42210054_FTIG WWTP SBR 2 and Digester 2 Rehab_Drawings_Rev.pdf
PDF 2 MB Posted
- Attached to
- WWTP SBR 2 and Digester 2 Rehabilitation
- Solicitation number
- 6100061392
- Issued by
- Lebanon County, Allentown City, Pennsylvania
About this file
This document contains drawings and specifications for the rehabilitation of the Sequencing Batch Reactor (SBR) 2 and Digester 2 at the Fort Indiantown Gap Wastewater Treatment Plant, a project managed by the Commonwealth of Pennsylvania Department of Military and Veterans Affairs. The work includes removing and replacing various equipment and components within the SBR and digester tanks, as well as applying a protective coating system to the interior walls and floors. The project has an estimated construction cost range of $2,000,001 to $3,000,000, with liquidated damages of $750 per day for delays. A mandatory pre-bid conference is scheduled for June 20, 2024, and bids are due on July 11, 2024. This project is subject to Small Diverse Business (SDB) and Veteran Business Enterprise (VBE) participation goals, which will be determined and included in the bid documents.
The contract will be awarded through a standard low-bid process. Bidders must submit their bids electronically through the PA Supplier Portal website. Questions regarding the project are due by July 1, 2024. The Department of General Services Public Works and the Bureau of Diversity, Inclusion and Small Business Opportunities will be setting the SDB and VBE participation goals for this project, which bidders must meet or demonstrate good faith efforts to achieve.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum #2.docx | DOCX document | |
| Notice to Bidders.docx | DOCX document | |
| General Conditions to the Construction Contract DMVA 2023 v5.docx | DOCX document | |
| Pre-bid sign in sheet.pdf | ||
| BDISBO participation review.docx | DOCX document | |
| Bid Form_GC_REV1_ADD3.pdf | ||
| Wage Rates.pdf | ||
| RFP 6100061392 WWTP SBR 2 and Digester 2 Rehabilitation BDISBO SDB VBE presentation.pdf | ||
| Construction_RFP_IFB_SDB_Participation_Form_2024.01.26 (1).pdf | ||
| Construction_RFP_IFB_VBE_Participation_Form_2024.01.26 (1).pdf | ||
| 42210054 FTIG WWTP SBR 2 and Digester 2 Rehabilitation_ADDENDUM NO 3.pdf | ||
| Addendum #3.docx | DOCX document | |
| 42210054_FTIG WWTP SBR 2 and Digester 2 Rehab_Specifications_Rev.pdf | ||
| Administrative Procedures 2023 DMVA.docx | DOCX document | |
| Instructions to Bidders 2023 DMVA.doc | DOC document | |
| FTIG WWTP Location Map.pdf | ||
| Bid docs to be returned.pdf | ||
| Addendum #1.docx | DOCX document | |
| FTIG Map 2017.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PA-5C
PA-5A
PA-5C
PA-5A
SITE
WWTP
APPROXIMATELY 33 MILES TO HARRISBURG
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
Project No. 42210054
MAY 28, 2024
G.1.0 - COVER SHEET
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
Project No. 42210054
G.1.1 - ABBREVIATIONS
PROJECT AREA
GENERAL NOTES:
1. SEE SPECIFICATIONS SECTION 010100 - SUMMARY OF
WORK.
2. EXISTING FEATURES AS ORIGINALLY DESIGNED ARE SHOWN
IN BLACK LINEWORK AND TEXT - BASED ON DESIGN DRAWINGS
DATED SEPTEMBER 30, 2002, RELEASED FOR BID JULY 9, 2004
PREPARED BY SAIC ENGINEERING, INC.
3. PROPOSED WORK IS INDICATED WITH RED TEXT, LINES,
ARROWS, AND/OR CLOUDS.
4. VERIFIY ALL DIMENSIONS, EXISTING CONDITIONS, AND
FEATURES ON SITE. REPORT ANY DISCREPANCIES TO DMVA.
DO NOT SCALE DRAWINGS TO OBTAIN DIMENSIONS OR
DISTANCES.
