47PB0022R0012 Tab 10 Amendement A0001 SIGNED 2022 02 16.pdf

PDF 212 KB Posted

Attached to
Moakley Elevators Modernization Project
Solicitation number
47PB0022R0012
Issued by

About this file

This document contains questions and answers related to solicitation number 47PB0022R0012 for the Moakley Elevators Modernization Project. Key details include that the scope of work involves replacing elevator equipment and modernizing four passenger elevators and one grand jury elevator. The freight elevator must be used for all equipment removal and delivery, with escort provided through restricted areas. Masks are required in common areas and work may proceed without masks in dedicated work areas. Daily check-in is required through the facilities office and escort will be provided into secured spaces. Testing will involve standard safety tests to certify the elevators for public use. The latest ASME A17.1 code at time of installation applies. Space will be provided for materials staging.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

R10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A0001

1PQC

David Mark, Contracting Officer

Solicitation referenced in Block# 9a for the Moakley Elevators Modernization Project is hereby amended as follows:

1. Pre-proposal Site Visit Agenda, Attendee List, and corrected SF1442 are attached.

2. Answers to offeror questions are provided on the following pages.

3.The Davis-Bacon Wage Determination is updated to Gen. Dec. No: No: MA20220001 02/11/2022 (attached).

4. All other terms and conditions of the solicitation remain unchanged.

5. Offerors are reminded that they must acknowledge receipt of this amendment by one of the methods outlined in Block 11.

US General Services Administration, Public Buildings Service, Region 1, Acquisition Management Division (1PQ), 10 Causeway St., Room 1100, Boston, MA 02222

47PB0022R0012

02/16/2022

01/25/2022

Digitally signed by DAVID MARK DN: C=US, O=U.S. Government, OU=General Services Administration, CN=DAVID MARK + OID.0.9.2342.19200300.100.1.1=47001003322662

Reason: I am the author of this document Location: your signing location here Date: 2022.02.16 09:19:37-05'00' Foxit PDF Editor Version: 11.1.0

DAVID MARK

2/16/2022

PAGE OF PAGES

1 3

Moakley Offeror Questions

Question 1: I am looking for clarification on the items below regarding the Moakley Courthouse modernization project:

Compensation (whisper flex) – Assuming this being retained

Governor- Assuming this being retained

Answer 1: Whisper flex will be replaced if any section is damaged and needs replacement.

Governors will be replaced.

Question 2: Can the passenger elevators (Car 13-16) or the Grand Jury Elevator (Car 18) for equipment removal and delivery?

Answer 2: No, the contractor has to use the freight elevator (Car 11) for all the equipment removal and delivery. Escort will be provided for access through the US Attorney Office.

Question 3: Specification Section 01 14 00: (1.3, D) What constitutes noisy work and/or odor-producing work?

Answer 3: Noisy work would be hammering or using impact wrenches during court proceedings. We can usually work with contractors on the best times to allow use of any heavy noise making machinery or tool. Odor producing work would be welding.

Question 4: Specification Section 01 14 00: (1.1, C, 19) What are the specific COVID procedures at the property?

Answer 4: Masks will be worn during all times while traveling through the building. If you are working in a space which is considered your work area, a mask is not necessary. We also request that employees are in compliance with CDC guidelines.

Question 5: Specification Section 01 14 00: (1.1, C, 15) What is required to gain daily access at the property? Check-in/out procedures, Badging, Security detail, Etc.?

Answer 5: We will require all contractors to sign in/out in the Facilities office. All contractors who have been cleared in accordance with Section III.H.5 of the Agreement will be escorted into the USAO space to the machinery room.

Question 6: Specification Section 01 59 50: (1.4, A. 9) Are the elevator pits considered confined space?

Answer 6: Elevator pits are not considered confined space.

Question 7: Specification Section 14 21 23: (3.16, A) Please define the scope of acceptance testing that will be required by the federal government and/or United Elevator Consultants, as well as the cost of any permits attributed with the tests?

Answer 7: Test will be code required safety tests to put elevator in service for general public use. No additional cost associated with testing.

Question 8: Specification Section 14 21 23: (2.3, B, 3) What is the specific code-year required

(elevator code ASME)?

Answer 8: Latest applicable code at time of install ASME a17.1 – 2019.

Question 9: Specification Section 14 21 23: (1.5, C) Are the original equipment drawings (from

OEM) able to be provided to bidder by GSA?

Answer 9: Contractor will be providing new equipment drawings & engineering layouts.

Question 10: Specification Section 14 21 23: (2.3, A) Is the intent to send this SOW to a machine shop, so that they can quote all of the work in full on all elevators? It may be deemed that all work specified may not be required, but do we continue the full SOW on these machines?

Would it make sense to have a machine shop come out and do an on-site survey of the equipment and write a specification for work required for all to bid on?

Answer 10: If contractor does not do work specified, they will have a sub come in and perform this specific task.

Question 11: Specification Section 14 21 23: (2.13, B) Is the plan to keep the sling and replace the platform? If so, what is the issue with the platform that needs to be resolved?

Answer 11: Platform is original and a new isolated platform will be installed for better ride quality.

Question 12: Specification Section 14 21 23: (2.13, G, 1). Please define what is meant by

Convenience light?

Answer 12: This lighting is for the elevator contractor to use. It’s located above and below cab.

Question 13: Is there a space available for materials staging?

Answer 13: We will provide an area to allow job boxes and material to be stored.