This document contains a request for information (RFI) related to replacing radiation portal monitors (RPM) at multiple land ports of entry for Customs and Border Protection. The General Services Administration solicits contractor support to provide all labor, materials, and equipment to replace RPMs at Sweet Grass, Montana; Pembina, North Dakota; and Portal, North Dakota. Supporting infrastructure such as communications and power equipment must be installed to make the new RPMs fully operational. The period of performance is 80 calendar days from notice to proceed, with substantial completion required within 60 days and project closeout within 20 days thereafter. Testing of concrete and compaction work is required. The contractor must coordinate with local port authorities to maintain border operations during construction.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Number Question Answer 1 SF 1442 states 45 days POP
Bid Schedule indicates: 10/27/2022 -
11/30/2022 POP
I.C. Period of Performance indicates 10 weeks from NTP for POP
(1) Commencement. The Contractor shall commence performance of the Work within 10 days after the Contractor receives the Notice to Proceed (NTP).
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 10 weeks from issuance of Notice to Proceed (NTP).
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 30 calendar days of Substantial Completion
•1.7. PROJECT SCHEDULE
The overall Period of Performance shall be no greater than 80 calendar days from Notice To Proceed (NTP) to Project Closeout, based on the following:
NTP to Substantial Completion 60 calendar days after NTP Project Closeout 20 calendar days after Substantial Completion
2 Cold weather concrete spec needed? No. There is no separate concrete spec for cold weather. However, the contractor shall take all required precautions as specified in
"SECTION 03 3000 CAST-IN-PLACE
CONCRETE" of the Design Specifications document associated with for each of site.
3 Bollard depth adequate for freeze? The engineer of record has determined that frost heave for minor structures such as bollards and vis masts is not of concern.
4 Is testing required (concrete and compaction)?
Yes, testing is required as specified in
"SECTION 03 3000 CAST-IN-PLACE
CONCRETE" of the Design Specifications document associated with for each of site.
5 Can GSA passes be processed in time (within the POP)?
RPM West (Sweet Grass, Pembina, Portal) Sites Installation RFIs
47PA0322R0021
6 Will an extension for the POP be granted if material lead times are an issue?
The POP start will be discussed in relation to material lead times as necessary.