TANK DEWATERING NOTES:
1. OWNER WILL DRAIN AND TRANSFER BULK LIQUID FROM
TANKS USING EXISTING FACILITIES.
2. CONTRACTOR SHALL PROVIDE ADDITIONAL PUMPS AND
RELATED EQUIPMENT TO COMPLETELY DEWATER AND REMOVE
LIQUIDS FROM TANKS. CONTRACTOR SHALL MAINTAIN
EQUIPMENT AS NEEDED DURING CONSTRUCTION TO DEWATER
TANKS.
3. LIQUID REMOVED SHALL BE TRANSFERRED TO ADJACENT
TANKS TO REMAIN IN OPERATION.
4. INORGANIC SOLIDS (GRIT, RAGS, ETC.) SHALL NOT BE
TRANSFERRED TO ADJACENT TANKS AND SHALL BE REMOVED
AND DISPOSED OF PROPERLY.
DEMOLITION NOTES:
1. REMOVE ALL EQUIPMENT AND COMPONENTS DESIGNATED
TO BE REPLACED. KEEP AND STORE MOTORS, PUMPS,
INSTRUMENTS, VALVES, VALVES, ACTUATORS, MIXER
ASSEMBLIES, DECANT ASSEMBLIES, AND RELATED ITEMS AS
DIRECTED BY DMVA. LEGALLY DISPOSE OF ALL OTHER
MATERIALS AND EQUIPMENT REMOVED DURING THE PROJECT
OFF SITE IN AN APPROVED MANNER.
2. CUT EXISTING ANCHORS AND FASTENERS IN CONCRETE
WALLS. REPAIR IN ACCORDANCE WITH THE PROPOSED COATING
MANUFACTURER'S RECOMMENDATIONS.
3. CONTRACTOR IS RESPONSIBLE FOR MEANS AND METHODS
AND PROVISION OF ALL LABOR, EQUIPMENT AND RESOURCES
REQUIRED TO EMPTY, CLEAN AND PREPARE SBR AND DIGESTER
TANKS FOR THE WORK IN ACCORDANCE WITH THE COATING
MANUFACTURER'S RECOMMENDATIONS AND REQUIREMENTS.
THIS INCLUDES REMOVAL OF ANY AND ALL ACCUMULATED
SEDIMENT AND GRIT IN SBR AND DIGESTER TANKS USING
MECHANICAL OR MANUAL METHODS. ALL WASTE REMOVED
FROM THE TANKS SHALL BE HAULED OFF SITE AND DISPOSED OF
AT AN APPROVED LANDFILL OR TREATMENT FACILITY.
TRANSPORT METHODS SHALL MEET REQUIREMENTS FOR THE
WASTE MATERIAL BEING HAULED. CONTRACTOR SHALL APPLY
FOR AND OBTAIN ALL REQUIRED APPROVALS/PERMITS FOR
HAULING AND DISPOSAL OF WASTE.
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
Project No. 42210054
MAY 28, 2024
C.1.0 - EXISTING
SITE PLAN
CONSTRUCTION NOTES (SHEET C.2.1):
1. REMOVE EXISTING INFLUENT BAFFLE. PROVIDE NEW SS INFLUENT BAFFLE.
2. REMOVE EXISTING INFLUENT PLUG VALVE AND ELECTRIC ACTUATOR.
PROVIDE NEW INFLUENT PLUG VALVE AND ELECTRIC ACTUATOR.
3. REMOVE EXISTING FLOATING DECANTER ASSEMBLY, RESTRAINED MOORING
SYSTEM, DISCHARGE PIPE AND FLEX JOINTS. PROVIDE NEW FLOATING
DECANTER ASSEMBLY, RESTRAINED MOORING SYSTEM, DISCHARGE PIPE AND
FLEX JOINTS, EQUIPMENT AND ACCESSORIES.
4. REMOVE EXISTING DECANT FLOW CONTROL VALVE. PROVIDE NEW DECANT
FLOW CONTROL VALVE.
