This is Addendum No. 3 to the bid documents for a roofing and window wind mitigation project at Delgado Community College's Westbank Campus in New Orleans, Louisiana, issued on September 10, 2026. The addendum provides critical clarifications to the original specifications for membrane roofing and window replacement in Building 1 and metal roofing and window replacement in Building 2 at 2600 General Meyer Avenue. Key clarifications include the deletion of carpet squares from the scope of work, confirmation that no unit prices apply to the project, clarification that the General Contractor is responsible for providing informational submittals and removing/moving/storing items within the buildings, and confirmation that fabricators and installers must be AISC certified. The addendum specifies that tapered ISO insulation shall be 3/16" per foot, deletes the Kawneer Trifab 451T storefront system from specifications (only IR 521T applies), requires Medium Stile doors with thermal breaks, and directs bidders to follow wind pressure requirements from the Components and Cladding Chart on the structural page rather than those in the specification section.

The addendum further clarifies that glass specifications shall utilize clear glass with Solarban 67 Low E coating on the #2 surface of insulating laminated units as the industry standard, eliminating confusion regarding multiple coating options and tinted glass alternatives. These clarifications supersede conflicting language in the original specifications and are now integral to the contract documents. The addendum was distributed to all plan holders of record via email, ensuring all bidders have consistent information for bid preparation prior to the September 16, 2026 bid deadline.

View the file

Other files

File Type Posted
40006-R0031505-2.pdf PDF
40006-R0031505-1.pdf PDF
40006-R0031505.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page-1

ADDENDUM NO. 3

TO THE BID DOCUMENTS FOR:

DELGADO COMMUNITY COLLEGE

WESTBANK, BUILDING 1 AND 2

ROOFING AND WINDOW WIND MITIGATION

2600 GENERAL MEYER AVE.

NEW ORLEANS, LOUISIANA 70119

PROJECT NO. 40006-R0031505

September 10, 2026

I. Scope:

1. Addendum No. 3 is issued in accordance with the provisions of the general specifications for the referenced project and is now considered to be an integral part of those original plans, specifications and contract documents.

2. ADDENDUM NO. 3 has been issued and shall also be posted and distributed by e-mail to Plan Holders of Record.

This addendum contains the following items:

Clarifications to Specifications.

II. Clarifications to the Specifications:

Section 011000 -

1.8 OWNER-FURNISHED PRODUCTS B. 1. Carpet Squares: Delete Spec Section 011000 1.8 B. 1.

There are no carpet squares in the scope of work.

Section 012200 - A schedule of unit prices is listed; however, there is no unit price form. Are there unit prices on this project? Delete Spec Section 012200, there are no unit prices in the job.

Section 015000 - Who is responsible for providing the informational submittals? The General Contractor. These are not items the contractor would have access to; will they be supplied to us? No, items such as the layout area, temporary offices and storage shed locations etc. are items the GC will have. Are the temporary office, its contents, and storage and fabrication sheds required for this project? No

Section 024119 - Is the owner or the contractor responsible for removing, moving, and storing any items in the buildings for the completion of scope of work? 1.9 B1 Contractor is responsible.

Section 051200 - Does the fabricator and installer need to be AISC Certified, or can they just adhere to their quality standards?

Yes, certified per the specification section.

Section 075500 - Is the new tapered Iso to be 3/16" per foot? It is usually 1/8" or 1/4", just wanted to clarify.

ADDENDUM NO. 002

DELGADO COMMUNITY COLLEGE

Page-2

Yes, 3/16 as shown.

Specification 084113- Both Kawneer Trifab 451T an IR 521T storefront systems are listed in the specification yet details in the drawings show only IR521T profiles. Please confirm if 451T is applicable to the project and if so, please confirm locations.

Delete the spec for Trifab 451T, it is not in the project.

Please confirm door stile and thermal requirements. (e.g., 350 Medium Stile vs. 500 Wide Stile; Non- Thermal vs. Thermal) Medium Stile with Thermal break.

Wind pressures noted in the specification differ from those provided on the Components and Cladding Chart in the Structural General Notes. Please confirm which are to be followed. Use the Components and Cladding Chart requirements on the structural page. Delete the pressure noted in the specification.

Specification 088000- Specified glass type GL-1 references multiple Low E Coatings and coating locations. Please confirm coating required and if the industry standard location on the #2 surface of the insulating laminated unit is acceptable. Please also confirm if the intent is for Clear or Atlantica tinted glass. Clear glass with Solarban 67 Low E on the #2 surface is acceptable.