466535 Bidding Addendum 1.pdf

PDF 922 KB Posted

Attached to
Dept of Military, Correct Structural Deficiencies-Rapid City AASF B3
Solicitation number
26IFB19796
Issued by
Pennington County, South Dakota

About this file

This Addendum #1 document is issued by the South Dakota Department of the Military's Construction and Facilities Management Office for CFMO# 466535, the Correct Structural Deficiencies project at the Rapid City Army Aviation Support Facility (AASF) Building 3 in Rapid City. The addendum, issued April 17, 2026 by Stone Group Architects, modifies the original project manual and drawing sets with numerous architectural and mechanical/electrical changes. Key modifications include updates to door hardware scheduling, signage specifications and placement, interior room layouts affecting spaces such as Flight Ops 107, Facility Storage 106, Flight Planning 111, and the Waiting Area; ceiling type changes in the unisex restroom; countertop material designations; cabinetry replacements and repositioning in the reception desk and corridor areas; and comprehensive material and color schedule revisions affecting carpet, flooring, and paint finishes across 15 rooms. The mechanical/electrical addendum revises rooftop air handling unit specifications, with RTU-1 and RTU-2 both manufactured by AAON and serving locker and restroom areas; electrical modifications include updated circuit breaker requirements with 25,000 AIC ratings for connections to existing electrical panels. Bidders must acknowledge receipt of Addendum #1 in their bid submissions and incorporate all modifications into their bid pricing. The bid submission deadline remains May 7, 2026 at 12:00 PM MT through the State of South Dakota's electronic bidding platform.

The addendum provides detailed architectural drawing revisions across 15 sheets (A-000 through A-802 and M-701) and mechanical/electrical coordination schedules without establishing separate pricing terms or modifications to bid security, insurance, or bonding requirements outlined in the original solicitation. No specific cost adjustments or allowances resulting from the addendum changes are detailed in this document; bidders are responsible for incorporating all addendum provisions and modifications into their total bid price. The document includes contact information for the project architect at Stone Group Architects (Jordan Metzger and Garry Black) and references West Plains Engineering's mechanical/electrical addendum with specific keynote deletions and replacements on electrical sheets EP102 and EP103. No funding sources, set-asides, or incumbent contractor information is provided in the addendum.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE

MILITARY

STATE OF SOUTH DAKOTA

ADDENDUM #1

April 17, 2026

Project: CORRECT STRUCTURAL DEFICIENCIES – RAPID CITY AASF B3 Rapid City, South Dakota

CFMO# 466535

Letting: 12:00 P.M. MT, Thursday, May 7, 2026 Attn: Kyle Roe Online bid opening:

https://www.sd.gov/cs?id=sc_cat_item&sys_id=1657742c1b94c754ff55631ee54bcb3c

Owner: State of South Dakota Department of the Military Construction and Facilities Management Office

SCOPE OF THIS ADDENDUM:

The following becomes a part of the original Project Manual, taking precedence over items that may conflict. The bidder shall note receipt and make acknowledgment of the addendum in their bid and incorporating its provisions in their bid price.

ITEM NO. 1:

Attached is Addendum 1 by Stone Group Architects. SGA Contacts are Jordan Metzger jordan.metzger@stonegrouparchitects.com and Garry Black GarryB@stonegrouparch.com.

DEPARTMENT OF THE MILITARY

KYLE ROE

Project Manager

Aviation Support Facility SDARNG AASF // 221060 P A G E 1 / 4

ADDENDUM

PROJECT: ADDENDUM NO.: 1

Aviation Support Facility SDARNG AASF

Rapid City Regional Airport DATE ISSUED: 04.16.2026

BIDS DUE: 05.07.2026

ARCHITECT’S PROJECT NO: 221060

The following changes or modifications are to be incorporated into and become a part of the Contract Documents.

The Bidder shall note receipt and make acknowledgement of this Addendum on the Bid Proposal, incorporating these provisions in the bid.

