This document summarizes an amendment to a solicitation for renovations at the St. Albans Federal Building in St. Albans, Vermont. The amendment provides clarification on key personnel qualifications, modifies specifications for HVAC system replacements and renovations, and includes questions and answers from potential offerors. Renovations include replacing multiple air handler units with more efficient VFD and VAV units, integrating new units into the existing building automation system, and completing bathroom and Customs and Border Protection port renovations involving asbestos abatement and ceiling work. The estimated price range for the base work and three option periods is between $1 million and $5 million. The solicitation is a 100% small business set-aside under NAICS code 236220. The response due date is September 10, 2021.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Solicitation 47PB0021R0053, CBP Port Bathroom Renovations, Full Port Refresh and AHU
Replacement at the St. Albans Federal Building (VT0018ZZ) in St. Albans, VT is hereby amended as follows:
1. Volume II, The Solicitation, II.D. Technical Proposal, Factor 3 Relevant Experience of
Key Personnel Qualifications is amended to change on-site electrical superintendent to on-site construction superintendent.
FROM:
At a minimum, the build key personnel for the project must consist of the following positions:
•project manager
•on-site electrical superintendent
TO:
At a minimum, the build key personnel for the project must consist of the following positions:
•project manager
•on-site construction superintendent
2. Volume III, The AHU Specifications dated 07/13/2021, Section 011000, 1.1 B Project
Summary Description is replaced as follows:
Base Work: Modify the existing HVAC system to make the system more efficient and easier to maintain as well as bringing them up to current code. The work involves removing multiple constant volume air handler units and replacing them with more modern air handler units utilizing VFD's and VAV's. The existing boilers and hydronic components will remain.
Major reconfiguration of some existing ductwork will be required and the system will need to be integrated into the existing building automation system.
Option 1: Option work includes CBP Port Renovations, Lead and Asbestos abatement, Ceiling work and the Bathroom renovations, all which are included in the CBP Port
Renovations Design and Specifications.
Option 2: Option work includes the additional HVAC related work and additional select interior demolition required if Option 1 is exercised. Pricing for Option 2 shall factor in the reduced effort for acoustical ceiling systems as this effort is carried in option 1.
Option 3: Option work includes the replacement of air handler unit 1 which feeds the 1st floor space of the original 1937 section of the building. All work to be completed as detailed in the design
3. Attachment A.1 The AHU Drawings dated 2021 07 13, drawing G-0001, Schedule of
Options section is revised as follows:
Option 1: Option work includes CBP Port Renovations, Lead and Asbestos abatement, Ceiling work and the Bathroom renovations, all which are included in the CBP Port
Renovations Design and Specifications.
Option 2: Option work includes the additional HVAC related work and additional select interior demolition required if Option 1 is exercised. Pricing for Option 2 shall factor in the reduced effort for acoustical ceiling systems as this effort is carried in option 1.
Option 3: Option work includes the replacement of air handler unit 1 which feeds the 1st floor space of the original 1937 section of the building. All work to be completed as detailed in the design
4. See attached Questions and Answers set 1.
The proposal due date has not been extended and remains due on September 10, 2021 by
2:00PM EST.
All other Terms and Conditions remain the same.
Offerors are reminded to acknowledge receipt of this amendment by one of the methods cited in
Block 11.
CBP Port Renovations, Full Port Refresh, and AHU Replacements St. Albans Federal Building (VT0018ZZ)
St. Albans, VT
Solicitation 47PB0021R0053
Question and Answer Set 1.
1. What is the schedule for the project?
ANS: Please reference Volume I, The Agreement, I.C. Period of Performance. The period of performance is 270 Calendar Days from Notice to Proceed (NTP). NTP is estimated to be issued mid October.
2. Who is the contractor providing service for the sprinkler system in the building?
ANS: Firetech Sprinkler Corp. 340 Hegeman Drive, Colchester, VT 802-655-1800
3. Is there any way of finding out what company, if any, has the warranty on the roof for this project?
ANS: GenFlex Roofing Systems, Inc. Job # QA4938. Warranty # GH100573. Rep. Bob Holmes 413-657-8452
4. Who is the Controls contractor for this building?
ANS: Alliance Mechanical
5. Where do dumpsters go?
ANS: The awarded contractor shall coordinate with the City of St. Albans to place a dumpster in parking spaces along Stebbins Street.
6.What is being done with the items currently located in room 157, 158 & 158a?
ANS: The awarded contractor will be responsible for the moving of the items within these rooms.
Room 157 is a locker room and this room will be moved to room 134. Rooms 158 and 158a, items will be relocated to the basement into rooms B38 and B45a.
7. Can you please confirm if you will be installing cabinets in 205B and 211 and if yes what are the specs needed for upper and/or lower cabinets.
ANS: 205B and 211 are for the mens and womens showers. There are no cabinets being installed in these 2 spaces.
8. Who is providing the Lockers in rooms 205B and 211? If the GC, is there a model and specification for these that can be provided?
ANS: 205B and 211 are the mens and womens showers. There are no lockers in these spaces.
