Line Item Sheet
(10) Other Forms Required for Submission with Proposals
I.C. Authorized Representatives The following individuals are designated as the authorized GSA representatives under this Solicitation:
Authorized Representative Information:
Contracting Officer’s Information Name: Patrick Spellman Address: 100 Independence Mall West, Philadelphia, PA 19106 Telephone: 215-606-1755 Email: Patrick.Spellman@gsa.gov Alternate POC Information Name: George Garcia Address: 100 Independence Mall West, Philadelphia, PA 19106 Telephone: 215-313-1692 Email: George.garcia@gsa.gov
I.D. Pre-Proposal Conference mailto:Patrick.Spellman@gsa.gov mailto:George.garcia@gsa.gov
Date: 05/23/2023 Time: 1:00 PM EST Video Call Link:
Meeting ID: meet.google.com/xbr-htva-xwc Phone Numbers
(US) 6066-228-+1 470
PIN: 283 610 648#
I.E. Estimated Price Range The individual orders to be placed under the contracts will range in value from $2,000 to Simplified Acquisition Threshold defined in FAR 2.101; however, there may be individual orders with lower or higher costs placed against this contract depending on Charleston’s Field Office needs. The contract duration will be one (1) base year with four (4) one-year options, with the possibility of an extension of performance up to an additional six (6) months, in accordance with FAR 52.217-8. The anticipated aggregate Maximum Ordering Limit (MOL) for this contract vehicle is $5,000,000.00. Meaning the cumulative total for all task orders awarded to all contractors against this Single Award IDIQ shall not exceed $5.0 Million for the duration of this contract. In other words, there is no single MOL per year, other than the MOL of the entire contract. The guaranteed minimum amount under the proposed contract is $2,500 for the initial year or base period of each contract.
The following historical ordering information is being provided to give offerors an idea of the quantity and size of projects typically performed on this size IDIQ.
Small Construction Projects Range Average per Fiscal Year (Data based on past four fiscal years)
Dollar Range ($) Percentage (%) Number of Project on Average per Fiscal Year
$2,000 - $25,000 79.5% 31
$25,000 - $35,000 15.4% 6
$35,000 - $50,000 5.1% 2
I.F. FAR 52.228-1 Bid Guarantee (Sep 96) Not Required.
I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)
(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.
(2) Site visits will be conducted on a task order basis I.H. Receipt of Offers https://meet.google.com/xbr-htva-xwc?hs=122&authuser=0 https://meet.google.com/xbr-htva-xwc?hs=122&authuser=0 https://www.acquisition.gov/far/part-52#FAR_52_236_2 https://www.acquisition.gov/far/part-52#FAR_52_236_3
(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 4:00 pm local time on the following date and at the following address.
Date: 06/14/2023 Time: 2:00 PM EST Email Address: Patrick.spellman@gsa.gov and George.garcia@gsa.gov All offers shall be provided via email.
II. Proposals II.A. Proposal Contents Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
1. Signed Standard Form 1442 with all the amendments acknowledged
2. Price Proposal – Signed Bid / Offer Spreadsheet (For the 1 Locality Bid
Factors)
3. Technical Proposal
4. Project Experience Information Worksheet
5. Experience Workbook Spreadsheet (excel)
6. Past Performance Questionnaire
7. GSA Form C301, Representations and Certifications
8. GSA Form 527, Contractor’s Qualifications and Financial Information
9. If applicable, Joint-Venture Agreement and any Mentor-Protégé Agreements
10. If applicable, SF LLL – Pages 1 and 2
11. The information required under FAR 52.215-1(c)(2)
12. Any other required by the solicitation
II.B. Proposal Format Submit one electronic copy of the Price Proposal and one electronic copy of the Technical Proposal. Proposals shall only be submitted via email. The Price Proposal must be submitted in a separate PDF file from the Technical Proposal.
Offerors are to submit an email with the subject line: “[Company Name] PROPOSAL – 47PD0123R0023 – Charleston East Repair and Alteration – Single Award IDIQ Construction Project”.
The Request for Proposal (“RFP”) Package shall consist of two (2) volumes (separate files) as shown below. Files shall not contain classified data and the use of hyperlinks in proposals is prohibited.
(1) Price Proposal Attachment labeled “[Contractor Name] Pricing Proposal – 47PD0123R0023 – Charleston East Repair and Alteration – Single Award IDIQ Construction Project”.
mailto:Patrick.spellman@gsa.gov mailto:George.garcia@gsa.gov
(2) Technical Proposal Attachment labeled “[Contractor Name] Technical Proposal – 47PD0123R0023 – Charleston East Repair and Alteration – Single Award IDIQ Construction Project”.