5. REMOVE EXISTING SUPERNATENT WITHDRAWAL MECHANISM. PROVIDE
NEW SUPERNATENT WITHDRAWAL MECHANISM INCLUDING PIPE, SWIVEL
JOINT, PLUG VALVE, BLIND FLANGE, EQUIPMENT AND ACCESSORIES.
6. REPLACE DUCTILE IRON INFLUENT PIPE FROM WALL TO BAFFLE. MATCH
EXISTING MATERIAL - PROVIDE CLASS 52 FLANGED DUCTILE IRON PIPE
MINIMUM. PAINT PIPE TO MATCH ORIGINAL EXISTING COATING.
SEE NOTE 1
SEE NOTE 1
SEE NOTE 2
436.0
SEE NOTE 3
SEE NOTE 4
SEE NOTE 5
SEE NOTE 5
SEE NOTE 6
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
Project No. 42210054
MAY 28, 2024
C.2.1 - SBR AND
DIGESTER PLAN
SEE NOTE 2 ON
SHEET C.2.1
SEE NOTE 4 ON
SHEET C.2.1
SEE NOTE 4 ON
SHEET C.2.1
C.2.2 - SBR AND
DIGESTER SECTIONS
COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF
MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
Project No. 42210054
CONSTRUCTION NOTES
(SHEET C.2.3):
1. THIS SHEET PROVIDED FOR
INFORMATION ONLY. FIELD VERIFY
EXISTING EQUIPMENT INSTALLATION
DETAILS AND COORDINATE
PROPOSED EQUIPMENT
DIMENSIONS, LAYOUT, AND
FABRICATION.
2. SEE NOTE 3 AND 4 SHEET C.3.1.
C.2.3 - SBR AND
DIGESTER DETAILS
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
CONSTRUCTION NOTES (SHEET C.3.1):
1. REMOVE EXISTING SBR MIXER, CABLE MOORING SYSTEM,
ELECTRICAL CABLE, AND RELATED EQUIPMENT. PROVIDE NEW SBR
MIXER, CABLE MOORING SYSTEM, ELECTRICAL CABLE AND RELATED
EQUIPMENT AND ACCESSORIES .
2. REMOVE EXISTING DIGESTER MIXER, POST MOORING SYSTEM,
ELECTRICAL CABLE, AND RELATED EQUIPMENT. PROVIDE NEW
DIGESTER MIXER, POST MOORING SYSTEM, ELECTRICAL CABLE AND
RELATED EQUIPMENT AND ACCESSORIES.
3. REMOVE EXISTING SBR AERATION SYSTEM. PROVIDE NEW
RETRIEVABLE FINE BUBBLE AIR DIFFUSER ASSEMBLIES, FRAME
ASSEMBLY, AIR COLUMN, TRACK/BEAM, FLEXIBLE AIR LINE,
ISOLATION VALVE, LIFT MECHANISM, AND RELATED EQUIPMENT
AND ACCESSORIES.
4. REMOVE EXISTING DIGESTER AERATION SYSTEM. PROVIDE NEW
RETRIEVABLE COARSE BUBBLE DIFFUSER ASSEMBLIES, TRACK/
BEAM, FLEXIBLE AIR LINE, ISOLATION VALVE, LIFTING MECHANISM,
AND RELATED EQUIPMENT AND ACCESSORIES.
5. REMOVE EXISTING SBR SLUDGE TRANSFER PUMP. PROVIDE NEW
SLUDE WASTING PUMP, CABLE, DISCHARGE ELBOW, DISCHARGE
PIPING, LIFTING CHAIN, GUIDE BARS, SUPPORTS, AND RELATED
HARDWARE, ANCHORS, EQUIPMENT AND ACCESSORIES.
6. REMOVE EXISTING DIGESTER SLUDGE TRANSFER PUMP.
PROVIDE NEW SLUDGE WASTING PUMP, CABLE, DISCHARGE
ELBOW, DISCHARGE PIPING, LIFTING CHAIN, GUIDE BARS,
SUPPORTS, AND RELATED HARDWARE, ANCHORS, EQUIPMENT AND
ACCESSORIES.