Rooms 205A and 209 and the locker rooms. The contractor is to provide lockers as listed in drawing A 4 02. Product basis of design per CBP: Tiffin Airflow Wardrobe Locker with securable compartment, drawer base, 18" wide by 72" tall and 24" deep.
https://tiffinmetal.com/airflow-locker/
9. Could I get some help with a model or specification for what you are looking for on the padded wall? Reference Attachment A The Drawings 2021 07 26, Drawing A-1-03 note 14.
ANS: Basis of Design is “Resilite The Mat Company”. Model: Guardian - Conventional” Thickness: 2 inch.
10. I have a contractor that would like to perform the demolition, drywall and ceiling work on this project, However the question has come up is can they work there? A lot of these guys only have green cards to work and other or in the process of getting them. He would like to know if that would affect his being able to work on this project?
ANS: Please reference GSA Access Card FAQs | GSA
11. Specification section 230923 is based on a “new” BAS system, Drawing M-701 makes reference to the new DDC controls required for this projects scope are to be an extension of the existing BAS. Please clarify the intent is as shown on drawing M-701, the new DDC controls required for this projects scope are to be an extension of the existing BAS, a Distech Niagara N4 system.
ANS: The previous Niagara system (Niagara AX) was replaced with a Distech branded Niagara N4 system. Existing end of life Niagra AX based JACES were replaced with Distech branded JACE 8000s (Distech Bos-8).
The system is set on a GSA Virtual Server (Distech N4 Supervisor).
The existing system referred to on drawing M-701 is the newly installed Distech Niagara N4 system.
12. Existing Pneumatic Controls; Please clarify if the existing pneumatic controls in the mechanical rooms are to be 100% removed, including all of the existing cable tray systems in place housing pneumatic controls lines, or the existing pneumatics only to be removed to the last active branch?
ANS: Remove all existing pneumatics including the existing cable trays to equipment being removed in the attic. Notify GSA before removals if found that pneumatics is needed for equipment to remain.
https://tiffinmetal.com/airflow-locker/ https://www.gsa.gov/technology/government-it-initiatives/identity-credentials-and-access-manage/gsa-access-card-faqs#f
13. Will any area of the parking deck to the West of the building be available for use by the G.C?
ANS: There will be no on site parking or laydown space available for use other than your work areas.
14. Can you provide a plan indicating what areas and offices of the building are intended to be occupied during construction?
ANS:The entire building will be occupied during construction. The 2nd floor work will be phased so your specific work area will be unoccupied during construction but the other areas will be staffed. The first floor and basement spaces will be occupied.
15. I’m unable to find a spec for the athletic flooring scheduled for rooms 212 & 214, please provide.
ANS:There is no specific specification on this. The CBP design guide states the following:
Athletic resilient flooring (FF-06) shall be provided for the physical training rooms and the health and wellness center and shall be a manufacturer's product designed specifically for the purpose, cushioned, and have a waterproof finish suitable to be wet mopped.
The Basis of Design used: Tarkett / Sports Multi-Function Flooring - Replay Multi-Functional and Sports Rubber Sheet and Tile
| topmostSubform[0]: |
| Page1[0]: |
| Code[0]: 1PQB |
| Copies[0]: |
| CheckBox9[0]: 1 |
| Code[2]: 1PQB |
| NameandTitleOfficer[0]: Sotheavy Khon, Contracting Officer |
| Is[0]: Off |
| CheckBox10[0]: Off |
| NameandAddress[0]: |
| DateSigned[1]: 09/02/2021 |
| Pages[0]: 2 |
| AmendmentNo[0]: 0002 |
| Dated10B[0]: |
| ModificationNo[0]: |
| AdministeredBy[0]: Acquisition Management Division (1PQ) Contract Operations Branch (1PQB) GSA/PBS |
10 CAUSEWAY ST., RM 1100
BOSTON, MA 02222-1077 USA
| FacilityCode[0]: | |
| CheckBox13B[0]: Off | |
| CheckBox13D[0]: Off | |
| ReqNumber[0]: EQ1PSKM-21-0096 | |
| Dated9B[0]: 8/13/2021 | |
| 2021-09-02T07:58:01-0400 | |
| SOTHEAVY KHON | |
| I am approving this document |
| C13[0]: |
| Description[0]: See attached. |
| NotExtended[0]: 1 |
| Code[1]: |
| AmendmentNo[1]: 47PB0021R0053 |
| ContractIDCode[0]: |
| DateSigned[0]: |
| CheckBox11[0]: 1 |
| Page[0]: 1 |
| AccountingData[0]: |
| CopiesReturned[0]: |
| CheckBox13A[0]: Off |
| IsNot[0]: Off |
| EffectiveDate[0]: 9/2/2021 |
| A13[0]: |
| ProjectNo[0]: RVT11049, RVT11023, N1699397 |
| CheckBox13C[0]: Off |
| Extended[0]: Off |
| D13[0]: |
| IssuedBy[0]: Acquisition Management Division (1PQ) Contract Operations Branch (1PQB) GSA/PBS |
10 CAUSEWAY ST., RM 1100
BOSTON, MA 02222-1077 USA
NameandTitleSigner[0]:
| Page2[0]: |
| TextField1[5]: |
| TextField1[4]: |
| TextField1[3]: |
| TextField1[2]: |
| TextField1[1]: |
| TextField1[0]: |
File details come from the government source that posted it. Updated .