472-23130.SDW - Advertisement.pdf

PDF 79 KB Posted

Attached to
472/23130. SDW; Woodland Center C. F. - Boiler Replacement
Solicitation number
RFQ-171-250000000253-2
Issued by
Washtenaw County, Michigan

About this file

This is a Project Advertisement document from the Michigan Department of Technology, Management and Budget (DTMB) State Facilities Administration Design & Construction Division for the Woodland Center Correctional Facility (WCC) Boiler Replacement Project. The project is located at 9036 M-36, Whitmore Lake, MI 48189, with bids due on March 12, 2025, at 2:00 p.m. Eastern time. A mandatory pre-bid meeting and walk-through is scheduled for Thursday, March 6, 2025, at 9:00 am at the facility. The scope of work includes removing existing boilers, pumps, hydronic piping, and associated equipment, and installing new boilers, pumps, piping, controls, and hydronic equipment, with drawings and specifications dated February 21, 2025.

Bid responses must be uploaded to SIGMA VSS, with a maximum of two attachments under 6 MB. A 5% bid security is required, and questions will be accepted until March 7, 2025, at 2:00 pm. Contractors must submit a Vendor/Contractor LEIN Request five business days prior to the meeting for facility access. The project uses specific NIGP codes (90921, 90976, 91036, and others) and allows for potential Qualified Disabled Veteran (QDV) bidder considerations. Contact for project documents and questions is Devon Pung at Matrix Consulting Engineers, Inc., with bid documents available through the SIGMA michigan.gov website.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0415 (R 10/22)

PROJECT ADVERTISEMENT

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

DESIGN & CONSTRUCTION DIVISION

This form is required for the advertisement of all construction projects. (1984 PA 431)

DTMB FILE NO.

472/23130.SDW

DATE

February 21, 2025

ADVERTISEMENT DATE

February 21, 2025

BID DUE DATE

March 12, 2025 @ 2:00 p.m. EASTERN time

PROJECT NAME AND LOCATION (INCLUDE STREET ADDRESS)

Woodland Center Correctional Facility (WCC) – Boiler Replacement Project (9036 M-36, Whitmore Lake, MI 48189)

WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION

Mandatory pre-bid meeting, Thursday, March 6, 2025, at 9:00 am will be held at Woodland Center Correctional Facility, 9036 M-36, Whitmore Lake, MI 48189.

Mandatory pre-bid walk-through will take place immediately following the pre-bid meeting.

Mandatory Yes No

LEIN CHECK (Dept. of Corrections ONLY) All contractor/vendor representatives attending a Pre-Bid Walk Through Meeting must submit a Vendor/Contractor LEIN Request five business days prior to the meeting date, (See the attached Vendor/Contractor LEIN Request form). Send the LEIN Request form, filled out and signed, by email to Daniel T. Smith at email address: SmithD76@michigan.gov. The email “Subject” must include (Facility Name, Project Name, Date & Time of Pre-Bid Walk Through Meeting).

NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.

DESCRIPTION OF WORK:

Includes but is not limited to the removal of existing boilers, pumps, hydronic piping, and other associated equipment. Installation of new boilers, pumps, piping, controls, and associated hydronic equipment. Drawings and specifications dated February 21, 2025.

Please NOTE:

Bid responses and bid attachments MUST be uploaded to SIGMA VSS.

Contractors should only submit a maximum of two (2) attachments (both being less than 6 MB) for bid responses. One attachment is to be bid documents (Bid Summary, Bid Schedule, Bid Bond, Certification forms, Signature Authority, etc.) and if applicable, the other attachment should be Qualified Disabled Veteran (QDV) information (DD214, Proof of 51% Ownership and Proof of Service-Connected Disability)

Do not wait until just before the 2:00 p.m. solicitation deadline to submit your bid response.

SIGMA VSS will not allow a proposal to be submitted after 2:00 p.m., even if a portion of the bid response has been uploaded.

If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m., solicitation deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749. You may also email the SIGMA Help Desk at sigma-procurement-helpdesk@michigan.gov

Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).

You may be asked by our contract specialists to email your bid response. Emailed submissions will require DCD approval and will be handled on a case-by-case basis.

Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.

Bid Responses should not be emailed to the Project Director.

5% Bid Security:

Required

Not Required

NIGP CODES: 90921, 90976, 91036, 91038, 91060, 91200, 91240, 91244, 91356, 91389, 91430, 91438, 91450, 91468

ACCEPTING QUESTIONS UNTIL: March 7, 2025 at 2:00 pm local time. Please e-mail questions directly to Devon Pung at Matrix Consulting Engineers, Inc. - dpung@matrixceinc.com

Please do not submit online questions via SIGMA VSS.

Documents may be obtained from:

https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfServi ce

PSC/Agency: Devon Pung

Address:

Phone: 517-487-2511

Matrix Consulting Engineers, Inc.

1601 East Cesar E. Chavez Avenue Lansing, MI 48906

Email: dpung@matrixceinc.com

Approved by: Susan Wheaton RA