Architect-Engineer (A/E) Services for Water Infiltration Remediation, Alexander Hamilton U. S. Custom House
Solicitation number
47PC0318N0001
Issued by

About this file

This document is a combined synopsis and solicitation notice for architectural-engineering services. The General Services Administration is seeking design and construction services for a two-phase water infiltration remediation and restoration project at the Alexander Hamilton U.S. Custom House in New York City, which is owned by GSA and houses several federal agencies including the U.S. Bankruptcy Court and Smithsonian Institution. Phase I involves below-grade waterproofing and structural rehabilitation with an estimated construction budget of $44.5 million, while Phase II includes installation of exterior blast windows and repairs to the skylight and laylight with an estimated $38.5 million construction budget. Responses are due by May 17, 2019 following a two-stage qualifications-based selection process, with interviews for shortlisted firms scheduled for August 2019 and contract award anticipated in December 2019. The selected firm must demonstrate at least 35% of contract services will be performed in New York City to receive full evaluation credit.

Alexander Hamilton Project Overview for Presubmittal Conference Slides

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. General Services Administration

Water Infiltration Remediation Alexander Hamilton U.S. Custom House

Architect-Engineer (A/E) Services Pre-Submittal Meeting presented by Mike Hogg

4-18-2019

2Photograph c. 2007 By Carol M. Highsmith

Program Overview

Alexander Hamilton U.S. Custom House 1 Bowling Green, New York, NY 10004

• 379,415 Rentable Square Feet

• 9 Levels - 7 Stories Above Grade + Basement and Subbasement

• Construction 1900-1907

• National Historic Landmark (1976)

• Primary Tenants:

� U.S. Bankruptcy Court � National Museum of the American Indian | Smithsonian Institution (NMAI) � National Archives at New York City (NARA) � U.S. Department of Transportation (USDOT) � Federal Trade Commission (FTC)

Project Description Phase 1 – Water Infiltration Remediation

Remediate water infiltration at basement & sub-basement including sidewalk vault

Leak mitigation for vehicle ramp, access hatches, exterior joints Repair/Replace damaged structure Repair/Replace Mechanical, Electrical, Plumbing components Removal of Hazardous Materials

Phase 2 – Windows, Skylight, Laylight, Artwork Restoration Replace windows for improved efficiency and blast mitigation Repair/Replace Skylight and Laylight Restore murals in the rotunda and perform Conservation

Project Description

• Building Envelop Waterproofing

• New York City Sidewalk Vault Inspection and Repair

• Structural Rehabilitation

• Remove failing terra cotta fireproofing

• Inspect, Repair or Replace Structural Steel

• Blast Mitigation

• All exterior Windows

• Courtyard windows only where analysis shows is needed

• 13 window types totaling 557 windows of varying size.

• Art Conservation

• Historic Preservation

Design Considerations

• Building to remain operational throughout construction

• Permissions, Permits, Approvals, Coordination including but not limited to:

• New York City Department of Buildings (D.O.B.)

• New York City Department of Environmental Protection (D.E.P.)

• New York City Department of Transportation (D.O.T.)

• City of New York Department of Parks and Recreation (D.P.R.)

• Metropolitan Transportation Authority (M.T.A.)

• Consolidated Edison (Con Ed)

• National Grid

• New York City Landmarks Preservation Commission (L.P.C.)

• The building is a National Historic Landmark, any work carried out in this building must be closely monitored to avoid any damage to historical elements.

An historic preservation consultant will be bought on board as part of the AE team. Section 106 review will be followed in accordance with NYSHPO and

ACHP.

Project Schedule

Phase 1 Phase 2

Design Start Jan 2020 Jun 2021

Concept Design Presentation

May 2020 Oct 2021

100% Construction Documents

Jun 2021 Oct 2022

Construction Start Aug 2021 Dec 2022

Substantial Completion Dec 2024 Apr 2026

Phase 1 Design

Phase 2 Design

Phase 1 Construction

Phase 2 Construction

All timeframes are approximate

Procurement Schedule

Responses Due May 17, 2019 3:00 pm Eastern

Issue Shortlist Mid July 2019

Stage II Interviews August 14-15, 2019

Selection September 2019

Contract Award December 2019

All timeframes are approximate