(3) Offerors are encouraged to make their proposals only as voluminous as is necessary to respond to the preparation instructions set forth in the solicitation. In addition, notice should be taken of any attachment size or page limitations specified in the instructions below.
Offerors are required to submit proposals as delineated below:
a. Technical Proposal: The technical proposal must contain all the necessary information to address the evaluation factors as set forth in the solicitation. The maximum page limit for the technical proposal submission is 14 pages. If more than 14 pages are submitted, only the first 14 pages will be evaluated.
The Technical Proposal will consist of the following:
1. Technical Proposal (pdf format) including:
a. Detailed narrative of the three (3) Prior Experience on Relevant Projects primary projects submitted in response to Technical Factor 1
b. Approach & Management Plan information provided in response to
Technical Factor 2
2. Project Experience Information Worksheet
3. Experience Workbook Spreadsheet (excel)
4. Past Performance Questionnaires
Technical Proposal Page Limit:
All pages submitted as a part of an offeror’s technical proposal will count against the page limitation (exceptions provided below) including, but not limited to:
5. Transmission pages,
6. Cover Sheets,
7. Title pages,
8. Introduction Letters / Introduction statements
9. Tables of Contents,
10. Prior Experience on Relevant Projects primary projects narrative
11. Approach & Management plan (including resumes)
12. Performance recognition documents such as awards, letters of commendation, and any other performance recognition submitted in response to Technical Factor
The following items are excluded from the page limit:
1. Project Experience Information Worksheet
2. Experience Workbook Spreadsheet (excel)
3. Past Performance Questionnaires
NOTE: All pages in the technical proposal must be 8.5 inches by 11 inches. Pages that differ from these page dimensions will not be evaluated.
Other: Forms provided by GSA that should be included in the price proposal (amendments, 527's, financial information etc.) are excluded from the page limitation.
b. Pricing Proposal: The pricing proposal, which must be separate from the technical proposal, must contain the following information in the formats delineated below:
• Signed Standard Form 1442 with all amendments acknowledged
• Signed bid offer and submission of bid sheet
• GSA Form C301, Representations and Certifications
• GSA Form 527, Contractor’s Qualifications and Financial Information
• If applicable, SF LLL – Pages 1 and 2
• If applicable, Joint-Venture Agreement and any Mentor-Protégé Agreements
• The information required under FAR 52.215-1(c)(2)
• Any other information required by the solicitation
3. Electronic Submission:
The Technical and Price proposal must be submitted as separate Portable Document Format (PDF) attachments in an email. Hard copy submissions will not be accepted.
II.C. Price Proposal
(1) Contents The Price Proposal shall consist of the SF-1442 and the Agreement, with the Total Evaluated Price shown in box 17; the Signed Bid / Offer Spreadsheet (For the 1 Locality Bid Factors)
(2) Qualifications, Exclusions and Conditions If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
(3) Additional Proposal Requirements There is one (1) locality Bid Factor required for the entire five (5) year Indefinite Delivery/Indefinite Quantity (IDIQ) contract, which will apply to all work items for which a unit price is stated in the most current version of the RS Means Building Construction Cost Data. (Example: The unit prices listed in the 2023 RS Means Building Construction Cost Data are bare costs and are based on national averages. Bare cost equals a factor of 1.000, the same as “NET”, all other bid factors “MINUS” or “PLUS” will be added or subtracted from the bare cost factor. A “MINUS” 4% shall be written 0.96, a “PLUS” 4% shall be written 1.040 and “NET” shall be written 1.000.) The single offered bid factor for the base and each option period will be applied to all work items for which a unit price is stated in the Price Schedule that are ordered via task orders in the respective base/option period.
2. BID GUARANTEES AND PERFORMANCE BONDS
a. Bid Guarantees and Performance Bonds may be required on a task order basis. Bid and Performance Bonds are not required in response to this solicitation.
b. Prior to commencement of work on an awarded task order, the contractor will be required to provide Performance and Payment Bonds or alternate payment protection, as follows:
(1) Orders less than or equal to $35,000: No additional protection required
(2) Orders over $35,000 but less than or equal to $150,000 --> Payment Bond or Alternate payment protection in accordance with FAR 52.228-13, Alternative Payment Protections.
(3) Orders over $150,000 --> Performance Bond: 100% of the awarded delivery order amount. Payment Bond: 100% of the awarded delivery order amount.
c. When additional bonding is required, the provisions of FAR 28.102-2(b)(1) and FAR 28.102-2(b)(2) shall apply.
II.D. Technical Proposal The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.