GENERAL:

ITEM NO: 1: None

PRODUCT APPROVALS:

The following manufacturers and products have been approved for bidding. Final acceptance is contingent upon receipt and approval of final shop drawings/submittals. Manufacturers shall conform to all warranties, performances, sizes, materials, etc. as the item specified. The burden of proof of the merit of the proposed substitution is upon the proposer.

ITEM NO: 1: None

PROJECT MANUAL:

ITEM NO: 1: Hardware Schedule

a) Heading # 6.1 Door 146: Included note for maximum opening with the surface closer.

ITEM NO: 2: 10 14 00 Signage

b) Included spec for signage with addition of Sheet A-602 in the drawing set.

DRAWINGS:

ITEM NO: 1: Sheet G-000

a) Updated interior image of waiting room.

ITEM NO: 2: Sheet G-003

a) Updated International Building Code 2015 to 2021.

ITEM NO: 3: Sheet AD-001

a) Added additional dust wall at plan west side of lockers.

ITEM NO: 4: Sheet A-101

a) Removed bookshelf at plan east wall of FLIGHT OPS 107.

b) Expanded door clearance of FACILITY STORAGE 106

Aviation Support Facility SDARNG AASF // 221060 P A G E 2 / 4

319 N Main Avenue, Suite 2

Sioux Falls, SD 57104 phone (605) 271.1144 stonegrouparchitects.com

c) Infilled window from FLIGHT OPS 107 to FACILITY STORAGE 106 with CMU.

d) Extended bookshelves around perimeter of FACILITY STORAGE 106.

e) Removed table from FLIGHT PLANNING 111.

f) Designated countertop material at WAITING AREA 149.

ITEM NO: 5: Sheet A-112

a) Updated ceiling type in UNISEX 125 from “Type 2” to “Type 3”

b) Removed air ducts interfering with ceiling lights.

ITEM NO: 6: Sheet A-450A

a) Keynote Schedule: Added Keynote 10.01B

b) C3: Added Keynote 10.01B and designation.

c) C4: Added Keynote 10.01B and designation.

d) B3: Designated wall paint and wall base.

e) Updated detail “D5” to “B5”

ITEM NO: 7: Sheet A-450C

a) D1 and D2: Updated “PLAM-2” countertop to “SS-1” and created D3 and D4 section details.

b) Keynote Schedule: added keynote 4.11.

c) B1 and A1: Designated CMU wall with keynote 4.11.

d) B3: Updated cabinetry under microwaves.

e) Moved details D3 and D4 to sheet A-454.

ITEM NO: 8: Sheet A-451A

a) Keynote Schedule: Added keynote 10.01B.

b) D1 and D2: Designated keynote 10.01B.

c) A3: Updated changing table height to 48” for handle not to exceed 48”.

ITEM NO: 9: Sheet A-452

a) A1: Extended bookshelf to cover CMU filled window.

b) A1, A2, and A3: Removed material note. All bookshelf, counter, and cabinetry is PLAM-1

c) B2: Included keynote 6.41D

d) Keynote Schedule: Add keynotes 6.41D

ITEM NO: 10: Sheet A-453 (reissue full sheet)

a) Lowered transaction counter from 24” to 12” (Total height of reception desk is now 42”)

b) Replaced open shelving with box-box lateral filing and box-box-file cabinetry.

c) Removed detail C5.

d) Updated details C3 and C4 to reflect updated cabinetry.

e) Removed wall base at front of reception desk.

f) Keynote Schedule: Added keynotes 6.40M and 6.40N for cabinetry fillers.

Aviation Support Facility SDARNG AASF // 221060 P A G E 3 / 4

Sioux Falls, SD 57104 phone (605) 271.1144 stonegrouparchitects.com

g) A1: Designated locations of keynotes 6.40M and 6.40N for cabinetry fillers.

ITEM NO: 11: Sheet A-454

a) A1: Added room name; Designated wall type at new south wall as type A.

b) Removed wall base from reception desk.

c) Removed large printer.

d) Updated height of transaction counter from 18” to 12” (full height is 42”).

e) Included details D1, D2, D3, D4, and C1 to the sheet for the shelving area at CORRIDOR 158.