7. EXISTING STEEL PIPE SUPPORTS INSTALLED BY DMVA TO
PROVIDE ADDITIONAL SUPPORT FOR DIGESTER MIXER POST (EACH
TANK). REMOVE / RELOCATE AS NEEDED DURING CONSTRUCTION
AND REPLACE / RESTORE IN ORIGINAL LOCATION WHEN WORK IS
COMPLETE.
8. PROVIDE PROTECTIVE COATING SYSTEM ON INTERIOR WALLS
AND FLOOR OF SBR 2 AND DIGESTER 2 TANKS. COATING SYSTEM
ON WALLS SHALL EXTEND FROM FLOOR TO THE BOTTOM OF THE
WALKWAY. SEE SPECIFICATION SECTION 09 96 00.
A. EXISTING CONCRETE TANKS ARE PRE-CAST POST TENSIONED
CONCRETE TANKS MANUFACTURED AND INSTALLED BY
DUTCHLAND, LLC, GAP, PA. POINT OF CONTACT IS JOSH ALLEN, P.E.,
717.442.1463.
B. DURING TANK PREP, REMOVE EXISTING FLEXIBLE SEALANT IN
VERTICAL JOINTS BETWEEN PRE-CAST WALL PANELS. FILL WITH A
CEMENTITIOUS MORTAR MATERIAL SUITABLE FOR SUBMERGED
WASTEWATER TREATMENT APPLICATIONS AND COMPATIBLE WITH
SPECIFIED COATING SYSTEM. APPLY COATING SYSTEM ACROSS
FILLED VERTICAL JOINTS.
C. REPLACE FLEXIBLE SEALANT AT WALL CORNERS AND WALL TO
FLOOR JOINTS WITH MATERIAL RECOMMENED BY DUTCHLAND, LLC
AND COMPATIBLE WITH SPECIFIED COATING SYSTEM.
SEE NOTE 1
SEE NOTE 2
SEE NOTE 3
SEE NOTE 3
SEE NOTE 4
SEE NOTE 5
SEE NOTE 6
SEE NOTE 7
C.3.1 - SLUDGE AND
AERATION PIPING PLAN
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
MOTOR
CONSTRUCTION NOTES (SHEET C.3.2):
1. THIS SHEET PROVIDED FOR INFORMATION ONLY. FIELD VERIFY EXISTING EQUIPMENT INSTALLATION
DETAILS AND COORDINATE PROPOSED EQUIPMENT DIMENSIONS, LAYOUT, AND FABRICATION.
2. SEE NOTE 1 AND 2 SHEET C3.1.
C.3.2 - SBR AND
DIGESTER EQUIPMENT
DETAILS
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
CONSTRUCTION NOTES (SHEET C.3.3):
1. THIS SHEET PROVIDED FOR INFORMATION ONLY. FIELD VERIFY EXISTING
EQUIPMENT INSTALLATION DETAILS AND COORDINATE PROPOSED
EQUIPMENT DIMENSIONS, LAYOUT, AND FABRICATION.
2. SEE NOTE 3 SHEET C.2.1.
3. SEE NOTE 5 AND 6 SHEET C.3.1.
C.3.3 - SBR AND
DIGESTER EQUIPMENT
DETAILS
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
C.4.1 - FILTER / UV
BUILDING PLAN
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF MILITARY AND VETERANS AFFAIRS
FORT INDIANTOWN GAP WASTEWATER TREATMENT PLANT -
SBR 2 AND DIGESTER 2 REHABILITATION
Project No. 42210054
MAY 28, 2024
CONSTRUCTION NOTES SHEET C.4.1:
1. UPGRADE CONTROLS IN DISK FILTER CONTROL
PANEL. SEE SPECIFICATION SECTION 46 53 53.
2. COORDINATE CONTROL PANEL UPGRADES AND
OPERATION OF FILTERS WITH PLANT OPERATION
STAFF.