NOTE: The following Non-Price Factors are listed in descending order of importance.
Technical Factor 1: Prior Experience on Relevant Projects This criterion will be used to measure the breadth, depth, and relevance of an Offeror’s experience in performing contracts and projects similar in size, scope and complexity to the one described in this solicitation.
For purposes of evaluation, a “ project ” is a discrete project, and is not an Indefinite Delivery Indefinite Quantity (IDIQ) , Blanket Purchase Agreement (BPA), or other type of master ordering instruments. Ordering instruments are considered a “contract” for purposes of evaluation.
Pertaining to this factor, each offer shall submit the following:
a. Factor 1 Primary Projects Detailed Narrative - The technical proposal must include a detailed narrative of three (3) primary Factor 1 projects submitted in response to Technical Factor 1,
b. Project Experience Information Worksheet completed for the offeror’s three
(3) primary Factor 1 projects, and
c. Experience Workbook Spreadsheet (excel).
The Factor 1 Primary Projects Detailed Narrative will be evaluated to determine project relevance to this procurement.
RELEVANCY CHARACTERISTICS
Project characteristics that will tend to demonstrate that a firm's prior experience is relevant to this project include the following:
1. General Construction / Repair and Alteration Experience including but not limited to:
• Roof repair and installation
• Exterior renovation
• Waterproofing
• Design/Build services
• Mechanical and electrical modernization
• General office renovations
2. Level of self-performance - The ability to self-perform is highly relevant to this procurement.
3. Project location within West Virginia;
4. Project with the Federal Government;
5. Project in a Federal Building;
6. Job Order Contract (JOC) experience;
7. Smaller projects with a value ranging from $10,000 to $50,000 may be considered more relevant than those exceeding $50,000. (Historically, the vast majority of projects fall towards the lower end of the $2,000.00 and $250,000.00 range. As a result, GSA considers demonstration of prior experience towards the lower end of this range (ie: between $10,000 and $50,000) to be more relevant under this technical factor);
8. Project in an occupied building;
9. Project Specialty Trade Experience (i.e. Electrical, Plumbing, HVAC, Fire Alarm, etc.).
For each project included in your submission, please include the following:
1. Project name and description;
2. Project location;
3. Project start/completion date;
4. Percentage and description of self-performed work;
5. Contract value at time of award and contract value at project completion;
6. Indicate whether the project is a Federal Government project located in a
Federal Building
7. Indicate if project is on a Job Order Contract (JOC)
8. Please provide a reference (including valid phone number and email address) for each project. This can be the customer and owners for contracts and projects listed in this section of their proposal. The Government may contact the POC’s to verify the information provided and may request past performance information.
9. Indicate Project Delivery Method
- Traditional-Design/Bid/Build
- Design/Build
The offerors shall also submit the “Experience Workbook” and provide no more than 25 contracts and/or projects performed within the last 5 years from the proposal due date.
These projects shall meet the same “Relevancy Characteristics” outlined above. The purpose of this spreadsheet is to demonstrate an offeror’s relevant prior experience, in addition to what is provided in each offeror’s Factor 1 Primary Projects Detailed Narrative, and the ability to simultaneously perform multiple projects of varying scope, size, and complexity for a variety of clients in multiple locations within the past 5 years. The contracts and projects the offeror selects must be relevant to the solicitation and future task orders that will be placed against this IDIQ. An offeror is not required to submit 25 projects, this is the maximum. These projects will be evaluated for relevancy Extra consideration will be given to firms demonstrating an Experience Workbook containing relevant project characteristics.
Projects that are not at least 75% (Period of Performance) complete will not be considered relevant.
*General Construction for this solicitation is defined as the supervision, administration, and performance for all construction activities required to complete a project successfully.
Construction activities for the anticipated solicitation include but are not limited to commercial office construction and/or renovations/repairs, MEP (Mechanical/Electrical/Plumbing) repairs/modifications/replacement, fire sprinkler systems repairs/modification/replacement, sitework, exterior construction repair and alterations (including facades and roofs), demolition (including abatement of hazardous materials), elevator modernizations and any other construction activities the government may require.
If proposing a joint venture, offerors shall clearly state which project were performed by the Joint Venture or an Individual Entity in Column D “Brief Description” in the Experience Workbook. Contracts/Projects performed by the Joint Venture will receive more consideration than contracts/projects performed by the individual entities separately.
Additional Information for Joint Ventures will be required in Factor 2 Approach and Management Plan.
An Offeror who successfully demonstrates that they possess the depth and breadth of project/contract experience that is considered most relevant when compared to the solicitation may receive a higher rating. If the offeror fails to meet any characteristic this may be considered a high risk. An offeror who fails to demonstrate they have relevant experience compared to the solicitation may receive a lower rating.