ITEM NO: 12: Sheet A-601

a) Door Schedule: Updated doors 112, 113, 115, 119 to have all existing frames remain, verified and painted HP-1.

b) Door Schedule: Update Door 161 from 5’-10” to 6’-0”.

c) General door and window notes: Updated 2015 IBC to 2021 IBC.

ITEM NO: 13: Sheet A-602

a) Added whole sheet for signage plan.

ITEM NO: 14: Sheet A-801

COLOR & MATERIAL SCHEDULE

a) Updated the following materials:

• CPT-1: From “FRIXTON-CHARGE” to “OBEX TILE CUTE/GRAIN”

• CPT-2: From 12X36 “NATURAL ELEMENTS TOO-AIR TOO” to 18X36 “RAW EDGE”

• CPT-3: From 12X36 “NATURAL ELEMENTS TOO-FIRE TOO” to 18X36 “THREADED”

• SS-1: From “AURORA BIANCO” to “EXCAVAGE”

• SS-2: From “BLACK LAVA” to “LAVA ROCK”

• P-2: From “KNITTING NEEDLES” to “AGREEABLE GREY”

• WC-1: Updated image and designated texture as “SILK”

B) Removed

• PLAM-2

• PT-5 “RESIDE”

• TB-2 “RESIDE”

c) Added

• P-3 “WATERLOO”

ROOM FINISH SCHEDULE

a) Updated the following rooms:

• 100: Floor from PT-5 to CPT-1

• 107: Added LVT-1 to flooring

• 112: Floor from CPT-3 to CPT-2

• 113: Floor from CPT-3 to CPT-2

• 115: Floor from CPT-2 to CPT-3; North wall from P-1 to P-3

• 117: Floor from PT-5 to CPT-1

• 122A: Floor from CPT-2 to CPT-3; West wall from P-1 to P-3

• 122B: Floor from CPT-2 to CPT-3; West wall from P-1 to P-3

• 128: Floor from PT-5 to CPT-1

• 129: South wall from P-1 to P-3

Aviation Support Facility SDARNG AASF // 221060 P A G E 4 / 4

Sioux Falls, SD 57104 phone (605) 271.1144 stonegrouparchitects.com

• 138: Removed CPT-3 flooring, so flooring is only LVT-1; West wall from P-1 to P-3

• 138A: Floor to be LVT-1

• 141: East wall from PT-4 to PT-3

• 142: East wall from PT-4 to PT-3

• 144: East wall from PT-4 to PT-3

• 145: West wall from PT-4 to PT-3

• 146: Floor from CPT-2 to CPT-3; South wall from P-2 to P-3

• 147: Floor from CPT-3 to CPT-2

• 148: Floor from CPT-3 to CPT-2

• 149: Floor from CPT-2 to CPT-3

• 152: Floor from CPT-3 to CPT-2

• 154: Floor from CPT-2 to LVT-1; West wall from P-1 to P-3

• 155: Floor from CPT-2 to LVT-1; West wall from P-1 to P-3

• 161: Floor from PT-5 to CPT-1

• 162: Floor from CPT-3 to CPT-2

ITEM NO: 15: Sheet A-802

a) Updated all vestibules from TL-5 to CPT-1

b) Updated FLOOR FINISH LEGEND to signify material changes on sheet A-801.

c) Removed carpet in Classroom 138.

d) Updated all carpet hatches to designated carpet material changes.

e) Added KEYNOTES schedule and keynote 9.63A.

ATTACHMENTS:

• MEP Addendum to the Drawings.

END OF ADDENDUM

Addendum

Date: April 15, 2026 Project: Aviation Support Facility

SDARNG AASF

To: Stone Group Architects Project #: WPE# BR26010 600 E. 7th Street Sioux Falls, SD 57103

From: West Plains Engineering Project Location: Rapid City Regional Airport 1750 Rand Rd.

Rapid City, SD 57702 Addendum Number: 1

To: All prime contract bidders and all others to whom Drawings and Specifications have been issued by the

Engineer. Acknowledge receipt of the Addendum by inserting its number and date on the Bid Form. Failure to do so may subject bidder to disqualification. This Addendum forms a part of the Contract Documents. It modifies them as follows:

Drawings

Sheet M-701

1. ROOFTOP AIR HANDLING UNIT SCHEDULE – Replace schedule in its entirety. (See attached)

2. MECHANICAL/ELECTRICAL COORDINATION SCHEDULE – Replace schedule in its entirety. (See attached)

Sheet EP102

1. Delete Keynote 1 and replace with the following: 1. PROVIDE 60/3 BREAKER FOR EXISTING SQUARE ‘D’ I- LINE PANEL ‘P1’. BREAKER AIC RATING SHALL BE 25,000. CONNECT ROOF TOP UNIT TO NEW BREAKER

WITH 3-#4, 1-#8 GRD, 1 1/2 INCH CONDUIT.

Sheet EP103

1. Delete Keynote 3 and replace with the following: 3. PROVIDE 60/3 BREAKER FOR EXISTING SQUARE ‘D’ SWITCHBOARD ‘MDP’ IN ROOM 116. BREAKER AIC RATING SHALL BE 25,000. CONNECT ROOF TOP UNIT

TO NEW BREAKER WITH 3-#4, 1-#8 GRD, 1 1/2 INCH CONDUIT.

END OF DOCUMENT – DFR/MRS

Attachments: ROOFTOP AIR HANDLING UNIT SCHEDULE

MECHANICAL/ELECTRICAL COORDINATION SCHEDULE

MECHANICAL / ELECTRICAL COORDINATION SCHEDULE

ABBREVIATION:

E ELECTRICAL CONTRACTOR HP HORSEPOWER 4X NEMA 4X V VOLTAGE

M MECHANICAL CONTRACTOR KW KILOWATTS PH PHASE VFD VARIABLE FREQUENCY

I INTEGRAL WITH EQUIPMENT MR PER MANUFACTURER'S RE REVERSING DRIVE

C COMBINATION STARTER AND RECOMMENDATION RV REDUCED VOLTAGE 2S TWO SPEED

SAFETY SWITCH NF NON-FUSED SF FUSE HOLDER WITH SWITCH 3S THREE SPEED

CB CIRCUIT BREAKER NR NON-REVERSING SS SAFETY SWITCH

FV FULL VOLTAGE N1 NEMA 1 SH HP RATED SWITCH

FLA FULL LOAD AMPS 3R NEMA 3R ST THERMAL ELEM. SWITCH

REFER TO SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS

MARK DESCRIPTION

RATING

DISCONNECT MOTOR STARTER NAMEPLATE

REMARKSFURNISH/

INSTALL

BY

TYPE

RATING

(AMPS)

FUSE

SIZE

ENCL.

FURNISH/

INSTALL

BY

TYPE/

NEMA

SIZE

ENCL.

MINIMUM

SCCR

(AMPS)LOAD V PH

GWH-1 GAS WATER HEATER

0.74

WATTS

120 1 E/E - - - - M/M - - - 1

GWH-2 GAS WATER HEATER

0.74

WATTS

120 1 E/E - - - - M/M - - - 1

PP-1 RECIRCULATION PUMP

1/20

HP

120 1 E/E SH 20 MR N1 M/M - - -

PP-2 RECIRCULATION PUMP

1/20

HP

120 1 E/E SH 20 MR N1 M/M - - -

EF-1 EXHAUST FAN

1/10

HP

120 1 M/I - - - - M/I - - - -

RTU-1 ROOF TOP UNIT 58 FLA 208 3 M/I - - - - M/I - - 10000 -

RTU-2 ROOF TOP UNIT 58 FLA 208 3 M/I - - - - M/I - - 10000 -

GENERAL NOTES:

A. VERIFY/COORDINATE ALL RATINGS FOR EQUIPMENT. WHERE SUCH RATINGS ARE OTHER THAN THAT INDICATED ON MECHANICAL/ELECTRICAL COORDINATION SCHEDULE, PROVIDE DISCONNECTS, MOTOR STARTERS, OVERCURRENT DEVICES AND RELATED REVISIONS ACCORDINGLY. WHERE EQUIPMENT IS PROVIDED WITH RATINGS OTHER THAN THAT INDICATED, CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION AND ASSOCIATED COSTS FOR REVISIONS.

