This is an Addendum No. 01 to a Request for Proposal issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration Design and Construction Division, for professional design and construction services related to the Northern Region Training Academy project managed by the Michigan Department of Corrections. The project scope encompasses remodeling two buildings at the existing Northern Region Training Academy complex, including Phases 400 (Preliminary Design), 500 (Final Design), 600 (Construction Administration—Office Services), and 700 (Construction Administration—Field Services). Services requested include design of WiFi systems, security and technology upgrades per MDOC standards, roof replacements with snow avalanche mitigation, elevator replacement, exterior concrete work including an exercise pad and instruction platform, entrance signage design, roadway and parking lot redesign, and general site beautification. The Professional Services Contractor (PSC) will work with a selected Construction Manager for cost estimating during Phases 400 and 500. A pre-proposal meeting was held on June 22, 2023, at the Northern Region Training Academy in Kincheloe, Michigan, with site accessibility and photography permitted. Proposals were due June 29, 2023, at 2:00 p.m. EST, and selection was scheduled for the State Ad Board Agenda on July 25, 2023. Construction documents were to be completed and released for bidding no later than autumn 2023 for winter 2023/2024 interior construction and spring 2024 for site work. The project will be bid as a whole with phased construction, with Building 233 (MSI building) to be completed first while Building 257 (main building) remains operational; upon Building 233 completion, operations will transfer to allow Building 257 construction to commence.
The RFP utilizes a Not-to-Exceed billable rate plus reimbursables format, with proposals evaluated on an 80% Technical portion and 20% Cost portion by an Ad Hoc Advisory Committee. Reimbursable expenses include a minimum of eight soil borings, material testing, concrete and steel testing, plan review fees (minimum eight reviews), and a $50,000 line item for Commtech Design to cover IT, security, technology, and DTMB infrastructure coordination. The PSC is responsible for leading bi-monthly construction progress meetings on-site, providing field reports within five business days of each site visit, and submitting meeting minutes within five days of each meeting. Travel reimbursement is provided at $0.625 per mile for travel beyond the first 100 miles each way, with per diem rates of $9.75 for breakfast or lunch and $22.00 for dinner, and lodging at $85.00 per day (negotiable post-award). No budget has been established; compensation will be based on the PSC's cost estimates. Asbestos abatement for both buildings will be completed by DTMB prior to construction, and the project includes site demolition work scheduled for summer 2024 under a separate contract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 RFP (Rev 2/22)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
REQUEST FOR PROPOSAL
ADDENDUM NO. 01
This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.
Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.
TO:
ALL PROPOSERS
DATE ISSUED
6/26/2023
PROJECT NAME
Northern Region Training Academy / Northern Region Training Academy
FILE NUMBER
472/23280.SDW
PROJECT DIRECTOR
Susan Wheaton RA
PROPOSAL DUE DATE:
June 29, 2023, at 2:00 pm EST
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
Attached please find:
1. Attendance / sign-in sheet
2. Meeting Agenda with revised items in Bold Purple.
3. RFI questions and responses.
4. It has bee decided that MDOC / DTMB will contract with a Construction Manager for this project. The
PSC is to work with the selected Construction Manager for all cost estimating during phases 400 and 500.
RFI questions / responses below:
Q1 – Is the Wi-Fi design by the PSC or DTMB infrastructure Team? Please provide delineation of work.
R1 – Per the walk through on June 22, 2023, the PSC is to include a $50,000.00 reimbursable expense for Commtech Design to cover this scope of work and coordination with DTMB infrastructure.
Q2 – Will both buildings be design simultaneously Phase 400 through plan review completion?
R2 – Per the walk through on June 22, 2023, design for both buildings will happen simultaneously but construction will be phased per building with building 233 being completed first and then building 257.
Q3 – Will the full project (site, main building, auxiliary building) be awarded to one contractor as one phase or shall PSC bids plan to have the CA for two separate phases of construction with two separate contractors?