Technical Factor 2: Approach & Management Plan
The Government will evaluate each Offeror’s relative understanding of the contract requirements and to the extent their proposed approach meets the government needs.
The Government has the right to incorporate all or part of the Contractor’s proposed Approach & Management Plan into the contract. If incorporated, the Approach &
Management Plan will be binding upon the Contractor and the Government. Below are specific items which must be completely addressed by the Offeror in the proposed Approach & Management Plan.
a. Approach: The Offeror shall demonstrate their overall approach by demonstrating sound means and methods to ensure organizational management for the contract.
i. At a minimum the Offeror’s Approach must demonstrate how they will approach:
1. Providing general construction services within the geographical area
a. This must be supported by Projects provided in Factor
b. Offerors who demonstrate capability to perform throughout the entire area is considered favorable, but not required to be considered for award
2. The different Project Delivery Methods
3. Prepare proposals to multiple solicitations
4. Perform multiple projects simultaneously
5. Security, including HSPD-12 Process
6. Submittal Process;
7. Quality Control,
8. Safety,
9. Closeout,
10. Communication, and
11. Any other information an Offeror deems vital to successful performance.
ii. As part of the IDIQ approach offeror shall provide a letter from their surety confirming they have the following minimum bonding capabilities;
1. Individual Project- $250,000.00
2. Aggregate Total- $2,000,000.00
ii. As part of the IDIQ approach offerors shall provide a Certificate of Insurance (Acord 25) demonstrating they meet all the contractual requirements of the IDIQ;
1. General Commercial Liability- $500,000.00;
2. Automobile;
a. Per Person-$200,000.00
b. Per Occurrence for Bodily Injury-$500,000.00
c. Per Occurrence for Property Damage- $20,000.00
3. Worker’s Compensation- $100,000.00
4. Or Umbrella Coverage- $500,000.00
b. Management Plan: The Offeror’s management plan must include a detailed description of how the Contractor intends to provide general construction services.
The management plan must include, at a minimum:
i. Narrative that clearly describes how the offeror will staff the contract to successfully perform general construction services. It must address the following items
1. Interaction between the home office and the project sites during construction.
2. How they plan to recruit and retain home office and field office personnel (Contract Managers, PM, Supers, etc), in- house labor force (if applicable, tradesmen), and Trade Subcontractors.
3. Offeror must indicate which trades they are able to self-perform with their in-house labor force. If offerors perform in house A/E services this must be presented here.
4. Offeror must provide the name and location of key subcontractors (MEP (Mechanical/Electrical/Plumbing) repairs/modifications/replacement, fire sprinkler systems repairs/modification/replacement, sitework, exterior construction, demolition, etc) including A/E firms for Design/Build projects, whom they have previously worked with for major trades within the geographical area and indicate which projects they have previously worked with them in Factor 1. Key Subcontractors will not be evaluated for experience or performance, only to establish the prime contractor has available resources within the geographical area to perform future task orders. This does not bind the offeror to use these subcontractors for future orders or prohibit them from working with other subcontractors.
ii. Organizational Chart and Line of Authority to manage the IDIQ Contract and subsequent task orders.
iii. Resumes: Resumes shall at a minimum list the position, title, years served, responsibilities, physical locations, degrees, training, certifications and the firm for which the employee works. Key personnel are at a minimum the following positions:
1. Owner/Executive/Operations Manager;
2. Project Manager(s) (at least one);
3. Superintendent(s) (at least one); and
4. Any other personnel the offeror determines to be key to successfully meet the requirements of the IDIQ and subsequent general construction task orders. The offerors must consider how they will staff a typical task order issued against the IDIQ from the home office and in the field.
Personnel with more relevant experience/degrees/training/etc to the contract requirements may receive greater consideration. Personnel with minimal relevant experience/degrees/training/etc may be assigned weaknesses. Personnel with no relevant experience/degrees/training/etc may result in a high weakness.
The resumes of the personnel submitted will set the baseline qualifications of each position for the entirety of the IDIQ contract. If the offeror is selected for award of an IDIQ the awardee shall at a minimum provide personnel that match or exceed the qualifications of the proposed personnel for each task order award . Failure to do so may lead to options not being exercised.
Joint Venture Requirements
i. All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.
ii. An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.
iii. In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.
iv. Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.
The SSEB Technical board will evaluate each Offeror’s relative understanding of the contract requirements and to the extent their proposed approach meets the government needs. The government will assign strengths and weaknesses identified in its evaluation of the proposal. Failure to provide all the information being requested in the solicitation may result in lower ratings. The board will assign the rating that best describes its findings of the offeror’s Approach & Management Plan.