B. PROVIDE FRACTIONAL HORSEPOWER MOTORS WITH INTEGRAL OVERLOAD PROTECTION.

C. EQUIPMENT LISTED IN SCHEDULE MAY APPEAR IN NUMEROUS LOCATIONS. IN THESE INSTANCES, THE ELECTRICAL REQUIREMENTS DO NOT CHANGE FROM ONE TO

THE NEXT.

D. HORSEPOWER RATED SWITCHES (SH): FOR 120 V MOTORS LESS THAN 1/2 HP, PROVIDE FUSEHOLDER WITH SWITCH, FUSED PER MANUFACTURER'S RECOMMENDATION AND NEC REQUIREMENTS. FOR 120 V MOTORS RATED 1/2 HP OR 3/4 HP, PROVIDE HP RATED TOGGLE SWITCH (WHERE BRANCH CIRCUIT OVERCURRENT DEVICE MEETS NEC REQUIREMENTS FOR SHORT-CIRCUIT PROTECTION) OR FUSED SAFETY SWITCH.

E. INDUSTRIAL CONTROL PANELS AS DEFINED BY NEC ARTICLE 409, MOTOR CONTROLLERS, HERMETIC REFRIGERANT MOTOR COMPRESSORS AND EQUIPMENT SHALL BE MARKED WITH INFORMATION AS REQUIRED BY THE NATIONAL ELECTRICAL CODE (NEC). MARK IN ACCORDANCE WITH NEC ARTICLE 409.110 FOR INDUSTRIAL CONTROL PANELS, NEC ARTICLE 430.8 FOR CONTROLLERS AND NEC ARTICLE 440.4(B) FOR HERMETIC REFRIGERANT MOTOR COMPRESSORS AND EQUIPMENT. THE MARKED SHORT CIRCUIT CURRENT RATING (SCCR) SHALL BE NO LESS THAN THE VALUE INDICATED ABOVE.

F. FOR MOTORS CONTROLLED BY VARIABLE FREQUENCY DRIVES, PROVIDE FACTORY INSTALLED SHAFT GROUNDING THAT REQUIRES NO MAINTENANCE FOR THE

SERVICE LIFE OF THE MOTOR.

REMARKS:

1. DUPLEX RECEPTACLE SHALL SERVE AS DISCONNECTING MEANS VIA CORD AND PLUG FURNISHED WITH THE GWH.

DUCTWORK INSULATION SCHEDULE

DUCTWORK SYSTEM

ACOUSTICAL FLEXIBLE RIGID THICKNESS

REMARKS

LINER FIBERGLASS FIBERGLASS (INCHES)

CONCEALED LOW VELOCITY ROUND SUPPLY AIR AND RETURN

AIR DUCTWORK

- X - 2.2" 1

RECTANGULAR SUPPLY AIR DUCTWORK X - - 1-1/2" 1

RETURN AIR DUCTWORK X - - 1" 1

EXHAUST AIR DUCTWORK - X - 2.2" 1, 2

REMARKS:

1. SEE SPECIFICATION SECTION "METAL DUCTS" FOR ACOUSTICAL LINER & SEE SPECIFICATION SECTION "HVAC INSULATION" FOR OTHER DUCT INSULATION SPECIFICATIONS.

2. FROM ROOF TO 15-FEET INSIDE THE BUILDING.

FAN SCHEDULE

MARK LOCATION TYPE

AIRFLOW

(CFM)

ESP

(IN WG)

FAN SPEED

(RPM)

DRIVE TYPE MAX SOUND (dBA)

WEIGHT

(LBS)

MANUFACTURER &

MODEL NO.

REMARKS

EF-1 ROOF

ROOF MOUNTED

CENTRIFUGAL

125 0.3" 1694 DIRECT 4.4 24

GREENHECK

G-060-VG

1, 2, 3

REMARKS:

1. SEE MECHANICAL/ELECTRICAL COORDINATION SCHEDULE FOR ELECTRICAL DATA.

2. PROVIDE 24" ROOF CURB, BACKDRAFT DAMPER AND BIRDSCREEN.

3. PROVIDE FACTORY MOUNTED ELECTRICAL DISCONNECT.

REGISTER - GRILLE - DIFFUSER SCHEDULE

MARK FUNCTION TYPE

CFM MAX SIZE BORDER OR MATERIAL

FINISH ACCESS.

MANUFACTURER

REMARKS

RANGE N.C. (INCHES) FRAME ALUM. STEEL & MODEL NO.

A SUPPLY

SQUARE FACE

NOMINAL PNL.

0 -

25 6" Ø NECK

24 x 24

LAY-IN

X

STND.

WHITE

TITUS

OMNI-AA

1, 2, 3

B SUPPLY

SQUARE FACE

NOMINAL PNL.

101 -

25 8" Ø NECK

24 x 24

LAY-IN

X

STND.

WHITE

TITUS

OMNI-AA

1, 2, 3

C SUPPLY

SQUARE FACE

NOMINAL PNL.

251 -

10" Ø

NECK

24 x 24

LAY-IN

X

STND.

WHITE

TITUS

OMNI-AA

1, 2, 3

D SUPPLY

DOUBLE

DEFLECTION

0 -

25 6 x 6

SURFACE

MOUNT

X

STND.

WHITE

TITUS

272FL

1, 2, 3

E RETURN/EXHAUST

SQUARE FACE

NOMINAL PNL.

0 -

10 x 22

NECK

12 x 24

LAY-IN

X

STND.

WHITE

TITUS

PAR-AA

1, 2, 3

F RETURN/EXHAUST

SQUARE FACE

NOMINAL PNL.

0 -

22 x 22

NECK

24 x 24

LAY-IN

X

STND.

WHITE

TITUS

PAR-AA

1, 2, 3

G RETURN/EXHAUST

FIXED DEFL.

45° BLADE

0 - 230 25 12 x 8

SURFACE

MOUNT

X

STND.

WHITE

TITUS

3FL

1, 2, 3

REMARKS:

1. PROVIDE SPECIFIC NOISE CRITERIA (NC) DATA FOR EACH LINE ITEM WITH SHOP DRAWINGS.

2. COORDINATE BORDER OR FRAME TYPE WITH CEILING TYPE. SEE ARCHITECTURAL CEILING PLANS.

3. COORDINATE FINISH/COLOR WITH ARCHITECT. REFER TO PLANS FOR REGISTERS, GRILLE, DIFFUSERS THAT ARE DESIGNATED A CERTAIN COLOR.

ROOFTOP AIR HANDLING UNIT SCHEDULE

MARK LOCATION APPLICATION / SERVES

SUPPLY AIR

(CFM)

HEATING SECTION (GAS OR ELECTRIC) COOLING SECTION SUPPLY FAN EXHAUST FAN ENERGY RECOVERY WHEEL

MAXIMUM

WEIGHT

(LBS)

MANUFACTURER &

MODEL NO.

REMARKSEAT DB

(°F)

MAX LAT

(°F)

GAS HEAT

EAT

DB/WB

(°F)

LAT

DB/WB (°F)

TOTAL

CAP

(MBH)

SENS

CAP

(MBH)

EER IEER

NO.

FANS

ESP

(IN WG)

POWER

(HP)

NO. FANS

AIRFLOW

(CFM)

ESP

(IN WG)

POWER

(HP)

SUMMER SUPPLY AIR SUMMER EXHAUST AIR SUMMER EFFECTIVENESS WINTER SUPPLY AIR WINTER EXHAUST AIR WINTER EFFECTIVENESS

INPUT

(MBH)

OUTPUT

(MBH)

DB WB DB WB LATENT % SENSIBLE % TOTAL % DB WB DB WB LATENT % SENSIBLE % TOTAL %

RTU-1 ROOF LOCKER/RESTROOMS 1850 -20.0 97.2 186.8 149.5 80.8/62.7 52.9/50.8 55.1 46.4 12.9 14.8 1 1.50 2.00 1 1850 0.75 2.00 95.0 65.0 89.1 64.4 66.2 70.6 75.4 9.9 5.8 27.4 22.2 66.2 70.5 69.4 1594

AAON

RN-006

1 THRU 15

RTU-2 ROOF LOCKER/RESTROOMS 2050 -20.0 89.0 186.8 149.5 80.6/62.6 50.9/49.1 53.9 43.7 12.9 14.8 1 1.50 2.00 1 2050 0.75 2.00 95.0 65.0 90.2 64.6 68.4 73.0 78.7 14.0 8.9 29.0 22.9 68.4 72.9 71.7 1601

AAON

RN-006

1 THRU 15

REMARKS:

1. SEE MECHANICAL/ELECTRICAL COORDINATION SCHEDULE FOR ELECTRICAL DATA.

2. CAPACITY BASED ON 95°F SUMMER OUTDOOR AIR TEMPERATURE AND -20°F WINTER OUTDOOR AIR TEMPERATURE.

3. PROVIDE UNIT WITH INTAKE AND EXHAUST HOODS.

4. PROVIDE UNIT WITH STAINLESS STEEL OR PLASTIC DRAIN PAN AND CONDENSATE OVERFLOW SWITCH.

5. PROVIDE HINGED ACCESS PANELS WITH OPERATING HANDLES.

6. PROVIDE SINGLE POINT POWER CONNECTION.

7. PROVIDE 24-INCH INSULATED PLENUM ROOF CURB.

8. PROVIDE WITH ULTRA-LOW LEAKAGE ECONOMIZER.

9. PROVIDE 2-INCH THICK MERV 8 FILTERS.

10. PROVIDE WITH STAINLESS STEEL HEAT EXCHANGER.

11. PROVIDE UNIT MOUNTED GFCI RECEPTACLE.

12. PROVIDE WITH HAILGUARDS.

13. REFRIGERANT SHALL BE R-410A.

14. COORDINATE WITH CONTROLS CONTRACTOR FOR CONNECTION TO BUILDING MANAGEMENT SYSTEM.

15. PROVIDE WITH DEHUMIDIFICATION HOT GAS REHEAT COIL.

CONSTRUCTION

NOT FOR

PROGRESS PRINT

DATE:BY:

OMAHA | LINCOLN | COLORADO SPRINGS | SIDNEY

FARRIS ENGINEERING

farris-usa.com

FE#:232012

SHEET TITLE:

CHECKED BY:

PROJECT NO.:

ISSUE DATE:

DESIGNED BY:

DRAWN BY:

SHEET NUMBER:

A

B

D

1 2 3 4

C

F ul l s iz e x3

6;

H al f s iz e x1

A

B

D

C

1 2 3 4 5

600 E. 7th Street Sioux Falls, SD 57103 phone: 605.271.1144 stonegrouparchitects.com

© Copyright 2020

MDW 03/29/2024

04/26/2024

4/

/2

2:

:1

P

M

M-701

221060

04.26.2024

JDB

JRR

GTK

A V

IA

T

IO

N

S U

P P

O R

T F

A C

IL

IT

Y

S D

A R

N G

A A

S F

R A

P

ID

C

IT

Y R

E G

IO

N

A L

A

IR

P O

R T

MECHANICAL SCHEDULES

Permit / Bid Set

NO. REVISION DATE

1 PERMIT/BID SET 04-26-2024

43 FLA

43 FLA