R3 – The project will be bid as a whole with the buildings being phased as stated during the walk through on June 22, 2023. The Construction Manager (refer to note 4 above and added information in the meeting agenda) will be responsible for coordinating the phasing but the PSC will be responsible to complete bi-monthly inspections per the normal DTMB standards.
Q4 – For technology and security upgrades necessary per MDOC standards – may the firm provide their services or is there an assignment of subcontractor?
R4 – This will be covered under the Commtech Design reimbursable as indicated in Question / Response 1.
Q5 – Will an asbestos report be provided by DTMB to the contractors prior to bid? Is abatement necessary and if so, will it be a separate contractor contract agreement with DTMB?
R5 – An asbestos report has been completed for the main building 257 and abatement will be completed prior to construction. It is believed that building 233 also has an asbestos report and any abatement will be completed prior to construction.
APPROVED BY:
PROJECT DIRECTOR Susan Wheaton RA DATE June 26, 2023
GRETCHEN WHITMER
GOVERNOR
STATE OF MICHIGAN
DEPARTMENT OF TECHNOLOGY, MANAGEMENT & BUDGET
LANSING
MICHELLE LANGE
DIRECTOR
PRE‐PROPOSAL MEETING AGENDA
MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
Design and Construction Division
3111 W. St. Joseph Street Lansing, MI 48917
Revisions are in Bold Purple
Project: Northern Region Training Academy File Number: 472/23280.SDW Professional Services Contractor: TBD Contract Order Number: Y‐TBD Meeting Date and Time: June 22, 2023, 11:00 am Meeting Place: Norther Region Training Academy
PROJECT REPRESENTATIVES
Project Director: Field Representative:
Susan Wheaton RA Dan Hall
DTMB‐DCD DTMB‐DCD
P.O. Box 30026 1238 Carpenter Ave Lansing, MI 48909 Iron Mount, MI 49801 WheatonS1@michigan.gov Halld22@michigan.gov 517‐242‐9945 517‐284‐7921
Facility Representative: Facility Representative:
Trever LeBarre (MDOC – Physical Plant) Jeff Niemi 206 E Michigan Avenue 5086 W. M‐80 Lansing, MI 48933 Kincheloe, MI 49788 517‐643‐6518 906‐203‐1036 lebarret@michigan.gov niemij2@michigan.gov
Introductions and Sign‐In Sheet
A. Request for Proposals – Standard Not‐to‐Exceed RFP, with Part I Technical portion and
Part II Cost portion.
1. Technical – Qualification format includes: General Information; Understanding of the Project and Tasks; Personnel; Management Summary, Work Plan & Schedule; Budget Analysis and References. See Section II‐1 through 6.
2. Cost – Not to Exceed Billable Rate plus reimbursables format. See Section III‐1 through 2. See Section III 2‐A, B, C and D of RFP for samples.
3. Proposals must include Phases 400 Preliminary Design, 500 Final Design, 600
Construction Administration – Office Services and 700 Construction Administration – Field Services.
4. Include plan review fees, (minimum 8) soil borings and material testing as reimbursable expenses. Refer to the Project Statement.
5. Include signed Certification of a Michigan Based Business and Responsibility
Certification forms.
6. Proposals will be evaluated by an Ad Hoc Advisory Committee and scored based on the combined 80% Technical portion and 20% Cost portion.
B. Project Scope
The Michigan Department of Corrections is seeking professionals for the remodel of two buildings at their existing Northern Region Training Academy complex. The project will include Phases 400, 500, 600 and 700 design services. The MDOC has completed a schematic design / study for the two buildings but are open to revisions to the schematic design. Currently there is WI‐FI in the classroom building but it will need to be revised to meet the new floor plans. The second building will need to have WI‐FI included. Both buildings will require the standard security upgrades and technology upgrades per MDOC standards for administrative spaces.
Also, to be included are roadways, parking lots, sidewalks, and general beautification of the two areas of the complex.
Your proposal should include:
50 and 90% reviews with probable cost estimates for Phases 400 and 500. PSC will work with the selected CM to create cost estimates.
Revit / AutoCAD files will be provided for the existing buildings.
CAD files will be provided for the topo.
The PSC will be responsible for leading the construction progress meetings which will take place twice a month on site for the duration of the work. Meeting minutes will also be required to be sent out within 5 days after the meeting.
Testing for concrete, steel, rebar etc. are to be included as a reimbursable expense.
Plan reviews are to be included as a reimbursable expense.
Include as a line item Commtech Design as a $50,000.00 reimbursable expense to cover the IT, Security, Technology / DTMB coordination.
Part of the exterior work will also include a concrete pad for outside exercise, with a raised platform for instruction / graduations.
Design meetings will be via Teams.
Construction progress meetings will be via Teams, the PSC will be responsible for visiting the site twice a month and to provide a field report for each visit within 5 business days after the field visit.
The existing elevator shaft is to be reused for a new elevator.
The PSC will design a “street / road sign” at the entrance off of M‐80.
Replacement of the roofs on both buildings to be included, along with mitigation for preventing snow avalanches.
Construction of the MSI building 233 will be completed first while the main building 257 stays in use. Upon completion of building 233 the training academy will move over to building 233 so that building 257 construction can take place.
C. Site Visits
1. Accessibility to the site – today.
2. Photography is allowed.
D. Schedule
1. Proposals are due on Thursday, June 29, 2023, no later than 2:00 p.m. EST to issuing office / SIGMA.
2. Ad Hoc Advisory Committee will review proposals with the selected PSC to be placed on the earliest Agenda for approval or the State Ad Board Agenda for approval on July 25, 2023.
3. Construction documents complete and out to bid no later than Autumn for winter 2023 / 2024 interior construction and spring 2024 for site work.
E. Budget
A budget has not been set at this time and will be based on the PSC’s cost estimates.
F. Other Items
1. Access to Site Upon Contract Award
a. Normal business hours for facility, or hours in which work can take place will be determined by Jeff Niemi.
b. Provide notice to the facility prior to any site visits.
2. Travel Rates:
a. Breakfast or Lunch $9.75 per day
b. Dinner $22.00 per day
c. Travel – the first 100 miles each way will not be billed for as stated in the
RFP Not to Exceed proposal paperwork. Current premium rate is $0.625 per mile.
d. Lodging $85.00 day – negotiable after award of the contract.
G. Questions / Comments
1. E‐mail questions to Wheatons1@michigan.gov
2. Questions will be accepted until 5:00 p.m., Friday, June 23, 2023.
3. If necessary, an addendum will be posted on the SIGMA VSS website no later than noon, Monday, June 26, 2023.
4. There will be a site demolition project taking place the summer of 2024. Refer to provided PDF’s for reference. This work is being done under another contract.
H. Tour / Walk‐through
80' Light Poles
80' Light Poles
Electrical Poles
Baseball Diamond and
Associated Structures
Large Debris Pile
A1
Electrical Poles
Garden Shed
80' Light Poles
80' Light Poles
Cleanup Remnants of Former Greenhouses
Former Guard Shack Base
A2
Electrical Poles Electrical Poles
80' Light Poles
Baseball Diamond
Associated Structures and
Horseshoe Area
Benches Park
A3
Electrical Poles
Electrical Poles
80' Light Poles
Steam Vault
A4
80' Light Poles
Fences
Electrical Poles
Monument
Electrical Poles
Steam Vault
A5 Poles
80' Light Poles
Steam Vault
Electrical Poles
Electrical Poles
A6
Pole Remains Remove Siren
Former Gas Station
A7
Steam Vaults
Light Poles
Steam Vault
Flagpole
A8
All Sidewalks
| Photos of Areas-Materials to be Removed.pdf |
| Old Kinross - Area - 1.pdf |
| Old Kinross - Area - 2 |
| Old Kinross - Area - 3 |
| Old Kinross - Area - 4 |
| Old Kinross - Area - 5 |
| Old Kinross - Area - 6 |
| Old Kinross - Area - 7 |
| Old Kinross - Area - 8 |
| Photos of Roads and Parking Areas to be Removed.pdf |
| North Section - Roads and Parking Areas - 1.pdf |
| South Section - Roads and Parking Areas - 2 |