Technical Factor 3: Past Performance on Relevant Projects
The Government will evaluate each Offeror’s past performance by how well they performed on completed projects of similar size, scope and complexity as required by the solicitation.
a. The offeror shall submit a Past Performance Questionnaire (PPQ) (included in the solicitation) completed by the applicable client, for each of the three (3) “Highlighted Projects” included in its proposal for Factor 1. Completed PPQs shall be submitted with the proposal. Ensure correct phone numbers and email addresses are provided for the client point of contact who can attest to the level of acceptability of the services provided. Offerors must follow-up with clients/references to ensure timely submission of questionnaires. If the Offeror is unable to obtain a completed PPQ from a client for a project before proposal closing date, the Offeror must complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the project.
b. Offeror may include performance recognition documents received within the last five (5) years such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition. Please note the PPQ requests mentioned above are for projects completed within the last three (3) years.
c. In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS/UEI numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), previously submitted PPQ information, and any other known sources not provided by the Offeror. While the Government may elect to consider data from a variety of sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. GSA will not maintain a database of PPQs submitted by Offerors.
NOTE : THE GOVERNMENT HAS THE RIGHT TO CONTACT ALL CLIENT POCS
PROVIDED TO VERIFY THE INFORMATION PROVIDED BUT IS NOT REQUIRED TO.
d. Offerors shall NOT incorporate by reference into their proposal PPQs previously submitted for other RFPs.
e. If proposing a joint venture, Offerors must first submit past performance records demonstrating that they have performed together. These experiences will receive more consideration than experiences performed separately.
f. If the Offeror has no record of relevant past performance or the information on their past performance is not available, the Offeror may not be evaluated favorably or unfavorably on past performance. This rating shall be characterized as "neutral".
Proposals that exhibit relevant experiences and provide the Government a high level of confidence that the Offeror will successfully perform the required effort will receive the highest ratings. If an offeror’s past performance indicates any unsatisfactory performance on previous projects this may be considered additional risk and be assigned a weakness.
II.E. Other Information to Submit with Proposal
(1) Representations and Certifications Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management. Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204- 8), using the attached Offeror’s Representations and Certifications (C301).
(2) Qualifications of Offerors Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract.
Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.
II.F. Requirements of Joint Venture Offerors
(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.
(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.
(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.
(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.
https://www.sam.gov/
III. General Provisions III.A. Availability of Funds Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.
III.B. Requests for Clarification or Interpretation The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 15 calendar days. Prospective Offerors must make such requests not less than 15 calendar days prior to the date set for receipt of offers.
III.C. Notice to Small Business Firms A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.
III.D. Information Concerning the Disclosure of Solicitation Results This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.
III.E. Affirmative Procurement Program GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products.
Offerors must familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement. Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.
III.F. Notice Concerning Preparation of Proposals Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
III.G. Bond Requirements http://www.sba.gov/
If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties must note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.
III.H. Contractor Performance Information
(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment Completed CPARS evaluations may then be used by Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.
AWARDEES shall be evaluated at the IDIQ base level annually.
(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an email that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.
(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.
(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.
Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.
GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.
Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.
III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information http://www.cpars.gov/ https://www.cpars.gov/lc.htm
Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.
IV. FAR/GSAR Solicitation Provisions IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29
(AUG 98)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to—
GSA Federal Supply Service Specifications Section, Suite 8100 470 East L’Enfant Plaza, SW Washington, DC 20407 Telephone (202) 619-8925 Facsimile (202) 619-8978
(b) If the General Services Administration, Department of Agriculture, or
Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision.
Additional copies will be issued for a fee.
IV.B. FAR 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (JUN 1988) (Applicable to solicitations that cite specifications not listed in the Index and are not furnished with the solicitation)
(a) The specifications cited in this solicitation may be obtained from: GSA Specifications Unit at (202) 755-0325. MIL Specifications may be obtained by calling
(215) 697-2179.
(b) The request must identify the solicitation number and the specification required by date, title, and number as cited in the solicitation.
IV.C. FAR 52.216-1 Type of Contract (APR 84)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
IV.D. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work
(MAY 14)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
IV.E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999) (Applicable to solicitations resulting in construction contracts in excess of $10,000.)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade Goals for the varying counties may be found at:
https://www.dol.gov/sites/dolgov/files/ofccp/ParticipationGoals.
GOAL FOR FEMALES 6.9%
GOALS FOR MINORITIES
These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is: eastern West Virginia.
IV.F. Buy American Requirements FAR 52.225-10…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .